2021-08-20
|
11
|
Activity Closed
|
|
|
|
2021-08-20
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2021-08-20
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2021-08-20
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
|
|
2021-08-20
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
|
|
2021-08-20
|
238
|
Continuing Obligation - Inspection Reports Required
|
|
|
|
2021-08-20
|
46
|
Impacted Right-of-Way (ROW) Notification
|
|
|
|
2021-08-20
|
66
|
Continuing Obligations (COs) Apply at Off-site Property(ies)
|
|
|
|
2021-07-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-07-06
|
190
|
Remaining Actions Needed Requirements Met or Docs Received
|
|
REMAINING ACTION REQUIREMENT MET (MW ABANDONMENT FORMS RECEIVED)
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-02-24
|
118
|
PFAS Sampling Not Required At This Time
|
|
PFAS SAMPLING NOT REQUIRED
|
|
2021-01-14
|
84
|
Remaining Actions Needed
|
|
MW ABANDONMENT, DOCUMENTATION
|
|
2021-01-11
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-12-18
|
114
|
PFAS Scoping Statement Received
|
|
EMERGING CONTAMINANTS EVALUATION - PFAS SCOPING STATEMENT REC'D
|
|
2020-12-16
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
REQUESTED REVISIONS RECEIVED
|
|
2020-09-18
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
INFO REQUESTED
|
|
2020-09-17
|
779
|
Case Closure Review Fee Received
|
|
CK # 1201550
|
|
2020-09-17
|
700
|
Database Fee Paid for Groundwater Continuing Obligation(s)
|
|
CK # 1201550
|
|
2020-09-17
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
CK # 1201550
|
|
2020-09-17
|
79
|
Case Closure Review Request Received
|
|
AUTO-ENTERED
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-02-12
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SIR REC'D
|
|
2020-01-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2019-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-03-29
|
43
|
Site Activity Status Update Received
|
|
SMP USH 2 - WIDOT PROJECT # 8680-00-71, 72 & 8998-00-24
|
|
2019-01-07
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-11-26
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
SOW GO AHEAD
|
|
2018-11-23
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
SI WORK PLAN REC'D
|
|
2018-11-05
|
33
|
Tank System Site Assessment (TSSA) Report Received
|
|
TSSA RPT REC'D - FROM WI DOT PROJECT ID # 8680-00-71
|
|
2018-07-26
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-01-18
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2017-07-28
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2017 - 6/30/2017
|
|
2017-02-13
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2016-08-16
|
99
|
Miscellaneous
|
|
WI DOT NOTIFICATION OF POTENTIAL SOIL TRANSPORTED TO ANOTHER PROPERTY - WI DOT PROJECT #8680-00-01
|
|
2016-07-19
|
43
|
Site Activity Status Update Received
|
|
ADDENDUM #1 EXCAVATION MGMT PLAN WI DOT PROJECT # 8680-00-01(71)
|
|
2016-07-11
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2016 - 6/30/2016
|
|
2016-03-11
|
43
|
Site Activity Status Update Received
|
|
EXCAVATION MGMT PLAN - WI DOT PROJECT #8680-00-01-71
|
|
2016-02-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2015 - 12/31/2015
|
|
2015-09-03
|
99
|
Miscellaneous
|
|
COPIES OF RP LETTER SENT TO RP
|
|
2015-07-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2015 - 6/30/2015
|
|
2015-02-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2014 - 12/31/2014
|
|
2014-09-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2014 - 6/30/2014
|
|
2013-04-19
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2013-04-12
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
2013-04-03
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
WI DOT PROJECT 8680-00-01 (71)
|