ANTIGO LAKE DISTRICT: Antigo Lakes AIS Control & Prevention Project: Phase 1 2013-2016
The Antigo Lakes Inland Lakes Protection & Rehabilitation District is sponsoring a project which focuses on the control and monitoring of the Curly-leaf Pondweed (CLP) infestation within Antigo Lake. Treatment strategies will be implemented over the next two years.
The project includes the following goals: 1) Pretreatment confirmation and refinement Survey (Spring 2013, 2014); 2) Quantitative CLP Monitoring (sub-sample PI survey)(Summer 2013, 2014); 3) Early season AIS survey (2013, 2014); 4) Pre/Post evaluation monitoring (2013, 2014); 5) Treatment letter report and future treatment planning (2013, 2014); 5) Informational meeting (winter 2014).
Project deliverables include: 1) A final report will be completed discussing the results of the surveys and recommended treatment strategies for 2014; 2) Antigo Lake Aquatic Plant Management Plan update.
Specific conditions for this Project: 1) The WDNR will be provided electronic and hard copies of all data and or reports/plans generated as a result of this project; 2) Make sure lake association members are informed about this project; 3) Provide hard copy of point intercept data in proper spreadsheet format.
Project Type
|
AIS_GRANT
-
Aquatic Invasives Education
|
Project ID
|
AEPP-400-13
|
Year Started
|
2013
|
Status
|
COMPLETE
|
Activities
- Monitor Pre and Post Treatment
- Aquatic Plant Management Plan
- Aquatic Plant Monitoring or Survey
- Informational Meetings
- Monitor Invasive Species
People/Organizations Involved
-
Antigo Inland Lake P & R District