2020-12-07
|
83
|
No Further Action Required per NR 708.09
|
|
NFA VIA REVIEW OF 7/29/2019 AC 43 REPORT
|
|
2020-12-07
|
11
|
Activity Closed
|
|
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-10
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-01-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2019-07-29
|
43
|
Site Activity Status Update Received
|
|
PECFA WORK SCOPE LETTER REPORT (LUST CASE) & NFA REQUEST (ERP CASE). NO FEE YET.
|
|
2019-07-10
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-07-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-01-16
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2017-10-02
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2017-07-17
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2017 - 6/30/2017
|
|
2017-01-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2016-07-15
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2016 - 6/30/2016
|
|
2016-05-12
|
99
|
Miscellaneous
|
|
FILE REVIEW CONDUCTED BY CONSULTANT
|
|
2016-01-13
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2015 - 12/31/2015
|
|
2015-09-22
|
99
|
Miscellaneous
|
|
PECFA LETTER SENT IN ERROR
|
|
2015-07-09
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2015 - 6/30/2015
|
|
2014-06-24
|
200
|
Push Action Taken
|
|
SENT LETTER REQUESTING SITE UPDATE
|
|
2012-01-10
|
200
|
Push Action Taken
|
|
|
|
2011-09-07
|
130
|
DNR Regulatory Reminder Sent
|
|
Vapor Intrusion (VI) Assessment Notification Ltr Sent
|
|
2010-08-24
|
99
|
Miscellaneous
|
|
MEETING WITH OWNER, LOCATING DOC & POSSIBLE SALE OF PROPERTY
|
|
2010-07-23
|
200
|
Push Action Taken
|
|
|
|
2001-11-13
|
99
|
Miscellaneous
|
|
REQUEST 30 DAY EXTENSION TO COMPLETE PHASE II ASSESS,
|
|
2001-11-13
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
2001-10-22
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2001-10-11
|
1
|
Notification of Hazardous Substance Discharge
|
|
|