2024-07-23
|
98
|
Technical Assistance Provided
|
|
FOR OFF-SITE EVALUATION OF PFAS
|
|
2024-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2024 - 6/30/2024
|
|
2024-05-10
|
97
|
Technical Assistance Request Received (fee)
|
|
OFF-SITE EVALUATION OF PFAS
|
|
2024-05-03
|
43
|
Site Activity Status Update Received
|
|
ANNUAL REPORT - JANUARY TO DECEMBER 2023 (QUARTERLY GROUNDWATER MONITORING)
|
|
2024-03-08
|
99
|
Miscellaneous
|
|
COMMENTS FOR PROPOSED WELL LOCATIONS
|
|
2024-03-06
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL MONITORING WELL LOCATIONS PROPOSED FOR PFAS INVESTIGATION & GENERAL COMMENTS TO PLAN
|
|
2024-02-16
|
64
|
Inject/Infiltrate Request Approved
|
|
INJECTION TO GROUNDWATER FOR CVOC REMEDIATION
|
|
2024-01-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2024-01-16
|
63
|
Inject/Infiltrate Request Received (fee)
|
|
INJECTION TO GROUNDWATER FOR CVOC REMEDIATION
|
|
2023-10-09
|
99
|
Miscellaneous
|
|
RESPONSE TO ADDITIONAL INVESTIGATION RESULTS FOR PCBS AND PFAS SUBMITTED IN AUGUST 2023
|
|
2023-08-24
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER ANALYTICAL RESULTS FOR POLYFLUORINATED ALKYL SUBSTANCES (PFAS)
|
|
2023-08-22
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL SITE INVESTIGATION RESULTS (PCBS)
|
|
2023-07-31
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-07-07
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL PRE-REMEDIAL DESIGN INVESTIGATION ACTIVITIES IN CENTRAL VOC GROUNDWATER PLUME AREA
|
|
2023-06-02
|
99
|
Miscellaneous
|
|
DNR RESPONSE TO ADDITIONAL EVALUATION OF PFAS
|
|
2023-04-12
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL EVALUATION OF PFAS
|
|
2023-02-17
|
99
|
Miscellaneous
|
|
CONCURRENCE THAT FURTHER EVALUATION OF SURFACE WATER AND SEDIMENT IS NOT WARRANTED
|
|
2023-01-30
|
43
|
Site Activity Status Update Received
|
|
EAST TWIN RIVER AND HARBOR SEDIMENT STUDY - SURFACE WATER AND SEDIMENT EVALUATION
|
|
2023-01-30
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE ON WORK COMPLETED FROM 8/30/2022 WORK PLAN
|
|
2023-01-23
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-09-16
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2022-08-30
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
2022 WORK PLAN ADDENDUM II - PRE-DESIGN GROUNDWATER AND SOIL INVESTIGATION
|
|
2022-08-22
|
43
|
Site Activity Status Update Received
|
|
WORK PLAN TO BE SUBMITTED THIS WEEK
|
|
2022-07-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-05-04
|
98
|
Technical Assistance Provided
|
|
RESPONSE TO CONTAMINANTS OF CONCERN AND MEDIA EVALUATION IN REPORT RECEIVED ON 3/18/2022
|
|
2022-03-18
|
97
|
Technical Assistance Request Received (fee)
|
|
OCTOBER AND NOVEMBER 2021 ADDITIONAL GROUNDWATER AND SOIL INVESTIGATION REPORT
|
|
2022-03-18
|
120
|
PFAS Sampling Completed - Actionable Levels Detected
|
|
|
|
2022-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2021-12-10
|
43
|
Site Activity Status Update Received
|
|
FOR ADDITIONAL SITE INVESTIGATION WORK
|
|
2021-09-23
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2021-09-10
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
ADDITIONAL SAMPLING IN SOIL AND/OR GW FOR METALS, PAHS, PCBS, PFAS, AND 1,4 DIOXANE
|
|
2021-07-28
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
DATED FEBRUARY 1993, USED AS SUPPLEMENTAL INFO FOR SITE INVESTIGATION SCOPING
|
|
2021-07-26
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-07-16
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
|
|
2021-07-16
|
140
|
Site Investigation Report (SIR) Not Approved
|
|
SEE REMEDIAL ACTION OPTIONS LETTER WITH THE SAME DATE FOR DOCUMENTATION
|
|
2021-07-16
|
116
|
PFAS Sampling Required
|
|
AND 1,4 DIOXANE, DETERMINATION INCLUDED IN SI NOT APPROVED LETTER DATED 7/16/2021
|
|
2021-06-18
|
114
|
PFAS Scoping Statement Received
|
|
|
|
2021-06-18
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
|
|
2021-06-09
|
98
|
Technical Assistance Provided
|
|
NO VAPOR MITIGATION REQUIRED AS A CONTINUING OBLIGATION FOR OFF-SITE HOTEL DEVELOPMENT
|
|
2021-05-20
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
NEED EMERGING CONTAMINANT SCOPING TO COMPLETE REVIEW OF REMEDIAL ACTION OPTIONS REPORT
|
|
2021-05-11
|
143
|
Remedial Action Options Report (RAOR) Received (fee)
|
|
|
|
2021-05-11
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
SEE AC 143 OF SAME DATE FOR DOCUMENTATION
|
|
2021-05-03
|
99
|
Miscellaneous
|
|
CLARIFICATIONS ON SUBMITTAL OF FEE FOR RAOR AND EMERGING CONTAMINANT SCOPING
|
|
2021-04-07
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
VAPOR INTRUSION ASSESSMENT RESULTS REPORT RECEIVED FOR OFF-SITE HOTEL DEVELOPMENT
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-03-29
|
43
|
Site Activity Status Update Received
|
|
TIMELINE FOR SUBMITTING REPORT FOR ADDT'L SITE INVESTIGATION AND REMEDIAL ACTION OPTIONS EVALUATION
|
|
2021-01-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-11-11
|
99
|
Miscellaneous
|
|
FOLLOW UP NEEDED FOR VAPOR ASSESSMENT/MITIGATION FOR TECHNICAL ASSISTANCE REQUEST FOR OFF-SITE HOTEL
|
|
2020-10-09
|
99
|
Miscellaneous
|
|
EMERGING CONTAMINANT SCOPING REQUIRED FOR THE SITE INVESTIGATION
|
|
2020-10-08
|
43
|
Site Activity Status Update Received
|
|
CLARIFICATIONS ON ACCESS AND OWNERSHIP OF MONITORING WELLS IN THE CITY OF TWO RIVERS ROW
|
|
2020-10-06
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
CALL NEEDED TO DISCUSS VAPOR ISSUES PRIOR TO ISSUING TECHNICAL ASSISTANCE LETTER FOR OFF-SITE HOTEL
|
|
2020-08-24
|
97
|
Technical Assistance Request Received (fee)
|
|
OFF-SITE HOTEL REDEVELOPMENT VAPOR ASSESSMENT & MITIGATION DUE TO CVOC CONTAMINATION FROM THIS CASE
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-14
|
43
|
Site Activity Status Update Received
|
|
QUARTERLY GROUNDWATER MONITORING REPORT
|
|
2020-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-05-27
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON PROGRESS OF SITE INVESTIGATION WORK
|
|
2020-02-04
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2020-01-23
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
VAPOR INTRUSION EVALUATION WORK PLAN ADDENDUM 1
|
|
2020-01-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2019-09-13
|
43
|
Site Activity Status Update Received
|
|
UTILITY INFORMATION FROM CITY OF TWO RIVERS
|
|
2019-08-23
|
99
|
Miscellaneous
|
|
SITE INVESTIGATION CLARIFICATIONS
|
|
2019-08-08
|
43
|
Site Activity Status Update Received
|
|
5TH QUARTERLY GW SAMPLING EVENT AND ADDITIONAL NORTH INVESTIGATION SUMMARY
|
|
2019-07-22
|
43
|
Site Activity Status Update Received
|
|
MW-22S ABANDONMENT PLAN CORRESPONDENCE BETWEEN DNR, CITY OF TWO RIVERS, AND ERM
|
|
2019-07-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-05-13
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2019-05-10
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
ADDITIONAL SI ON NORTH SIDE OF SITE
|
|
2019-04-25
|
140
|
Site Investigation Report (SIR) Not Approved
|
|
ADD'L SI FOR CVOCS, CPAH ASSESS NO FURTHER SI FOR PAHS
|
|
2019-04-24
|
43
|
Site Activity Status Update Received
|
|
REVISED SIGNATURE PAGE FOR 3/8/2019 SIR
|
|
2019-04-11
|
43
|
Site Activity Status Update Received
|
|
REVISED PAH SOIL TABLE AND CPAH ASSESSMENT TABLES FOR 3/8/2019 SIR
|
|
2019-04-11
|
99
|
Miscellaneous
|
|
REQUEST TO TWO RIVERS FOR INVESTIGATION OF MW-2 LNAPL AREA OFF-SITE
|
|
2019-03-08
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
|
|
2019-01-11
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-08-09
|
99
|
Miscellaneous
|
|
SI UPDATE, INTEGRATION OF OFF-SITE DATA, & NO CURRENT VAPOR CONCERNS DUE TO BUILDING DEMO OFF-SITE
|
|
2018-08-06
|
99
|
Miscellaneous
|
|
CORRESP WITH TWO RIVERS ON REDEVELOPMENT PLANS AND POTENTIAL VAPOR CONCERNS OFF-SITE
|
|
2018-07-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-05-11
|
99
|
Miscellaneous
|
|
NOTIFICATION TO TWO RIVERS AND RP THAT TWO CITY PHASE II ESA'S INFO INTEGRATED INTO THIS CASE
|
|
2018-04-20
|
99
|
Miscellaneous
|
|
VAPOR SAMPLING CLARIFICATIONS
|
|
2018-04-11
|
43
|
Site Activity Status Update Received
|
|
SUETTINGER PHASE I ESA & CITY ROW ASSESSMENT INFORMATION RELEVANT TO CASE
|
|
2018-03-22
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2018-03-19
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2018-02-12
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
ADDITIONAL SI REPORT
|
|
2018-01-08
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2017-11-13
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2017-11-13
|
43
|
Site Activity Status Update Received
|
|
NO SURFACE WATER CONCERNS FOR INVESTIGATION
|
|
2017-11-13
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON DELINEATION OF GW CONTAMINATION
|
|
2017-11-07
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2017-08-18
|
43
|
Site Activity Status Update Received
|
|
CLARIFICATIONS FOR SI WORKPLAN
|
|
2017-08-18
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2017-08-17
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2017-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2017 - 6/30/2017
|
|
2017-06-14
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2017-05-24
|
43
|
Site Activity Status Update Received
|
|
UPDATE FOR SI AND FREE PRODUCT
|
|
2017-04-27
|
43
|
Site Activity Status Update Received
|
|
PETROLEUM LNAPL FOUND IN MW-2
|
|
2017-03-22
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2017-03-22
|
43
|
Site Activity Status Update Received
|
|
RESPONSE TO SI WORKPLAN NOTICE TO PROCEED
|
|
2017-03-17
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
REVISED SI WORKPLAN
|
|
2017-02-22
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
CITY OF TWO RIVERS PHASE II ESA ASSESSMENT ADJACENT TO SITE
|
|
2017-01-16
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2017-01-09
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2017-01-06
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2017-01-06
|
43
|
Site Activity Status Update Received
|
|
CITY PROVIDED UPDATE ON THEIR ADDITIONAL SAMPLING BEING DONE ADJACENT TO THE SITE
|
|
2016-12-19
|
7
|
Environmental Consultant Hired
|
|
ERM
|
|
2016-11-18
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2016-11-09
|
99
|
Miscellaneous
|
|
NOTIFICATION TO CONSULTANT AND OWNER THAT NEW CASE WILL BE CREATED AND RP LETTER ISSUED
|
|
2016-11-07
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON CITYS SAMPLING PLANS ADJACENT TO SITE
|
|
2016-10-31
|
43
|
Site Activity Status Update Received
|
|
ADDITION INFORMATION FOR RELEASE NOTIFICATION REPORT
|
|
2016-10-31
|
43
|
Site Activity Status Update Received
|
|
SPLIT SAMPLING DATA FOR RELEASE NOTIFICATION
|
|
2016-10-25
|
1
|
Notification of Hazardous Substance Discharge
|
|
UTILITY EXCAVATION FOR CITY WATER LINE - 10/1/2016
|
|
2016-08-31
|
43
|
Site Activity Status Update Received
|
|
NOTIFICATION OF RESULTS FROM CITY FOR CONTAMINATION POTENTIALLY MIGRATING FROM OFF-SITE SOURCE
|
|
2016-04-01
|
99
|
Miscellaneous
|
|
ECONOMIC DEVELOPMENT NEWS ARTICLE
|