02-05-552220
TIDY CLEANERS & LAUNDRY
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
TIDY LAUNDRY CLEANERS INC | BROWN | NORTHEAST |
Address | Municipality |
---|---|
818 S BROADWAY | GREEN BAY |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the SW 1/4 of Sec 36, T24N, R20E | 44.5089893 | -88.0264532 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
405009220 | 2008-08-27 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-04-22 | 213 | DERF - Interim Action Workplan Received |
![]() |
DERF OCST APPROVAL REQUEST FOR INSTALLING A VMS AT THE ON-SITE BUILDING; HIRING A RADON MITIGATOR | |
2024-04-22 | 214 | DERF - Interim Action Workplan Approved |
![]() |
DNR APPROVES THE COSTS ASSOCIATED WITH VMS INSTALL. | |
2024-02-14 | 99 | Miscellaneous |
![]() |
PHONE CALL FOLLOW-UP FOR FUTURE VMS INSTALL; VMS WOULD NOT BE CONSIDERED AN SVE FOR RA | |
2024-01-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-12-14 | 364 | VAL and/or VRSL Exceeded | |||
2023-07-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-06-22 | 99 | Miscellaneous |
![]() |
AFFORDABLE HOUSING REDEVELOPMENT NEXT DOOR REQUIRES A VAPOR INVESTIGATION | |
2023-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2022-10-10 | 99 | Miscellaneous |
![]() |
DNR RESPONSE THAT GW NEEDS TO BE FURTHER DELINEATED & AN RA IS NEEDED TO ADDRESS SOURCE OF VAPORS | |
2022-09-01 | 43 | Site Activity Status Update Received |
![]() |
FEBRUARY 2022 GW SAMPLING RESULTS, SUB-SLAB AND SANITARY VAPOR SAMPLING RESULTS | |
2022-07-05 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-02-09 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
SIWP FOR SANITARY SEWER VAPOR SAMPLING & ADDITIONAL SUB-SLAB SAMPLING ON-SITE | |
2022-02-09 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | SEE AC 35 DATED 2/9/2022 FOR VAPOR SAMPLING NTP | ||
2022-01-11 | 99 | Miscellaneous |
![]() |
DNR REQUIRING VAPOR MITIGATION, ADDITIONAL VAPOR SAMPLING & SANITARY VAPOR INVESTIGATION | |
2022-01-04 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2021-12-15 | 43 | Site Activity Status Update Received |
![]() |
SEPT 2021 GROUNDWATER MONITORING & SUB-SLAB VAPOR SAMPLING RESULTS | |
2021-09-09 | 99 | Miscellaneous |
![]() |
DERP CHANGE ORDER #4 APPROVED | |
2021-09-09 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
NOTICE TO PROCEED WITH DNR COMMENTS | |
2021-08-30 | 118 | PFAS Sampling Not Required At This Time |
![]() |
||
2021-08-23 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
SUPPLEMENTAL SITE INVESTIGATION WORKPLAN FOR ADDITIONAL VAPOR SAMPLING & GROUNDWATER MONITORING | |
2021-08-23 | 112 | DERF - Change Order Received | CHANGE ORDER #4; SEE AC 35 OF SAME DATE FOR DOCUMENTATION | ||
2021-08-23 | 114 | PFAS Scoping Statement Received | SEE AC 35 DATED 8/23/2021 FOR DOCUMENTATION | ||
2021-07-22 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO VAPOR SAMPLING RESULTS; RECOMMEND ADDITIONAL PORTS NEAR DRY CLEANING MACHINE | |
2021-07-19 | 43 | Site Activity Status Update Received |
![]() |
STATUS UPDATE WITH SUB-SLAB VAPOR SAMPLING; PCE ABOVE RESIDENTIAL VRSLS BUT NOT COMMERCIAL VRSLS | |
2021-07-13 | 99 | Miscellaneous |
![]() |
IN LIEU OF DNR 2019 REQUEST TO SAMPLE PFAS, DNR IS REQUESTING AN UPDATED PFAS SCOPING BE SUBMITTED | |
2021-07-08 | 99 | Miscellaneous |
![]() |
DNR REQUESTING SIWP SUBMITTAL FOR VAPOR SAMPLING AFTER PHONE CONVERSATION WITH CONSULTANT | |
2021-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2020-10-27 | 130 | DNR Regulatory Reminder Sent |
![]() |
DERF FUNDING STATUS LTR | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-03-18 | 36 | Site Investigation Workplan (SIWP) Approved |
![]() |
PFAS GW SAMPLING SIWP APPROVED | |
2020-03-04 | 135 | Site Investigation Workplan (SIWP) Received (fee) |
![]() |
SIWP FOR PFAS SAMPLING IN GROUNDWATER | |
2020-01-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2019-10-30 | 99 | Miscellaneous |
![]() |
REQUEST FOR PFAS SIWP FOR GW SAMPLING | |
2019-10-30 | 116 | PFAS Sampling Required | PFAS SAMPLING WORKPLAN REQUEST DUE: 01/03/2020 | ||
2019-09-03 | 43 | Site Activity Status Update Received |
![]() |
MAY 2019 SOIL SAMPLING & JUNE 2019 GROUNDWATER SAMPLING RESULTS | |
2019-07-09 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-03-01 | 43 | Site Activity Status Update Received |
![]() |
PROPOSED MW & BORING LOCATIONS | |
2019-02-25 | 99 | Miscellaneous |
![]() |
CHANGE IN PROJECT MANAGER (SCHULTZ) | |
2019-02-08 | 99 | Miscellaneous |
![]() |
APPROVAL OF CHANGE ORDERS #2 & #3 | |
2019-01-27 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2018 - 12/31/2018 | |
2019-01-24 | 112 | DERF - Change Order Received |
![]() |
||
2018-07-16 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2018 - 6/30/2018 | |
2018-01-26 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2017 - 12/31/2017 | |
2018-01-04 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
DNR COMMENTS REGARDING PROPOSED SI WORKPLAN | |
2017-09-20 | 99 | Miscellaneous | STATUS OF PROPOSED FIELD WORK | ||
2017-09-20 | 43 | Site Activity Status Update Received |
![]() |
FIELD WORK ON HOLD UNTIL DNR PRESENTS EXISTING SI DATA TO THE CLOSURE COMMITTEE FOR INPUT | |
2017-08-30 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2017 STATUS REPORT | |
2017-08-25 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER ANALYTICAL DATA | |
2017-07-28 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2017 - 6/30/2017 | |
2017-06-27 | 99 | Miscellaneous |
![]() |
REQUEST TO COLLECT A ROUND OF GROUNDWATER SAMPLES | |
2017-06-27 | 43 | Site Activity Status Update Received |
![]() |
SUMMARY OF 06/27/2017 PHONE CONVERSATION W/DNR | |
2017-06-13 | 43 | Site Activity Status Update Received |
![]() |
PROPOSAL FOR MOVING FORWARD W/PREVIOUSLY APPROVED SCOPE OF WORK | |
2017-06-08 | 99 | Miscellaneous |
![]() |
DNR REQUEST FOR COPY OF SIGNED PROPOSAL & PROPOSED WORK START DATE | |
2017-05-10 | 43 | Site Activity Status Update Received |
![]() |
REVISED PROPOSAL FOR ADDT'L SITE INVESTIGATION ACTIVITYES | |
2017-04-25 | 99 | Miscellaneous |
![]() |
PHONE CONVERSATION | |
2017-01-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2016 - 12/31/2016 | |
2016-07-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2016 - 6/30/2016 | |
2016-02-03 | 99 | Miscellaneous | REQUEST FOR CASE STATUS UPDATE | ||
2016-02-03 | 43 | Site Activity Status Update Received | CONSULTANT WILL CONTACT RP FOR A STATUS UPDATE & RESPOND TO DNR | ||
2016-02-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2015 - 12/31/2015 | |
2015-08-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-01-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-09-24 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-07-15 | 99 | Miscellaneous | REQUEST FOR CASE STATUS UPDATE | ||
2014-01-30 | 130 | DNR Regulatory Reminder Sent | DERF FUNDING STATUS LTR | ||
2013-05-23 | 218 | DERF - Cost Reimbursement Application Approved | DERF PAYMENT ISSUED $8251.50. | ||
2013-02-15 | 217 | DERF - Cost Reimbursement Application Received | |||
2012-10-04 | 99 | Miscellaneous | SI CHANGE ORDER #1 APPROVED | ||
2012-10-01 | 112 | DERF - Change Order Received | SI CHANGE ORDER #1 | ||
2012-06-07 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | DRAFT WORK PLAN - NOT SUBMITTED TO CLIENT/RP | ||
2011-10-24 | 99 | Miscellaneous | DNR OK WITH WAITING FOR SECOND ROUND OF GW DATA BEFORE CONDUCTING ADDITIONAL SI ACTIVITIES | ||
2011-09-28 | 99 | Miscellaneous | ADDITIONAL SI ACTIVITIES NEEDED. SUBMIT A WORKPLAN | ||
2011-09-27 | 43 | Site Activity Status Update Received | SOIL ANALYTICAL DATA AND 1ST ROUND OF GROUNDWATER ANALYTICAL DATA AVAILABLE | ||
2011-09-08 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2011-05-05 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | |||
2011-04-26 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | |||
2011-03-17 | 99 | Miscellaneous | REQUEST FOR CASE STATUS UPDATE | ||
2010-11-29 | 99 | Miscellaneous | APPROVAL TO HIRE ALPHA TERRA SCIENCE AS SI CONSULTANT | ||
2010-08-30 | 113 | DERF - Bid Review Request Received | |||
2010-06-17 | 43 | Site Activity Status Update Received | RP INTENDS TO PURSUE NEW SI BIDS | ||
2010-05-19 | 43 | Site Activity Status Update Received | CONSULTANT TERMINATED SITE INVESTIGATION CONTRACT. RESPONSIBLE PARTY TO SEEK "ABILITY TO PAY" REVIEW | ||
2010-05-07 | 3 | Notice of Noncompliance (NON) Issued | |||
2010-03-03 | 99 | Miscellaneous | REQUEST FOR CASE STATUS UPDATE FROM CONSULTANT | ||
2009-02-04 | 99 | Miscellaneous | APPROVAL TO HIRE MMA | ||
2009-01-28 | 43 | Site Activity Status Update Received | RP REQUEST TO HIRE MMA AS SI CONSULTANT | ||
2009-01-15 | 43 | Site Activity Status Update Received | REVISED DERP SITE INVESTIGATION BID FROM MMA | ||
2009-01-02 | 43 | Site Activity Status Update Received | DERF SI BID SPREADSHEETS PROVIDED BY STS & MMA | ||
2008-11-30 | 43 | Site Activity Status Update Received | SITE INVESTIGATION BID DEADLINE | ||
2008-11-14 | 43 | Site Activity Status Update Received | END DATE TO SUBMIT DERP SI BIDS IS NOVEMBER 30TH. | ||
2008-10-13 | 43 | Site Activity Status Update Received | REQUEST FOR ASSISTANCE IN OBTAINING SITE INVESTIGATION DERP BIDS | ||
2008-09-10 | 110 | DERF - Potential Claim Form Approved | PCN RECIEVED 8/27/08, CONDITIONALLY APPROVED BUT NEEDS TO UPGRADE TO DIRECT-COUPLE PERC DELIVERY | ||
2008-08-29 | 2 | Responsible Party (RP) letter sent | |||
2008-08-27 | 1 | Notification of Hazardous Substance Discharge | SITE ASSESSMENT JULY 23, 2008 |
Substance | Type | Amt Released | Units |
---|---|---|---|
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
Category | Fiscal Year | Amount |
---|---|---|
DERF Reimbursements:Grant | 2013 | $8,252 |
JIM MOHR 818 S BROADWAY AVE, GREEN BAY, WI 54304 |
JOSIE SCHULTZ josie.schultz@wisconsin.gov |