2024-02-19
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN-DEC 2023
|
|
2023-06-21
|
99
|
Miscellaneous
|
|
EMAIL RESPONSE TO 2022 ANNUAL OM&M REPORT-MONITORING PLAN CHANGE APPROVAL
|
|
2023-01-31
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN-DEC 2022
|
|
2022-02-04
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
|
|
2021-02-12
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN-DEC 2020
|
|
2020-01-29
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN - DEC 2019
|
|
2019-02-04
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN - DEC 2018
|
|
2018-02-12
|
99
|
Miscellaneous
|
|
EMAIL RESPONSE TO 2017 ANNUAL O&M REPORT - MONITORING PLAN CHANGE APPROVAL
|
|
2018-02-09
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN - DEC 2017
|
|
2017-02-20
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
JAN - DEC 2016
|
|
2016-02-04
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
NOV 2014 - DEC 2015
|
|
2015-09-09
|
99
|
Miscellaneous
|
|
COST RECOVERY WAIVER MEMO SENT
|
|
2014-12-09
|
43
|
Site Activity Status Update Received
|
|
ANNUAL RPT REC'D
|
|
2014-05-15
|
99
|
Miscellaneous
|
|
LETTER SENT TO AFFECTED OFF-SITE PROPERTY OWNERS RE: REMOVAL FROM GIS REGISTRY
|
|
2014-04-23
|
99
|
Miscellaneous
|
|
GROUNDWATER CONTAMINANT TREND ANALYSIS RECEIVED FROM CONSULTANT
|
|
2014-04-21
|
99
|
Miscellaneous
|
|
OPEN HOUSE MEETING TO ADDRESS CONCERNS OF AFFECTED OFF-SITE PROPERTY OWNERS
|
|
2014-04-16
|
99
|
Miscellaneous
|
|
CONTINUING OBLIGATION CLARIFICATION LETTER SENT TO AFFECTED OFF-SITE PROPERTY OWNERS
|
|
2013-12-26
|
11
|
Activity Closed
|
|
|
|
2013-12-26
|
234
|
Continuing Obligation - Monitoring Well Needs Abandonment
|
|
MISSING MW, UNABLE TO BE ABANDONED MW-2, MW-15, MW-20 MW WAS NOT ABLE TO BE LOCATED
|
|
2013-12-26
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2013-12-26
|
228
|
Continuing Obligation - Site Specific Condition
|
|
OPERATION & MTC OF ACTIVE GAS EXTRACTION SYSTEM
|
|
2013-12-26
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2013-12-26
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
|
|
2013-12-26
|
228
|
Continuing Obligation - Site Specific Condition
|
|
CONVERSION OF GAS SYSTEM REQUIRED IF LAND USE CHANGES IN FUTURE
|
|
2013-12-26
|
46
|
Impacted Right-of-Way (ROW) Notification
|
|
AUTO-POPULATED 2018-03-20
|
|
2013-12-23
|
190
|
Remaining Actions Needed Requirements Met or Docs Received
|
|
MW ABANDONMENT FORMS RECEIVED
|
|
2013-11-18
|
84
|
Remaining Actions Needed
|
|
WM ABANDONMENT
|
|
2013-11-17
|
50
|
Groundwater Use Restriction Potentially Filed
|
|
|
|
2013-11-07
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
O&M RPT REC'D
|
|
2013-11-01
|
179
|
Case Closure Review Request Received (non-fee)
|
|
CLOSURE REQUEST REC'D; NO FEE VPLE
|
|
2013-11-01
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
CONSTUCTION COMPLETION RPT REC'D
|
|
2013-10-28
|
99
|
Miscellaneous
|
|
LTR SENT - ADDENDUM TO ASSURANCE LTR DATED 7/25/13
|
|
2013-10-11
|
99
|
Miscellaneous
|
|
DRAFT CONSTRUCTION COMPLETION RPT REC'D
|
|
2013-10-08
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-10-01
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-10-01
|
99
|
Miscellaneous
|
|
SOURCE PROPERTY & OFF-SITE NOTIFICATION LTRS SENT
|
|
2013-09-24
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-09-17
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-09-13
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
SIWP REC'D - SALZMANN BUILDING FLOOR PLAN. VPLE SITE NO-FEE
|
|
2013-09-13
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
SIWP APPROVED
|
|
2013-09-10
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-09-03
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-08-27
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS PRT REC'D
|
|
2013-08-20
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-08-14
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-08-12
|
99
|
Miscellaneous
|
|
DESIGN MODIFICAITON APPROVAL - COVER THICKNESS SE CORNER
|
|
2013-08-08
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS PRT REC'D
|
|
2013-07-31
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-07-25
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-07-23
|
99
|
Miscellaneous
|
|
SITE VISIT
|
|
2013-07-18
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-07-10
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-07-05
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-07-03
|
99
|
Miscellaneous
|
|
DESIGN MODIFICATION APPROVAL - CLAY COMPACTION
|
|
2013-06-27
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-06-24
|
99
|
Miscellaneous
|
|
ABANDONMENT FORMS REC'D (GP9, 12, 13, 14)
|
|
2013-06-20
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-06-20
|
402
|
Historic Fill Case by Case Exemption Issued
|
|
BAL EXEMPTION GRANTED FOR CONCESSION/RESTROOM BLDG & FIELD LIGHTING
|
|
2013-06-14
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
BAL ADDENDUM REC'D
|
|
2013-06-13
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-06-12
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
REQUEST FOR MORE INFORMATION ON BAL APPLICATION
|
|
2013-06-05
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-06-03
|
401
|
Historic Fill Case by Case Exemption Request (fee)
|
|
BAL SUBMITTAL REC'D - CONCESSION BUILDING & FIELD LIGHTING. NO FEE VPLE CASE
|
|
2013-05-30
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-05-22
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS REPORT REC'D
|
|
2013-05-16
|
99
|
Miscellaneous
|
|
WEEKLY PROGRESS RPT REC'D
|
|
2013-05-06
|
99
|
Miscellaneous
|
|
PRE-CONSTRUCTION MEETING
|
|
2013-04-29
|
99
|
Miscellaneous
|
|
LTR SENT CLARIFYING DNR APPROVAL OF LF MODIFICATIONS PER CONSENT DECREE
|
|
2013-04-24
|
99
|
Miscellaneous
|
|
CONSTRUCTION QAP REC'D
|
|
2013-04-15
|
99
|
Miscellaneous
|
|
PROPOSED LANDFILL CAP & GAS REPAIRS (PER CONSENT DECREE) REC'D
|
|
2013-04-11
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS RPT REC'D
|
|
2013-03-08
|
99
|
Miscellaneous
|
|
MONTHLY PROGRESS RPT REC'D
|
|
2013-03-06
|
402
|
Historic Fill Case by Case Exemption Issued
|
|
BAL EXEMPTION GRANTED; FINAL DESIGN RPT APPROVED
|
|
2013-02-08
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
FINAL DESIGN RPT REC'D
|
|
2013-02-08
|
199
|
Additional Information Received (Fee-Based or Closure)
|
|
FINAL DESIGN RPT REC'D
|
|
2013-01-16
|
99
|
Miscellaneous
|
|
COMMENTS TO CONSULTANT ON DESIGN SUBMITTAL
|
|
2012-12-13
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
FINAL DESIGN SUBMITTAL FOR PROPOSED REDEVELOPMENT REC'D
|
|
2012-10-17
|
99
|
Miscellaneous
|
|
COPY OF AGREEMENT BETWEEN MARATHON CNTY & CITY OF WAUSAU FOR O&M REQUIREMENTS
|
|
2012-10-15
|
99
|
Miscellaneous
|
|
COMMENTS TO CONSULTANT ON 30% DESIGN
|
|
2012-10-12
|
99
|
Miscellaneous
|
|
PURCHASED BY MARATHON CNTY; MOU BETWEEN CNTY & STEERING COMMIT'E RECD; UPDATED DEEDS, LEGAL DOCS RCD
|
|
2012-10-01
|
99
|
Miscellaneous
|
|
MEETING W/ CONSULANT, RR, WMM TO DISCUSS 30% DESIGN
|
|
2012-07-25
|
38
|
Site Investigation Report (SIR) Approved
|
|
SI RPT APPROVED; ASSURANCE LTR SENT
|
|
2012-07-25
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
RAP APPROVED; ASSURANCE LTR SENT
|
|
2012-07-10
|
99
|
Miscellaneous
|
|
MEETING W/ STEERING COMMITTEE, CITY & COUNTY TO DISCUSS NEXT STEPS
|
|
2012-05-17
|
99
|
Miscellaneous
|
|
CONF CALL W/ RP CONTACT REGARDING CURRENT STATUS OF VPLE APPL
|
|
2012-05-17
|
99
|
Miscellaneous
|
|
EMAIL TO CITY OF WAUSAU RE: STATUS OF 2011 ANNUAL MONITORING RPT
|
|
2012-04-13
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
REQUEST FOR ADDT'L INFO - NEED FINAL DESIGN RPT
|
|
2012-04-12
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
PROPOSED MODIFICATIONS TO GAS EXTRACTION SYSTEM
|
|
2012-04-12
|
99
|
Miscellaneous
|
|
MEETING W/ RP GROUP, CITY OF WAUSAU, MARATHON COUNTY LEGAL - TO DICUSS REDEVELOPMENT OPTIONS
|
|
2012-04-12
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2012-04-12
|
401
|
Historic Fill Case by Case Exemption Request (fee)
|
|
BAL EXEMPTION REQUEST REC'D; NO-FEE VPLE CASE
|
|
2012-04-09
|
99
|
Miscellaneous
|
|
EXPERT OPINION ON GW REC'D FROM CONSULTANT
|
|
2012-03-15
|
99
|
Miscellaneous
|
|
SENT LTR TO WAUSAU CURLING CLUB RE: BUILDING NEXT TO AN ABANDONED LANDFILL
|
|
2012-03-07
|
99
|
Miscellaneous
|
|
MEETING W/ RP, CONSULTANT, & WMM PROGRAM TO DISCUSS GAS EXTRACTION SYSTEM
|
|
2011-12-22
|
43
|
Site Activity Status Update Received
|
|
FALL 2011 GW MONITORING RESULTS REC'D
|
|
2011-12-13
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
|
|
2011-10-26
|
93
|
Operation & Maintenance (O&M) Report Approved
|
|
LETTER SENT
|
|
2011-10-24
|
99
|
Miscellaneous
|
|
ACCESS AGREEMENTS W/ WAUSAU CEMETERY & CURLING CLUB REC'D
|
|
2011-10-10
|
99
|
Miscellaneous
|
|
MTG W/ STEERING COMMITTEE & CONSULTANT RE: SITE GOALS
|
|
2011-10-04
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
2010 ANNUAL REPORT REC'D
|
|
2011-06-27
|
99
|
Miscellaneous
|
|
ROD AMENDMENT LETTER SENT TO HOLTZ & KRAUSE LANDFILL STEERING COMMITTEE
|
|
2011-06-27
|
99
|
Miscellaneous
|
|
PUBLIC PARTICIPATION REQUIREMENTS FOR THE ROD AMENDMENT
|
|
2011-06-22
|
99
|
Miscellaneous
|
|
ROD AMENDMENT FINALIZED
|
|
2011-06-13
|
99
|
Miscellaneous
|
|
PUBLIC MEETING HELD BY STEERING COMMITTEE
|
|
2011-06-09
|
99
|
Miscellaneous
|
|
WRITTEN COMMENT PERIOD COMPLETE (5/9/11-6/9/11)
|
|
2011-06-06
|
99
|
Miscellaneous
|
|
PROPOSED REVISIONS TO ROD AMENDMENT RECEIVED FROM STEERING COMMITTEE
|
|
2011-05-26
|
99
|
Miscellaneous
|
|
MEETING WITH NEW CONSULTANT - CRA
|
|
2011-05-17
|
99
|
Miscellaneous
|
|
CONFERENCE CALL STEERING COMMITTEE - SITE STATUS
|
|
2011-05-09
|
99
|
Miscellaneous
|
|
PUBLIC NOTICE POSTED - WAUSAU DAILY HERALD (5/9,5/11,5/13)
|
|
2011-04-05
|
98
|
Technical Assistance Provided
|
|
DRAFT ROD AMENDMENT COMPLETE
|
|
2011-03-14
|
97
|
Technical Assistance Request Received (fee)
|
|
ROD AMENDMENT.
|
|
2011-02-11
|
99
|
Miscellaneous
|
|
TECHNICAL SUPPORT FOR ROD AMENDMENT REC'D.
|
|
2010-12-29
|
99
|
Miscellaneous
|
|
ACCESS AGREEMENTS BETWEEN STEERING COMMITTEE AND WAUSAU CURLING CLUB AND WAUSAU CEMETERY ASSOC. REC'
|
|
2010-12-22
|
99
|
Miscellaneous
|
|
CITY OF WAUSAU LETTER TO SALZMAN RE; CONTINUING OBLIGATIONS RELATED TO LF CAP.
|
|
2010-12-16
|
99
|
Miscellaneous
|
|
CITY OF WAUSAU LETTER TO STEERING COMMITTEE RE; ACCESS RIGHTS TO WELLS ON CITY PROPERTY.
|
|
2010-12-15
|
99
|
Miscellaneous
|
|
EMAIL TO STORM WATER RE; GRADING BEING DONE NEAR LF CAP.
|
|
2010-11-03
|
99
|
Miscellaneous
|
|
SITE VISIT.
|
|
2010-08-31
|
50
|
Groundwater Use Restriction Potentially Filed
|
|
|
|
2010-08-31
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2010-08-31
|
228
|
Continuing Obligation - Site Specific Condition
|
|
GAS EXTRACTION SYSTEM & LT GW MONITORING
|
|
2010-08-31
|
236
|
Continuing Obligation - Residual GW Contamination
|
|
|
|
2010-08-18
|
98
|
Technical Assistance Provided
|
|
TECH ASSISTANCE PROVIDED; REVIEW OF 5 YR REVIEW REPORT
|
|
2010-07-27
|
97
|
Technical Assistance Request Received (fee)
|
|
TECH ASSISTANCE REGARDING 5 YEAR REVIEW REPORT
|
|
2010-07-20
|
99
|
Miscellaneous
|
|
FIVE YEAR REVIEW REPORT (EMAIL REQUEST FOR REVIEW FEE SENT)
|
|
2009-01-19
|
99
|
Miscellaneous
|
|
2008 GW MONITORING EXCEEDENCE DATA
|
|
2009-01-06
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
2007 ANNUAL REPORT
|
|
2006-06-08
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON SAMPLING AND REPAIRS
|
|
2006-03-06
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
ADD'L SI WORK APPROVED.
|
|
2006-03-05
|
92
|
Operation & Maintenance (O&M) Report Received (non-fee)
|
|
2005 ANNUAL REPORT REC'D
|
|
2006-02-27
|
97
|
Technical Assistance Request Received (fee)
|
|
FEE REC'D TO REVIEW WORK PLAN
|
|
2006-02-27
|
98
|
Technical Assistance Provided
|
|
FEE REC'D TO REVIEW WORK PLAN
|
|
2005-03-09
|
99
|
Miscellaneous
|
|
2004 ANNUAL REPORT
|
|
2005-02-11
|
99
|
Miscellaneous
|
|
DNR REQUEST FOR FEE TO REVIEW SUBMITTAL
|
|
2005-01-27
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
STS RESPONSE TO DNR & WORK PLAN FOR ADDITIONAL INVESTIGATION
|
|
2003-09-30
|
99
|
Miscellaneous
|
|
REQUEST FROM ATTORNEY LINDA MAYA FOR DEED RESTRICTION
|
|
2003-05-13
|
99
|
Miscellaneous
|
|
2001, 2002 REPORT APPROVAL LETTER, IDENTIFIED WORK NEEDED FOR ROD AMENDMENT
|
|
2003-05-13
|
99
|
Miscellaneous
|
|
RESPONSE TO ANNUAL REPORT & TO STS JUSTIFICATION FOR THE ROB AMENDMENT.
|
|
2003-04-09
|
99
|
Miscellaneous
|
|
2002 ANNUAL MONITORING REPORT
|
|
2003-01-21
|
97
|
Technical Assistance Request Received (fee)
|
|
TECH ASSISTANCE REGARDING JUSTIFICATION FOR ROD AMENDMENT
|
|
2003-01-21
|
98
|
Technical Assistance Provided
|
|
TECH ASSISTANCE PROVIDED REGARDING JUSTIFICATION FOR ROD AMENDMENT
|
|
2003-01-21
|
99
|
Miscellaneous
|
|
JUSTIFICATION FOR ROD AMENDMENT RECEIVED
|
|
2002-04-12
|
99
|
Miscellaneous
|
|
O & M FLARE REQUIREMENTS
|
|
2002-04-05
|
99
|
Miscellaneous
|
|
2001 ANNUAL MONITORING REPORT
|
|
2001-04-20
|
170
|
Registry of Waste Disposal Site Screening Completed
|
|
|
|
2001-03-22
|
99
|
Miscellaneous
|
|
2000 ANNUAL REPORT APPROVAL
|
|
2001-03-19
|
99
|
Miscellaneous
|
|
2000 ANNUAL RPT
|
|
2000-05-19
|
99
|
Miscellaneous
|
|
1999 ANNUAL RPT APPROVAL
|
|
2000-03-22
|
99
|
Miscellaneous
|
|
1999 ANNUAL RPT
|
|
1999-05-27
|
99
|
Miscellaneous
|
|
1998 ANNUAL RPT APPROVAL
|
|
1999-03-08
|
99
|
Miscellaneous
|
|
ANNUAL (1998) RPT
|
|
1999-02-26
|
99
|
Miscellaneous
|
|
CLOSURE OF GUSTAFSON OIL #02-37-000507
|
|
1998-11-19
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
1998-11-18
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
1998-09-04
|
99
|
Miscellaneous
|
|
1997 ANNUAL REPORT APPROVAL
|
|
1998-06-09
|
99
|
Miscellaneous
|
|
ANNUAL (1997) RPT
|
|
1997-12-04
|
355
|
Superfund No Further Remedial Action Planned (NFRAP)
|
|
EPA SUPERFUND DATABASE.
|
|
1996-01-31
|
99
|
Miscellaneous
|
|
ANNUAL (1995) REPORT
|
|
1995-10-01
|
99
|
Miscellaneous
|
|
GAS CONTROL REPORT
|
|
1995-06-01
|
208
|
Remedial Design End - State Lead
|
|
|
|
1995-06-01
|
210
|
Remedial Construction End - State Lead
|
|
|
|
1995-06-01
|
211
|
Operation & Maintenance Start - State Lead
|
|
|
|
1995-06-01
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
|
|
1995-06-01
|
93
|
Operation & Maintenance (O&M) Report Approved
|
|
|
|
1995-05-01
|
192
|
Operation & Maintenance (O & M) Report Received (fee)
|
|
|
|
1994-08-26
|
99
|
Miscellaneous
|
|
CONSENT DECREE
|
|
1994-08-26
|
59
|
Environmental Enforcement Action Completed
|
|
CONSENT DECREE
|
|
1994-03-01
|
209
|
Remedial Construction Start - State Lead
|
|
|
|
1993-01-01
|
207
|
Remedial Design Start - State Lead
|
|
REMEDIAL DESIGN
|
|
1992-07-22
|
99
|
Miscellaneous
|
|
ROD
|
|
1992-07-22
|
149
|
Remedial Action (RA) Design Report Approved
|
|
|
|
1992-07-22
|
314
|
Superfund Decision Document (ROD or ESD) - See Description
|
|
ROD
|
|
1992-04-30
|
206
|
Site Investigation End - State Lead
|
|
|
|
1991-06-14
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
REMEDIAL INVESTIGATION REPORT
|
|
1991-02-12
|
205
|
Site Investigation Start - State Lead
|
|
|
|
1990-06-01
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
1989-10-12
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
REMEDIAL INVESTIGATION/FEASIBILITY WORK PLAN
|
|
1988-12-01
|
99
|
Miscellaneous
|
|
REMEDIAL INVESTIGATION/FEASIBILITY STUDY
|
|
1988-05-13
|
23
|
Referral to Department of Justice (DOJ)
|
|
PCP SITE
|
|
1986-11-06
|
351
|
Superfund Site Assessment Site Inspection (SI)
|
|
EPA SUPERFUND DATABASE.
|
|
1985-09-26
|
350
|
Superfund Site Assessment Preliminary Assessment (PA)
|
|
EPA SUPERFUND DATABASE.
|
|
1984-09-01
|
303
|
Superfund Site Assessment Action Taken - Not on NPL or SAS
|
|
FROM EPA SUPERFUND DATABASE.
|