02-20-554881
WI DOT TYNAN PROPERTY - LGU-SL
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / CLOSED | DNR RR |
Location Name | County | DNR Region |
---|---|---|
TYNAN PROPERTY | FOND DU LAC | NORTHEAST |
Address | Municipality |
---|---|
W998 STH 23 | FOREST TN |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the NE 1/4 of Sec 15, T15N, R19E | 43.7724816 | -88.20621 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
Electronic Only - No Hard File; WISDOT #: 1440-15-01; 1440-15-72 | UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
420143680 | 2010-01-20 | 2020-11-06 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Name | File |
---|---|
SITE FILE FOR YEARS 2010 THRU 2017 | ![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2020-11-06 | 11 | Activity Closed |
![]() |
||
2020-11-06 | 83 | No Further Action Required per NR 708.09 | |||
2020-11-04 | 118 | PFAS Sampling Not Required At This Time |
![]() |
||
2020-11-04 | 199 | Additional Information Received (Fee-Based or Closure) | |||
2020-11-03 | 114 | PFAS Scoping Statement Received |
![]() |
||
2020-10-30 | 99 | Miscellaneous |
![]() |
DNR REQUESTING NR 716 EMERGING CONTAMINANT SCOPING (VIA EMAIL) | |
2020-09-29 | 198 | Request for Additional Information (Fee-Based or Closure) | DNR REQUESTING NR 716 EMERGING CONTAMINANT SCOPING (VERBAL) | ||
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-08-11 | 183 | No Further Action per NR 708.09 Request (fee) |
![]() |
||
2020-07-24 | 99 | Miscellaneous |
![]() |
NFA WARRANTED. COUNTY MUST SUBMIT 708.09 REQUEST & FEE. | |
2020-07-08 | 43 | Site Activity Status Update Received |
![]() |
WI DOT PERFORMED AN EXCAVATION & TOOK CONFIRMATION SAMPLES | |
2020-06-30 | 99 | Miscellaneous |
![]() |
NEW DNR PROJECT MANAGER - JAMES, UPDATE RECEIVED | |
2020-02-21 | 43 | Site Activity Status Update Received |
![]() |
SCHEDULE OF EXCAVATION & SAMPLING EVENT | |
2019-10-16 | 99 | Miscellaneous |
![]() |
DNR CONCURRENCE | |
2019-10-11 | 43 | Site Activity Status Update Received |
![]() |
SPECIAL PROVISIONS RECVD | |
2019-09-04 | 43 | Site Activity Status Update Received |
![]() |
EXCAVATION MANAGEMENT PLAN | |
2019-07-03 | 43 | Site Activity Status Update Received |
![]() |
SOIL & GROUNDWATER ANALYTICAL RESULTS | |
2019-07-03 | 99 | Miscellaneous |
![]() |
NOTIFICATION OF ANALYTICAL RESULTS TO RP | |
2019-07-03 | 43 | Site Activity Status Update Received |
![]() |
TEMPRORARY WELL ABANDONMENT FORMS | |
2019-06-17 | 99 | Miscellaneous |
![]() |
TEMPORARY WELL CONSTRUCTION APPROVAL | |
2019-04-03 | 43 | Site Activity Status Update Received | SIGNED ACCESS AGREEMENTS | ||
2019-03-27 | 43 | Site Activity Status Update Received |
![]() |
SITE PICTURES, POTABLE WELL REMAINS IN PLACE ON SITE | |
2019-03-21 | 99 | Miscellaneous |
![]() |
REQUEST FOR PERMISSION TO ACCESS | |
2019-02-28 | 99 | Miscellaneous |
![]() |
02/28/2019 MEETING BETWEEN DNR, DOT & FOND DU LAC CNTY | |
2019-01-15 | 99 | Miscellaneous |
![]() |
CHANGE OF PM (KRUEGER) | |
2018-12-10 | 43 | Site Activity Status Update Received |
![]() |
FOND DU LAC COUNTY'S STANCE | |
2018-05-01 | 99 | Miscellaneous |
![]() |
NOTICE OF NEW PROJECT MANAGER - BEGLEY | |
2018-03-08 | 99 | Miscellaneous |
![]() |
INTERIM PM CHANGE - SCHMENK | |
2017-09-14 | 99 | Miscellaneous |
![]() |
CHANGE OF PROJECT MANAGER - NESTE | |
2017-09-14 | 43 | Site Activity Status Update Received | STATUS UPDATE FROM FDL COUNTY (VIA PHONE) | ||
2015-11-13 | 99 | Miscellaneous | FDL COUNTY WILL WAIT FOR THE COMPLETION OF DOT WORK ON STH 23 BEFORE MOVING FORWARD | ||
2015-10-05 | 611 | Local Government Unit (LGU) Liability Exemption Applies | |||
2015-08-19 | 59 | Environmental Enforcement Action Completed | |||
2015-08-10 | 99 | Miscellaneous | CHANGE OF PROJECT MANAGER NOTIFICATION TO SARAH FREDERICK | ||
2015-08-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-05-26 | 200 | Push Action Taken | LETTER REQUESTING LETTER FROM RP | ||
2015-04-23 | 99 | Miscellaneous | LETTER REQUESTING RP TO INITIATE SITE INVESTIGATION & DISPOSE OF DRUMMED SOIL | ||
2015-01-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-09-25 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-09-02 | 4 | Enforcement Conference Held | |||
2014-07-31 | 14 | Notice of Violation (NOV) Issued | |||
2013-10-15 | 43 | Site Activity Status Update Received | NOTICE OF NON-COMPLIANCE LETTER REFUSED & RETURNED TO DNR | ||
2013-10-09 | 99 | Miscellaneous | NOTICE OF NON-COMPLIANCE CERTIFIED LETTER SENT TO RP | ||
2013-07-18 | 99 | Miscellaneous | LETTER TO RP: RP DETERMINED ABLE TO PAY, PROCEED W/INVESTIGATION | ||
2013-05-14 | 99 | Miscellaneous | EMAIL TO RP REGARDING STATUS OF ABILITY TO PAY PAPERWORK | ||
2013-04-17 | 99 | Miscellaneous | CONTACTED RP: ABILITY TO PAY SUBMITTAL IS STILL INCOMPLETE VIA PHONE CALL | ||
2012-08-08 | 99 | Miscellaneous | SENT ABILITY TO PAY PAPERWORK TO RP | ||
2012-06-13 | 43 | Site Activity Status Update Received | EMAIL FROM CONSULTANT: RP HAS NOT YET INITIATED SITE INVESTIGATION | ||
2012-02-09 | 43 | Site Activity Status Update Received | RESPONSIBLE PARTY HAS OBTAINED COST ESTIMATE AND WILL INITIATE FIELD WORK IN SPRING | ||
2011-10-21 | 43 | Site Activity Status Update Received | RECEIVED EMAIL FROM CONSULTANT - RP IS OBTAINING COST ESTIMATE FOR WORK | ||
2011-09-19 | 43 | Site Activity Status Update Received | CALL FROM RP: RP WILL OBTAIN ESTIMATES FROM CONSULTANTS | ||
2011-09-08 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2011-08-03 | 43 | Site Activity Status Update Received | RECD WIS DOT TO RP WITHDRAWING ASSISTANCE IN INVESTIGATION AND CLEANUP | ||
2011-08-03 | 99 | Miscellaneous | LETTER TO RP RE WI DOT LETTER TO RP | ||
2011-07-13 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | PHASE 4 POTENTIALLY HAZ LIQUID WASTE MANAGEMENT & DISPOSAL REPORT | ||
2010-02-24 | 2 | Responsible Party (RP) letter sent | |||
2010-01-20 | 1 | Notification of Hazardous Substance Discharge | SITE ASSESSMENT 12/16/2009 | ||
2010-01-20 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
PHASE 3 SITE INVESTIGATION REPORT |
Substance | Type | Amt Released | Units |
---|---|---|---|
Petroleum - Unknown Type | Petroleum |
FOND DU LAC COUNTY 160 S MACY ST, FOND DU LAC, WI 54936 |
Northeast Region Contact: Denise Danelski denise.danelski@wisconsin.gov |