2020-06-15
|
33
|
Tank System Site Assessment (TSSA) Report Received
|
|
TSSA
|
|
2005-06-07
|
11
|
Activity Closed
|
|
BB. FINAL CLOSURE LETTER SENT
|
|
2005-06-07
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
*** AUTO POPULATED AT FINAL CLOSURE DUE TO 700 ACTION ***
|
|
2005-06-07
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
*** AUTO POPULATED AT FINAL CLOSURE DUE TO 710 ACTION ***
|
|
2005-06-07
|
56
|
Continuing Obligation(s) Applied
|
|
AUTO-POPULATED AS REPLACEMENT FOR CODE 50
|
|
2005-06-06
|
90
|
SER First In/First Out (FIFO) Review Process Started
|
|
REC'D WELL ABANDONMENT FORMS AND WASTE DISPOSAL INFO.
|
|
2004-11-03
|
84
|
Remaining Actions Needed
|
|
BB. PENDING WELL ABANDONMENT & WASTE DISPOSAL
|
|
2004-07-30
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
REC'D CK# 043707 $200.00
|
|
2004-07-29
|
700
|
Database Fee Paid for Groundwater Continuing Obligation(s)
|
|
REC'D CK# 043707 $250.00
|
|
2004-07-22
|
79
|
Case Closure Review Request Received
|
|
REC'D CK# 043747 $750.00 REC'D GIS PKT GIVEN TO MW 07/30/04
|
|
2003-11-07
|
43
|
Site Activity Status Update Received
|
|
RCV'D ADD'L INVESTIGATION AND GROUNDWATER MONITORING RESULTS REPORT
|
|
2003-06-16
|
43
|
Site Activity Status Update Received
|
|
CONCOURSE "C" EXPANSION PROJECT SUMMARY
|
|
2002-08-09
|
43
|
Site Activity Status Update Received
|
|
EA
|
|
2002-03-04
|
42
|
Remedial Action Report Approved
|
|
EA
|
|
2002-03-04
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
|
|
2002-02-05
|
143
|
Remedial Action Options Report (RAOR) Received (fee)
|
|
EA.REC'D CK# 42005 $750.00
|
|
2001-11-07
|
99
|
Miscellaneous
|
|
EA.FREE PRODUCT; TCE CO-MINGLED WITH PETROLEUM
|
|
2001-04-09
|
43
|
Site Activity Status Update Received
|
|
|
|
2000-06-16
|
92
|
Operation & Maintenance (O & M) Report Received (non-Fee)
|
|
|
|
2000-02-11
|
43
|
Site Activity Status Update Received
|
|
SUBMITTAL OF SEMI-ANNUAL REPORT
|
|
2000-02-11
|
99
|
Miscellaneous
|
|
SUP SITE & COST INFO FOR REMEDIAL SYS
|
|
1999-05-18
|
99
|
Miscellaneous
|
|
CONSTRUCTION COMPLETION REPORT
|
|
1999-04-26
|
43
|
Site Activity Status Update Received
|
|
|
|
1998-09-14
|
92
|
Operation & Maintenance (O & M) Report Received (non-Fee)
|
|
|
|
1997-06-24
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
|
|
1997-01-24
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
1996-04-01
|
43
|
Site Activity Status Update Received
|
|
CASE SINCE '90;RAP APPROVED/IMPLEMENTED
|
|
1990-05-05
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
1990-05-05
|
2
|
Responsible Party (RP) letter sent
|
|
SENT WHEN CASE WAS A SPILL.
|