ACTIVITY DETAILS

 
02-37-315888 MURRAY MACHINERY LF
Activity Type / Status Jurisdiction
ERP  CLOSED DNR WMM
Location Name County DNR Region
MURRAY MACHINERY INC (FORMER) MARATHON WEST CNTRL
Address Municipality
901 S 60TH AVE WAUSAU
PLSS Description Latitude (WGS84) Longitude (WGS84) Google Maps RR Sites Map
NW 1/4 of the SW 1/4 of Sec 32, T29N, R07E 44.9484693 -89.7082843 Click to view on Google Maps using Lat/Long Click to View RR Sites Map
Additional Activity Details Acres
UNKNOWN
Facility ID PECFA No. EPA ID Start Date End Date
737062920 1972-10-16 2003-10-02
Characteristics
Above Ground
Petrol Tank

Drycleaner
EPA
NPL Site
EPA
Superfund
PECFA Funds
Eligible

PFAS

ROW Impact

Sediments
Underground
Petrol Tank
WI DOT
Site
 
Actions and Document
Date Code Name File Comment
2003-10-02 400 Transferred to DNR WMM Program
2003-10-02 11 Activity Closed R&R PROJECT COMPLETE.
2003-10-02 99 Miscellaneous Download PDF file SUMMARY OF ALL MURRAY MACHINERY SITES
2002-11-19 43 Site Activity Status Update Received GROUNDWATER MONITORING RESULTS SUBMITTED
2002-10-23 43 Site Activity Status Update Received GROUNDWATER MONITORING RESULTS SUBMITTED
1999-12-15 27 Long Term Monitoring Plan Approved
1999-09-24 40 Remedial Action Options Report (RAOR) Approved REMEDIAL ACTION OPTIONS REPORT APPROVED
1998-01-09 151 Remedial Action (RA) Documentation Report Received (non-fee) CONSTRUCTION DOCUMENTATION REPORT FOR CAPPING OF TREATED SEDIMENT
1997-11-01 620 DNR BEAP Assessment Completed
1996-12-20 99 Miscellaneous PHASE 1 ENVIRONMENTAL ASSESSMENT REPORT
1996-11-25 151 Remedial Action (RA) Documentation Report Received (non-fee) CONSTRUCTION DOCUMENTATION REPORT FOR CAPPING OF TREATED SEDIMENT
1996-08-14 99 Miscellaneous EPA TIME-CRITICAL REMOVAL ACTIONS COMPLETE
1994-10-12 99 Miscellaneous EPA TIME-CRITICAL REMOVAL ACTIONS BEGIN
1994-10-03 99 Miscellaneous ARARS
1994-07-29 351 Superfund Site Assessment Site Inspection (SI)
1994-07-29 355 Superfund No Further Remedial Action Planned (NFRAP) FROM SUPERFUND DATABASE
1994-07-06 99 Miscellaneous PROPERTY ASSESSMENT (PA) AND SITE SCREENING
1993-09-29 350 Superfund Site Assessment Preliminary Assessment (PA)
1993-02-02 59 Environmental Enforcement Action Completed ENFORCEMENT END. FINAL JUDGEMENT AGAINST MURRAY MACHINERY, INC.
1991-10-18 99 Miscellaneous DECISION, JUDICIAL REVIEW OF CLOSURE ORDER
1990-10-31 21 Contested Case Hearing Held
1990-10-10 99 Miscellaneous CONDITIONAL CLOSURE PLAN MODIFICATION
1990-01-09 23 Referral to Department of Justice (DOJ)
1983-11-23 99 Miscellaneous VERTICAL FILL PLAN APPROVED
1983-07-19 99 Miscellaneous SITE CONSTRUCTION DOCUMENTATION DENIAL, VERTICAL FILLING PLAN
1982-08-19 99 Miscellaneous GROUNDWATER MONITORING REQUIREMENTS MODIFIED
1980-11-19 99 Miscellaneous DEPARTMENT INSPECTION NOTED OPERATION VIOLATIONS
1975-04-09 99 Miscellaneous DEPARTMENT ISSUED ORDER ON NON-COMPLIANCE REGARDING SITE OPERATION AND MONITORING
1974-08-08 99 Miscellaneous GROUNDWATER MONITORING REQUIREMENTS ESTABLISHED
1972-10-16 1 Notification of Hazardous Substance Discharge
1972-10-16 99 Miscellaneous INITIAL SITE INSPECTION
1972-03-02 99 Miscellaneous INITIAL LANDFILL APPROVAL ISSUED BY THE DEPARTMENT

Jurisdictional Agency:  WI DNR WASTE & MATERIALS MANAGEMENT 101 S WEBSTER ST PO BOX 7921 MADISON, WI 53707-7921