2023-11-22
|
-
|
Maps
|
|
LARGE MAPS
|
|
2023-11-10
|
-
|
Site-specific Correspondence
|
|
|
|
2023-11-10
|
-
|
Photos
|
|
SITE PICTURES
|
|
2014-05-30
|
185
|
Continuing Obligation(s) Compliance Audit Complete
|
|
|
|
2002-09-20
|
11
|
Activity Closed
|
|
|
|
2002-09-20
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2002-09-20
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2002-09-20
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
|
|
2002-09-20
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
|
|
2002-09-20
|
46
|
Impacted Right-of-Way (ROW) Notification
|
|
AUTO-POPULATED 2018-03-20
|
|
2002-09-20
|
730
|
CO Packet created for Recorded Groundwater Use Restriction
|
|
AUTO-POPULATED
|
|
2002-06-25
|
97
|
Technical Assistance Request Received (fee)
|
|
NR 718 EXEMPTION
|
|
2002-06-25
|
98
|
Technical Assistance Provided
|
|
NR 718 EXEMPTION
|
|
2002-06-19
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
2000-05-02
|
84
|
Remaining Actions Needed
|
|
|
|
2000-05-02
|
52
|
Deed Restriction for Residual Soil Contamination Recorded
|
|
|
|
2000-01-14
|
79
|
Case Closure Review Request Received
|
|
|
|
1998-07-06
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
1998-06-04
|
41
|
Remedial Action Report Received
|
|
|
|
1998-06-04
|
99
|
Miscellaneous
|
|
EXCAVATION REPORT
|
|
1996-11-05
|
43
|
Site Activity Status Update Received
|
|
|
|
1996-11-05
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
1993-12-12
|
206
|
Site Investigation End - State Lead
|
|
|
|
1993-09-20
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
1993-08-14
|
43
|
Site Activity Status Update Received
|
|
QRTLY/MTHLY STATUS RPT
|
|
1993-08-09
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SI REPORT RECV'D
|
|
1993-08-09
|
43
|
Site Activity Status Update Received
|
|
GW REPORT
|
|
1993-08-09
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE
|
|
1993-02-19
|
205
|
Site Investigation Start - State Lead
|
|
|
|
1993-01-14
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
SI WORK PLAN RECV'D
|
|
1992-03-23
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
1992-01-01
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
1990-10-15
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
1989-12-11
|
33
|
Tank System Site Assessment (TSSA) Report Received
|
|
|
|
1989-11-10
|
2
|
Responsible Party (RP) letter sent
|
|
RP LETTER
|
|
1989-11-08
|
1
|
Notification of Hazardous Substance Discharge
|
|
|