ACTIVITY DETAILS

 
02-65-001069 ELKHORN METAL FINISHERS
Activity Type / Status Jurisdiction
ERP  CLOSED DNR RR
Location Name County DNR Region
ELKHORN METAL FINISHERS INC WALWORTH SOUTHEAST
Address Municipality
205 W CENTRALIA ST ELKHORN
PLSS Description Latitude (WGS84) Longitude (WGS84) Google Maps RR Sites Map
SW 1/4 of the NE 1/4 of Sec 01, T02N, R16E 42.665744 -88.5471561 Click to view on Google Maps using Lat/Long Click to View RR Sites Map
Additional Activity Details Acres
1
Facility ID PECFA No. EPA ID Start Date End Date
265008590 1980-01-01 2020-01-02
Characteristics
Above Ground
Petrol Tank

Drycleaner
EPA
NPL Site
EPA
Superfund
PECFA Funds
Eligible

PFAS

ROW Impact

Sediments
Underground
Petrol Tank
WI DOT
Site
  ROW Impact flag
Actions
Date Code Name File Comment
2020-01-06 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2019 - 12/31/2019
2020-01-02 11 Activity Closed
2020-01-02 56 Continuing Obligation(s) Applied Download PDF file
2020-01-02 222 Continuing Obligation - Maintain Cap Over Contaminated Area
2020-01-02 232 Continuing Obligation - Residual Soil Contamination
2020-01-02 236 Continuing Obligation - Residual GW Contamination
2020-01-02 66 Continuing Obligations (COs) Apply at Off-site Property(ies)
2020-01-02 46 Impacted Right-of-Way (ROW) Notification
2020-01-02 226 Continuing Obligation - Vapor Intrusion Response
2020-01-01 199 Additional Information Received (Fee-Based or Closure)
2019-07-02 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2019 - 6/30/2019
2019-01-09 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2018 - 12/31/2018
2019-01-03 198 Request for Additional Information (Fee-Based or Closure) PAUSE
2018-12-03 79 Case Closure Review Request Received Download Compressed Zip file AUTO-ENTERED
2018-11-29 700 Database Fee Paid for Groundwater Continuing Obligation(s) REC'D CK #331045 $350.00
2018-11-29 710 Database Fee Paid for Soil Continuing Obligation(s) REC'D CK #331045 $300.00
2018-11-29 779 Case Closure Review Fee Received REC'D CK #331045 $1050.00
2017-10-19 43 Site Activity Status Update Received PROGRESS REPORT #2
2016-12-08 43 Site Activity Status Update Received PROGRESS REPORT 2
2016-04-18 43 Site Activity Status Update Received GROUNDWATER SAMPLING REPORT
2016-04-07 43 Site Activity Status Update Received SITE CONSTRUCTION UPDATE
2013-12-23 43 Site Activity Status Update Received PROGRESS REPORT
2013-05-20 43 Site Activity Status Update Received PROGRESS REPORT #1
2012-11-01 43 Site Activity Status Update Received GROUNDWATER SAMPLING BID SELECTON
2012-02-27 43 Site Activity Status Update Received GW SAMPLING RESULTS
2011-09-07 130 DNR Regulatory Reminder Sent Download PDF file Vapor Intrusion (VI) Assessment Notification Ltr Sent
2011-06-22 64 Inject/Infiltrate Request Approved
2011-04-06 43 Site Activity Status Update Received INJECTION AND WPDES PERMIT REQUEST
2010-02-08 99 Miscellaneous RELEASE OF ENV LIEN
2009-02-18 99 Miscellaneous DEMOLITION SAFETY PLAN AND SCHEDULE
2008-10-24 209 Remedial Construction Start - State Lead BUILDING DEMOLITION BID
2008-01-02 43 Site Activity Status Update Received PRE DEMOLITION ASBESTOS INSPECTION AND LEAD PAINT SAMPLING
2007-11-15 43 Site Activity Status Update Received GROUNDWATER MODEL REPORT
2006-02-16 99 Miscellaneous ENV LIEN ON PROPERTY
2005-11-29 43 Site Activity Status Update Received GROUNDWATER MONITORING SUMMARY REPORT,MD12/6/05
2005-05-31 99 Miscellaneous ENV LEIN ON PROPERTY
2005-04-05 43 Site Activity Status Update Received GROUND WATER MONITORING SUMMARY REPORT
2004-10-19 43 Site Activity Status Update Received CONTAMINATION ASSESSMENT REPORT
2003-07-17 353 Superfund Site Assessment Expanded Site Inspection (ESI)
2003-07-17 354 Superfund Site Assessment Other Cleanup Authority (OCA)
2002-06-19 2 Responsible Party (RP) letter sent RP LETTER SENT
1991-12-26 351 Superfund Site Assessment Site Inspection (SI)
1987-09-04 350 Superfund Site Assessment Preliminary Assessment (PA)
1980-01-01 1 Notification of Hazardous Substance Discharge
Substances
Substance Type Amt Released Units
Petroleum - Unknown Type Petroleum
Responsible Party
SAM TAPSON 9 SOUTH BROAD ST, ELKHORN, WI 53121
For More Information on this Activity
Southeast Region Contact: Jenny Meyer  jennifer.meyer1@wisconsin.gov