2016-07-20
|
185
|
Continuing Obligation(s) Compliance Audit Complete
|
|
|
|
2007-02-14
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2007-02-14
|
11
|
Activity Closed
|
|
GW WELLS NOT ABANDONED, FURHTER MONITORING FOR ERP ACT 02-41-263675
|
|
2007-02-14
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
*** AUTO POPULATED AT FINAL CLOSURE DUE TO 700 ACTION ***
|
|
2007-02-14
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
*** AUTO POPULATED AT FINAL CLOSURE DUE TO 710 ACTION ***
|
|
2007-02-14
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2007-02-14
|
224
|
Continuing Obligation - Structural Impediment to Cleanup
|
|
|
|
2007-01-22
|
80
|
Closure Not Recommended
|
|
LTR SENT
|
|
2006-10-11
|
79
|
Case Closure Review Request Received
|
|
REC'D CK# 7649 $750.00 REC'D GIS & SOIL PKT GIVEN TO BG 10/13/06 COMPLETE 10/16/2006
|
|
2006-10-11
|
700
|
Database Fee Paid for Groundwater Continuing Obligation(s)
|
|
REC'D CK# 7649 $250.00
|
|
2006-10-11
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
REC'D CK# 7649 $200.00
|
|
2005-10-03
|
43
|
Site Activity Status Update Received
|
|
ANNUAL GW RPT
|
|
2004-08-17
|
43
|
Site Activity Status Update Received
|
|
ANNUAL REPORT
|
|
2003-07-01
|
43
|
Site Activity Status Update Received
|
|
COMMERCE APPROVAL OF RA FUNDING BID WAIVER LTR
|
|
2003-06-24
|
99
|
Miscellaneous
|
|
REC'D BID WAIVER REQUEST LTR.
|
|
2003-06-12
|
43
|
Site Activity Status Update Received
|
|
REC'D MONITORED NATURAL ATTENUATION ADDENDUM TO REM. ACT OPT RPT NOTED 6/13/03
|
|
2003-06-05
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
JH
|
|
2003-05-20
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
JH ADDENDUM #1
|
|
2003-04-23
|
43
|
Site Activity Status Update Received
|
|
MNA ADDENDUM TO RAP EVALUATION NOTED JH 5/5/03
|
|
2003-03-11
|
43
|
Site Activity Status Update Received
|
|
JH COMMERCE APPROVAL OF COST SEPARATION METHOD
|
|
2003-01-27
|
99
|
Miscellaneous
|
|
JH. ADDITIONAL INFO INCREASE SITE INVEST CAO
|
|
2003-01-22
|
99
|
Miscellaneous
|
|
JH.RECPD PROPOSED PECFA APPORTTION PLAN
|
|
2003-01-15
|
99
|
Miscellaneous
|
|
JH.PECFA PKG TRANSMITTAL & REQT FOR SITE INV. CAP INCREASE
|
|
2002-10-07
|
99
|
Miscellaneous
|
|
JH. RECVD BID WAVIER REQUEST
|
|
2002-09-04
|
99
|
Miscellaneous
|
|
REC'D ADD'L INF SI LETTER DATED 09-12-02
|
|
2002-05-23
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
JH Phase II SI Rpt Adden #1 recvd JH Picked up 6/18/02
|
|
2002-04-10
|
99
|
Miscellaneous
|
|
EA - denied request to exclude NA as a remedy
|
|
2002-03-22
|
99
|
Miscellaneous
|
|
EA - rec'd addendum to RAP - request to exclude NA as a remedial option
|
|
2002-03-08
|
42
|
Remedial Action Report Approved
|
|
EA - approved phased RAP for part of the petroleum contamination
|
|
2002-02-04
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
EA
|
|
2002-01-14
|
99
|
Miscellaneous
|
|
EA - approved interim action to address petroleum impact before non-petroleum impact.
|
|
2001-12-28
|
99
|
Miscellaneous
|
|
EA - Finalized Site Investigation Report received
|
|
2001-12-28
|
38
|
Site Investigation Report (SIR) Approved
|
|
EA
|
|
2001-11-23
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
EA - received check $750 - Preliminary SI and Technical Meeting; check #2062
|
|
2001-07-24
|
89
|
DSPS (formerly Commerce) Transferred Back to DNR
|
|
|
|
2000-06-01
|
76
|
Activity Transferred to DSPS (formerly Commerce)
|
|
|
|
1995-04-04
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SI REPORT RECV'D
|
|
1995-04-04
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
1990-06-27
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
1990-06-08
|
1
|
Notification of Hazardous Substance Discharge
|
|
|