02-71-582406
FOX RIVER NRDA/PCB RELEASES OU1 (ALT SF)
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / CLOSED | DNR RR |
Location Name | County | DNR Region |
---|---|---|
FOX RIVER PCB SEDIMENT | WINNEBAGO | NORTHEAST |
Address | Municipality |
---|---|
FOX RIVER | COVERS MANY MUNIC |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
SW 1/4 of the NW 1/4 of Sec 10, T20N, R17E | 44.2233816 | -88.4600108 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
Electronic Only - No Hard File | gt;100 |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
1998-07-28 | 2024-02-09 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-03-04 | 43 | Site Activity Status Update Received |
![]() |
EPA APPROVAL OF TERMINATION OF YOUNG-OF-YEAR FISH MONITORING FOR OU1 AND OU4 | |
2024-03-04 | 43 | Site Activity Status Update Received |
![]() |
EPA APPROVAL OF TERMINATION ECOLOGICAL FISH MONITORING IN OU1-5 | |
2024-02-09 | 11 | Activity Closed | |||
2024-02-09 | 56 | Continuing Obligation(s) Applied | |||
2024-02-09 | 228 | Continuing Obligation - Site Specific Condition | RESIDUAL SEDIMENT CONTAMINATION, SEDIMENT CAP MAINTENANCE, & FISH/SURFACE WATER MONITORING | ||
2023-10-11 | 43 | Site Activity Status Update Received |
![]() |
EPA NOTIFICATION TO DNR FOR INITIATING FOURTH FIVE YEAR REVIEW | |
2023-09-29 | 43 | Site Activity Status Update Received |
![]() |
REJECTION OF THE ORIGINAL NOVEMBER 2022 SURFACE WATER DATA SET | |
2023-09-22 | 43 | Site Activity Status Update Received |
![]() |
EPA APPROVAL OF INSTITUTIONAL CONTROL IMPLEMENTATION AND ASSURANCE PLAN (ICIAP) | |
2023-09-19 | 43 | Site Activity Status Update Received |
![]() |
REF ZZ - 2023 INSTITUTIONAL CONTROL IMPLEMENTATION AND ASSURANCE PLAN | |
2023-09-19 | 43 | Site Activity Status Update Received |
![]() |
INTEGRATED FINAL DESIGN & REMEDIAL ACTION WORK PLAN FOR POST-2009 RESPONSE WORK W/FINAL 2023 ICIAP | |
2023-07-31 | 43 | Site Activity Status Update Received |
![]() |
EPA APPROVAL OF LONG-TERM MONITORING PLAN (LTMP) - REVISION 1 | |
2023-06-20 | 43 | Site Activity Status Update Received |
![]() |
LONG-TERM MONITORING PLAN (LTMP) - REVISION 1 FOR OU2-5, ALSO UTILIZED FOR OU1 | |
2023-03-17 | 99 | Miscellaneous |
![]() |
FACT SHEET FOR PROCESS OF PROPOSED WATERWAY PROJECT PERMITTING, DREDGING, AND PCB CAP DISTURBANCE | |
2023-01-01 | 43 | Site Activity Status Update Received |
![]() |
PCB CAP FIGURE | |
2022-10-24 | 118 | PFAS Sampling Not Required At This Time | |||
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-04-06 | 779 | Case Closure Review Fee Received | |||
2020-04-06 | 700 | Database Fee Paid for Groundwater Continuing Obligation(s) | |||
2020-03-25 | - | Continuing Obligations |
![]() |
UPLOADING FINAL CO PACKET FOR PUBLIC VIEWING UNTIL CLOSURE LETTERS ARE ISSUED. | |
2018-11-02 | 43 | Site Activity Status Update Received |
![]() |
STH 441/US 10 WISDOT PROJ; MANAGEMENT OF CONTAMINATED SEDIMENT & REPAIR OF ENGINEERED SEDIMENT CAP | |
2018-06-25 | 99 | Miscellaneous | STH441/USH10 WISDOT LLBM BRIDGE PROJECT MISCELLANEOUS CORRESPONDENCE FROM APRIL TO JUNE 2018 | ||
2017-08-23 | 43 | Site Activity Status Update Received | GIS DATASET OF WINNEBAGO AND OUTAGAMIE COUNTIES PARCELS BORDERING OU1 | ||
2017-05-22 | 43 | Site Activity Status Update Received |
![]() |
STH 441/USH 10 LLBM; MANAGEMENT OF CONT SED & REPAIR OF ENG SED CAP; WISDOT PROJ ID #: 1517-07-76 | |
2016-06-29 | 99 | Miscellaneous |
![]() |
STH441/USH10 WISDOT LLBM BRIDGE PROJECT MISCELLANEOUS CORRESPONDENCE FROM MAY 2012 - JUN 2016 | |
2014-05-19 | 99 | Miscellaneous |
![]() |
STH 441/USH 10; FINAL CONCURRENCE W/ CAP MONITOR/REPAIR PLAN/SPECIAL PROVISION; WISDOT ID 1517-07-04 | |
2014-05-07 | 43 | Site Activity Status Update Received |
![]() |
STH 441/USH 10 LLBM; CAP MONITOR & REPAIR PLAN & SPECIAL PROVISIONS; WISDOT PROJ ID # 1517-07-00-04 | |
2013-11-01 | 43 | Site Activity Status Update Received |
![]() |
REF Z - 2012 LONG-TERM MONITORING SUMMARY REPORT - WITHOUT APPENDIX F | |
2013-11-01 | 43 | Site Activity Status Update Received |
![]() |
REF Z - 2012 LONG-TERM MONITORING SUMMARY REPORT - APPENDIX F ONLY | |
2013-01-07 | 43 | Site Activity Status Update Received |
![]() |
STH 441/USH 10 LLBM; SED INVEST DOC REPORT AND SPECIAL PROVISIONS; WISDOT PROJ ID #: 1517-07-00 | |
2012-11-01 | 43 | Site Activity Status Update Received |
![]() |
REF Y - 2010 LONG-TERM MONITORING SUMMARY REPORT | |
2011-08-26 | 99 | Miscellaneous |
![]() |
APPROVAL OF INTEGRATED FINAL DESIGN AND REMEDIAL ACTION WORK PLAN FOR POST-2009 RESPONSE WORK | |
2011-06-01 | 43 | Site Activity Status Update Received |
![]() |
REF W - INTEGRATED FINAL DESIGN AND REMEDIAL ACTION WORK PLAN FOR POST-2009 RESPONSE WORK | |
2011-06-01 | 43 | Site Activity Status Update Received |
![]() |
REF X - LONG-TERM MONITORING PLAN | |
2011-05-01 | 43 | Site Activity Status Update Received |
![]() |
REF V - CAP MONITORING AND MAINTENANCE PLAN | |
2011-04-01 | 43 | Site Activity Status Update Received |
![]() |
REF U - QUALITY ASSURANCE PROJECT PLAN (POST 2009) | |
2010-12-05 | 99 | Miscellaneous |
![]() |
APPROVAL OF REMEDIAL ACTION CERTIFICATION OF COMPLETION REPORT | |
2010-11-01 | 43 | Site Activity Status Update Received |
![]() |
REF T - REMEDIAL ACTION CERTIFICATION OF COMPLETION | |
2010-08-01 | 43 | Site Activity Status Update Received |
![]() |
SURFACE WEIGHTED AVERAGE CONCENTRATIONS (SWAC) CALCULATION REMAINING PCB CONCENTRATION FIGURES | |
2010-04-01 | 43 | Site Activity Status Update Received |
![]() |
REF S - 2009 REMEDIAL ACTION SUMMARY REPORT | |
2009-12-01 | 43 | Site Activity Status Update Received |
![]() |
REF R - LONG TERM MONITORING PLAN | |
2009-09-01 | 43 | Site Activity Status Update Received |
![]() |
REF Q - 2008 REMEDIAL ACTION SUMMARY REPORT | |
2009-07-01 | 43 | Site Activity Status Update Received |
![]() |
REF P - BASELINE MONITORING DATA REPORT 2006-2007 | |
2008-06-12 | 43 | Site Activity Status Update Received |
![]() |
REF O - AMENDED CONSENT DECREE | |
2008-06-01 | 314 | Superfund Decision Document (ROD or ESD) - See Description |
![]() |
REF N - 2008 ROD AMENDMENT | |
2008-05-01 | 43 | Site Activity Status Update Received |
![]() |
REF M - 2007 REMEDIAL ACTION SUMMARY REPORT | |
2007-11-01 | 43 | Site Activity Status Update Received |
![]() |
REF L - DESIGN SUPPLEMENT | |
2007-10-22 | 43 | Site Activity Status Update Received |
![]() |
REF K - DRAFT - CONCEPT PAPER | |
2007-05-01 | 43 | Site Activity Status Update Received |
![]() |
REF J - 2006 REMEDIAL SUMMARY REPORT | |
2007-01-01 | 43 | Site Activity Status Update Received |
![]() |
REF I - 2005 REMEDIAL SUMMARY REPORT | |
2006-03-01 | 43 | Site Activity Status Update Received |
![]() |
REF H - 2004 REMEDIAL SUMMARY REPORT | |
2005-03-01 | 43 | Site Activity Status Update Received |
![]() |
REF G - PRE-DESIGN - BASIS OF DESIGN | |
2004-04-01 | 43 | Site Activity Status Update Received |
![]() |
REF F - 2004 REMEDIAL ACTION PRELIMINARY DESIGN | |
2003-09-02 | 43 | Site Activity Status Update Received |
![]() |
REF E - CONSENT DECREE | |
2002-12-01 | 305 | Superfund Enforcement Documents - See Description |
![]() |
REF A - REMEDIAL INVESTIGATION REPORT | |
2002-12-01 | 310 | Superfund Final Feasibility Study (FS) Submittal |
![]() |
REF B - FINAL FEASIBILITY REPORT | |
2002-12-01 | 314 | Superfund Decision Document (ROD or ESD) - See Description |
![]() |
REF C - RECORD OF DECISION | |
1998-07-28 | 1 | Notification of Hazardous Substance Discharge | |||
1998-07-28 | 301 | Superfund NPL, NPL Proposed or Alternative Approach Site | PROPOSED ONLY - SUPERFUND ALTERNATIVE - 301 DATE BASED ON FINAL NPL LISTING DATE |
Substance | Type | Amt Released | Units |
---|---|---|---|
Polychlorinated Biphenyl | PCB |
BHC LLC W7881 OAKCREST DR, HORTONVILLE, WI 54955 |
Northeast Region Contact: Denise Danelski denise.danelski@wisconsin.gov |