2023-02-07
|
101
|
Continuing Obligation Modification Approval
|
|
NO CONTINUING OBLIGATIONS CHANGED
|
|
2022-12-14
|
194
|
CO Modification Final Documentation Received
|
|
|
|
2022-03-31
|
193
|
CO Modification Notice to Proceed (NTP)
|
|
POST CLOSURE MODIFICATION REQUEST APPROVED
|
|
2022-02-15
|
181
|
Continuing Obligation Modification Request Received (fee)
|
|
|
|
2022-02-15
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
|
|
2021-08-27
|
11
|
Activity Closed
|
|
|
|
2021-08-27
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2021-08-27
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2021-08-27
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
|
|
2021-08-27
|
48
|
Preventive Action Limit (PAL) NR140 Exemption at Closure
|
|
|
|
2021-08-20
|
-
|
Site Investigation
|
|
|
|
2021-08-09
|
84
|
Remaining Actions Needed
|
|
VAPOR PIN ABANDONMENT REQUIRED
|
|
2021-08-05
|
190
|
Remaining Actions Needed Requirements Met or Docs Received
|
|
UPDATED FIGURES AND VAPOR PIN ABANDONMENT
|
|
2021-07-27
|
79
|
Case Closure Review Request Received
|
|
AUTO-ENTERED
|
|
2021-07-26
|
779
|
Case Closure Review Fee Received
|
|
|
|
2021-07-26
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
|
|
2021-07-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-07-12
|
38
|
Site Investigation Report (SIR) Approved
|
|
|
|
2021-07-09
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
VAPOR SAMPLING RSULTS REC'D
|
|
2021-07-09
|
43
|
Site Activity Status Update Received
|
|
VAPOR SAMPLING RESULTS
|
|
2021-06-25
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
REQUESTED VAPOR SAMPLING
|
|
2021-06-18
|
118
|
PFAS Sampling Not Required At This Time
|
|
|
|
2021-06-07
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
|
|
2021-06-07
|
114
|
PFAS Scoping Statement Received
|
|
STATEMENT INCLUDED WITHIN SIR
|
|
2021-05-05
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2021-05-05
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2021-04-26
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2021-04-19
|
7
|
Environmental Consultant Hired
|
|
REI ENGINEERING
|
|
2021-04-16
|
43
|
Site Activity Status Update Received
|
|
GEOTECHNICAL REPORT FOR SITE
|
|
2021-04-06
|
1
|
Notification of Hazardous Substance Discharge
|
|
|