ACTIVITY DETAILS

 
02-49-000037 ELECTROCRAFT CORP/THOMPSON MACHINE
Activity Type / Status Jurisdiction
ERP  OPEN DNR RR
Location Name County DNR Region
ELECTRO-CRAFT CORP/THOMPSON MACHINE POLK NORTHERN
Address Municipality
705 S KELLER AVE AMERY
PLSS Description Latitude (WGS84) Longitude (WGS84) Google Maps RR Sites Map
NW 1/4 of the SW 1/4 of Sec 33, T33N, R16W 45.3003757 -92.3645972 Click to view on Google Maps using Lat/Long Click to View RR Sites Map
Additional Activity Details Acres
6
Facility ID PECFA No. EPA ID Start Date End Date
649013420 WIN000507965 1986-11-01
Characteristics
Above Ground
Petrol Tank

Drycleaner
EPA
NPL Site
EPA
Superfund
PECFA Funds
Eligible

PFAS

ROW Impact

Sediments
Underground
Petrol Tank
WI DOT
Site
 
Actions and Documents
Date Code Name File Comment
2021-04-06 130 DNR Regulatory Reminder Sent Download PDF file VAPOR INTRUSION AND TCE REMINDER LETTER
2020-08-17 130 DNR Regulatory Reminder Sent Download PDF file EMERGING CONTAMINANTS REMINDER LETTER
2020-01-08 315 Superfund Site Assessment Transmittal Memos TRANSMITTAL MEMO
2020-01-08 350 Superfund Site Assessment Preliminary Assessment (PA) Download PDF file PRELIMINARY ASSESSMENT
2018-07-26 313 Superfund Site Assessment Pre-CERCLA Screening (PCS) Download PDF file PRE CERCLIS SCREENING
2018-07-16 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2018 - 6/30/2018
2018-01-03 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2017 - 12/31/2017
2017-07-14 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2017 - 6/30/2017
2017-06-09 99 Miscellaneous EMAIL TO RP IN RESPONSE TO LETTER
2017-05-26 99 Miscellaneous REC'D LETTER FROM RP
2017-05-16 99 Miscellaneous RESPONSE LETTER FROM PROPERTY OWNER REC'D - FROM 4/26/17 RP LETTER
2017-04-26 2 Responsible Party (RP) letter sent Download PDF file
2017-04-12 99 Miscellaneous CALL W/ PROPERTY OWNER TO DISCUSS SITE
2017-01-12 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2016 - 12/31/2016
2016-10-21 99 Miscellaneous EMAIL FROM CONSULTANT & SITE REP RE: WORK ON-HOLD DUE TO LACK OF FUNDING
2016-08-23 99 Miscellaneous CALL WITH CONSULTANT AND SITE REP TO DISCUSS SITE
2016-07-22 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2016 - 6/30/2016
2016-05-26 99 Miscellaneous REQUEST ADDT'L INFO
2016-03-21 43 Site Activity Status Update Received Download PDF file GW MONITORING RPT REC'D
2016-02-11 99 Miscellaneous EMAIL TO CONSULTANT THAT 1/22/16 PROGRESS RPT IS WRONG, SITE IS NOT CONDITIONALLY CLOSED.
2016-01-22 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2015 - 12/31/2015
2015-07-27 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2015 - 6/30/2015
2014-12-23 99 Miscellaneous CALL WITH CONSULTANT TO DISCUSS SITE
2014-06-10 99 Miscellaneous EMAIL TO CONSULTANT DISCUSSING FUTURE SAMPLING
2014-05-30 99 Miscellaneous EMAIL REC'D DISCUSSING PROPOSED SAMPLE LOCATIONS
2014-02-18 99 Miscellaneous MEETING WITH CONSULTANT & BANK TO DISCUSS SITE
2014-02-03 43 Site Activity Status Update Received STATUS RPT REC'D
2013-10-03 200 Push Action Taken CALL WITH CONSULTANT TO DISCUSS SITE
2012-09-17 99 Miscellaneous EMAIL FROM CONSULTANT; GW SAMPLING IS ONGOING
2012-09-14 200 Push Action Taken EMAIL SENT TO CONSULTANT REQUESTING STATUS UPDATE
2011-01-20 98 Technical Assistance Provided LETTER SENT.
2011-01-07 97 Technical Assistance Request Received (fee) $500 SHORT ELLIOTT HENDRICKSON INC CHECK # 324797 RECD.
2011-01-07 43 Site Activity Status Update Received STATUS REPORT RECEIVED.
2010-10-14 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) CALL TO CONSULTANT; PROCEED WITH WORK PLAN SCOPE OF WORK.
2010-10-12 38 Site Investigation Report (SIR) Approved VAPOR INTRUSION WORKPLAN RECD
2010-04-23 99 Miscellaneous MEET WITH BANK TO DISCUSS SITE.
2009-05-11 99 Miscellaneous EMAIL TO RP RE: QUESTIONS ABOUT SITE.
2009-05-05 99 Miscellaneous EMAIL FROM RP, QUESTIONS ABOUT SITE.
2008-10-14 99 Miscellaneous STATUS UPDATE REQUEST SENT TO RP FROM ENVIRONMENTAL ENFORCEMENT STAFF
2008-10-09 99 Miscellaneous CALL FROM CONSULTANT - RP HAS NOT GIVEN AUTH TO PROCEED
2008-10-06 99 Miscellaneous EMIAL TO RP AND CONSULTANT REQUESTING STATUS UPDATE
2008-06-11 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
2008-06-10 35 Site Investigation Workplan (SIWP) Received (non-fee) SUPPLEMENTAL WP RECVD
2008-06-04 99 Miscellaneous PHONE CALL WITH RP TO DISCUSS SITE
2008-03-14 35 Site Investigation Workplan (SIWP) Received (non-fee)
2008-03-14 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) EMAIL TO CONSULTANT AND RP
2008-02-25 99 Miscellaneous CONFERENCE CALL WITH RP AND CONSULTANT
2008-01-25 99 Miscellaneous CONFERENCE CALL WITH OWNER AND CONSULTANT
2008-01-16 99 Miscellaneous 8EMAIL RESPONSE TO RP.
2008-01-15 99 Miscellaneous EMAIL FROM RP DISCUSSING PROPOSAL & REQUESTING PHONE DISCUSSION.
2008-01-11 99 Miscellaneous ENFORCEMENT CONFERENCE SUMMARY LETTER SENT TO RP.
2007-12-20 4 Enforcement Conference Held
2007-11-29 14 Notice of Violation (NOV) Issued
2007-09-17 3 Notice of Noncompliance (NON) Issued LETTER SENT TO RP
2007-08-14 99 Miscellaneous EMAIL TO RP REQUESTING STATUS UPDATE.
2007-04-12 99 Miscellaneous E-MAIL FROM RP DISCUSSING STATUS OF SITE
2007-03-26 99 Miscellaneous E-MAIL TO RP REQUESTING STATUS UPDATE
2006-12-15 99 Miscellaneous E-MAIL FROM RP DISCUSSING STATUS OF SITE
2006-12-08 99 Miscellaneous MET WITH RP TO DISCUSS SITE
2006-10-09 200 Push Action Taken LETTER SENT
2005-06-15 99 Miscellaneous EMAIL TO RP REQUESTING STATUS UPDATE.
2004-05-14 99 Miscellaneous GREEN TEAM MEETING
2004-02-24 2 Responsible Party (RP) letter sent
2004-02-19 99 Miscellaneous MEET WITH PROPERTY OWNER AT SITE.
2004-01-29 206 Site Investigation End - State Lead
2003-12-23 37 Site Investigation Report (SIR) Received (non-fee)
2003-12-01 43 Site Activity Status Update Received
2003-11-03 43 Site Activity Status Update Received
2003-09-02 43 Site Activity Status Update Received
2003-05-15 43 Site Activity Status Update Received
2003-01-30 43 Site Activity Status Update Received
2002-04-24 35 Site Investigation Workplan (SIWP) Received (non-fee)
2002-03-20 205 Site Investigation Start - State Lead
2002-03-20 13 Activity Reopened
2001-09-14 99 Miscellaneous SALE PENDING. REF TO BRF POSS GLC LETTER
1988-02-15 12 Activity Previous Case Closure Date Download PDF file
1987-11-16 84 Remaining Actions Needed
1987-01-01 206 Site Investigation End - State Lead FIELD INVEST P1 FOR VOC & METALS
1986-11-01 1 Notification of Hazardous Substance Discharge
1986-11-01 205 Site Investigation Start - State Lead FIELD INVEST P1 FOR VOC & METALS
Substances
Substance Type Amt Released Units
Trichloroethylene Industrial Chem
Responsible Party
THOMAS GIEBEL 1544 RIVERCREST RD N, LAKELAND, MN 55043
DNR Project Manager
PHIL RICHARD  philip.richard@wisconsin.gov
32873 | 02-49-000037