02-36-555544
JAGEMANN PLATING CO INC
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
JAGEMANN PLATING CO INC | MANITOWOC | NORTHEAST |
Address | Municipality |
---|---|
1324 S 26TH ST | MANITOWOC |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
SE 1/4 of the SE 1/4 of Sec 25, T19N, R23E | 44.0831187 | -87.6816333 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
Electronic Only - No Hard File; Site File 2010 thru 10/15/2014 | UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
436041980 | 2010-07-07 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Name | File |
---|---|
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-07-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-04-11 | 43 | Site Activity Status Update Received |
![]() |
REMEDIAL PROGRESS AND RESULTS REPORT, FIRST QUARTER 2024 (GROUNDWATER, VAPOR, METHANE GAS) | |
2024-04-02 | 7 | Environmental Consultant Hired |
![]() |
R. SCOTT POWELL FROM ENVIROFORENSICS TOOK OVER FOR WAYNE FASSBENDER | |
2024-01-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-12-22 | 43 | Site Activity Status Update Received |
![]() |
REMEDIAL PROGRESS AND RESULTS REPORT; GW MONITOR VOC AND PFAS, METHANE MONITOR, ADD'L VAPOR SI | |
2023-12-13 | 364 | VAL and/or VRSL Exceeded | |||
2023-11-17 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
||
2023-11-10 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
FURTHER SITE INVESTIGATION AND COMPLIANCE UPDATES | |
2023-10-24 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER AND VAPOR SAMPLING UPDATE AND TIMING OF NEXT WORK PLAN SUBMITTAL | |
2023-08-24 | 43 | Site Activity Status Update Received |
![]() |
3RD QUARTERLY POST-REMEDIAL SAMPLING RESULTS | |
2023-07-05 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-06-30 | 43 | Site Activity Status Update Received |
![]() |
A-1 RADON PRESSURE FIELD EXTENSION READINGS AND SUB-SLAB VAPOR MITIGATION SYSTEM PERFORMANCE | |
2023-06-02 | 99 | Miscellaneous |
![]() |
PREVIOUS OUTSTANDING ITEMS FOR OM&M & VAPOR AND QUESTIONS REGARDING PREVIOUSLY PROPOSED WORK | |
2023-05-12 | 43 | Site Activity Status Update Received |
![]() |
2ND QUARTERLY POST-REMEDIAL SAMPLING RESULTS | |
2023-02-21 | 43 | Site Activity Status Update Received |
![]() |
1ST QUARTERLY POST-REMEDIAL SAMPLING RESULTS AND ONE SUB-SLAB VAPOR SAMPLE IN MOST CONTAMINATED AREA | |
2023-02-13 | 43 | Site Activity Status Update Received |
![]() |
ENVIROFORENSICS CONTACT CHANGE TO WAYNE FASSBENDER | |
2023-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2023-01-05 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
FULL SCALE INJECTION DOCUMENTATION | |
2022-11-18 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO RAP-IMPLEMENT FULL SCALE INJECTION UNDER CURRENT INJECTION & WPDES PERMIT APPROVALS | |
2022-11-18 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO ADDITIONAL INVESTIGATION - MORE INVESTIGATION NEEDED & CONTINUE MONITORING PFAS | |
2022-11-10 | 147 | Remedial Action (RA) Design Report Received (non-fee) |
![]() |
FOR FULL SCALE INJECTION IMPLEMENTATION | |
2022-10-26 | 43 | Site Activity Status Update Received |
![]() |
NR 716.14 DATA TRANSMITTAL - SOIL AND GROUNDWATER SAMPLING RESULTS | |
2022-10-25 | 43 | Site Activity Status Update Received |
![]() |
ADDT'L SOIL AND GROUNDWATER INVESTIGATION WORK FROM MAY 2022 WORK PLAN COMPLETED | |
2022-10-21 | 43 | Site Activity Status Update Received |
![]() |
PILOT INJECTION & GW MONITORING COMPLETED, FULL SCALE PLAN TO BE SUBMITTED FOR NOV 2022 START | |
2022-07-19 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-07-11 | 43 | Site Activity Status Update Received |
![]() |
INJECTION PILOT STUDY TO BEGIN ON JULY 18, 2022 | |
2022-06-13 | 64 | Inject/Infiltrate Request Approved |
![]() |
||
2022-06-08 | 63 | Inject/Infiltrate Request Received (fee) |
![]() |
||
2022-05-31 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
||
2022-05-24 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
ADDITIONAL SOIL AND GROUNDWATER SAMPLE LOCATIONS FOR DEGREE AND EXTENT AND SAMPLE EXISTING WELLS | |
2022-05-18 | 99 | Miscellaneous |
![]() |
DNR COMMENTS FOR VAPOR INVESTIGATION AND MONITORING | |
2022-04-20 | 99 | Miscellaneous |
![]() |
DNR COMMENTS FOR OPERATION, MONITORING, & MAINTENANCE PLAN | |
2022-03-24 | 43 | Site Activity Status Update Received |
![]() |
SOIL AND GROUNDWATER RESULTS FOR VOCS, METALS, AND PFAS | |
2022-03-24 | 43 | Site Activity Status Update Received |
![]() |
RPT WITH CORRECTED VAPOR FIGURE FROM VAPOR & INDOOR AIR RESULTS RPT PREVIOUSLY SUBMITTED 02/17/2022 | |
2022-02-17 | 43 | Site Activity Status Update Received |
![]() |
JANUARY 2022 SUB-SLAB VAPOR AND INDOOR AIR MONITORING RESULTS FROM INTERIM ACTION RPT & OM&M PLAN | |
2022-01-14 | 43 | Site Activity Status Update Received |
![]() |
PFAS GROUNDWATER RESULTS FROM CURRENT MONITORING WELLS ON-SITE | |
2022-01-14 | 120 | PFAS Sampling Completed - Actionable Levels Detected | SEE AC 43 OF SAME DATE FOR DOCUMENTATION | ||
2022-01-04 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2021-12-10 | 43 | Site Activity Status Update Received |
![]() |
DEPT OF HEALTH SERVICES COMMENTS ON VAPOR MONITORING PLAN INCLUDED IN INTERIM ACTION DOC RPT | |
2021-12-09 | 36 | Site Investigation Workplan (SIWP) Approved |
![]() |
COMMENTS INCLUDED FOR ADDT'L EVALUATION & REPORTING FOR INVESTIGATION AND REMEDIAL ACTION PLANNING | |
2021-11-29 | 99 | Miscellaneous |
![]() |
APPROVAL TO SAMPLE OUTSIDE WELLS PRIOR TO OFFICIAL SI WORK PLAN APPROVAL LETTER | |
2021-11-12 | 135 | Site Investigation Workplan (SIWP) Received (fee) |
![]() |
INCLUDES SUPPLEMENTAL INVESTIGATION RESULTS FOR VAPOR, INDOOR AIR, SEWER VAPOR, & GROUNDWATER | |
2021-11-10 | 126 | Interim Action Report Received (non-fee) |
![]() |
DOCUMENTATION REPORT AND OPERATION, MONITORING, & MAINTENANCE PLAN | |
2021-09-16 | 99 | Miscellaneous |
![]() |
CORRESPONDENCE FOR INTERIM ACTION PLANNING TO ADDRESS ON-SITE VAPOR CONCERNS | |
2021-08-05 | 99 | Miscellaneous |
![]() |
REMINDER THAT PFAS SAMPLING SHOULD OCCUR PRIOR TO REMEDIATION | |
2021-07-07 | 99 | Miscellaneous |
![]() |
VAPOR REVIEW AND DNR CONSULT WITH DHS | |
2021-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-06-23 | 43 | Site Activity Status Update Received |
![]() |
SUMMARY OF SUB-SLAB, INDOOR AIR, AND SANITARY SEWER VAPOR RESULTS | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-03-24 | 99 | Miscellaneous |
![]() |
CLARIFICATIONS ON PROPOSED VAPOR PIN SAMPLE LOCATIONS | |
2021-03-09 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
SUPPLEMENTAL SITE INVESTIGATION RESULTS AND PROPOSED ADDITIONAL WORK | |
2021-01-21 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2020-12-02 | 99 | Miscellaneous |
![]() |
CLARIFICATIONS ON THE VAPOR MITIGATION SYSTEM, OMM PLAN, AND VAPOR INVESTIGATION | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-07-29 | 43 | Site Activity Status Update Received |
![]() |
OPERATION, MONITORING, AND MAINTENANCE PLAN FOR VAPOR MITIGATION SYSTEM | |
2020-07-22 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-07-01 | 43 | Site Activity Status Update Received |
![]() |
VAPOR MITIGATION SYSTEM/OMM INSPECTION AND COORDINATION OF ADDT'L VAPOR SAMPLING | |
2020-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2020-01-17 | 43 | Site Activity Status Update Received |
![]() |
DOCUMENTATION OF SANITARY SEWER AND STORM UTILITIES | |
2019-12-03 | 99 | Miscellaneous |
![]() |
VAPOR REVIEW | |
2019-11-12 | 116 | PFAS Sampling Required |
![]() |
PFAS SAMPLING WORKPLAN REQUEST DUE: 01/13/2020 | |
2019-07-23 | 114 | PFAS Scoping Statement Received | SITE REVIEWED BY DNR FOR PFAS SAMPLING REQUIREMENT PRIOR TO FORMAL SCOPING PROCESS IMPLEMENTATION | ||
2019-07-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-06-19 | 43 | Site Activity Status Update Received |
![]() |
MARCH 2019 GROUNDWATER SAMPLING | |
2019-02-19 | 43 | Site Activity Status Update Received |
![]() |
VAPOR SAMPLING RESULTS FOR OFF-SITE PROPERTY | |
2019-02-05 | 43 | Site Activity Status Update Received |
![]() |
UPDATES ON SUB-SLAB VAPOR SAMPLING ON OFF-SITE PROPERTY | |
2019-01-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2018 - 12/31/2018 | |
2018-08-17 | 99 | Miscellaneous |
![]() |
CLARIFICATION ON SUB-SLAB VAPOR SAMPLE LOCATIONS | |
2018-07-27 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2018 - 6/30/2018 | |
2018-01-26 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2017 - 12/31/2017 | |
2018-01-08 | 43 | Site Activity Status Update Received |
![]() |
RESPONSE TO ADDITIONAL INVESTIGATION FOLLOW UP QUESTIONS | |
2017-11-28 | 99 | Miscellaneous |
![]() |
ADDT'L INVESTIGATION FOLLOW-UP QUESTIONS | |
2017-11-20 | 99 | Miscellaneous |
![]() |
CLARIFICATION REQUESTED FOR ADDT'L PROPOSED SITE INVESTIGATION | |
2017-10-16 | 43 | Site Activity Status Update Received |
![]() |
UPDATE TO OFF-SITE PROPERTY OWNERS FOR SI & NEXT STEPS | |
2017-10-13 | 43 | Site Activity Status Update Received |
![]() |
ADDT'L INFO FOR PROPOSED SITE INVESTIGATION | |
2017-07-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2017 - 6/30/2017 | |
2017-05-24 | 99 | Miscellaneous |
![]() |
CLARIFICATIONS FOR SI REPORT | |
2017-04-28 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
||
2017-02-17 | 43 | Site Activity Status Update Received |
![]() |
NEW WELLS INSTALLED AND SAMPLED, ADDT'L SI REPORT TO BE SUBMITTED | |
2017-02-10 | 99 | Miscellaneous |
![]() |
STATUS UPDATE REQUESTED | |
2017-01-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2016 - 12/31/2016 | |
2016-08-11 | 43 | Site Activity Status Update Received |
![]() |
REQUEST FOR PERMISSION TO INSTALL GW MONITORING WELLS & PIEZOMETERS OFF-SITE | |
2016-07-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2016 - 6/30/2016 | |
2016-06-20 | 99 | Miscellaneous |
![]() |
STATUS UPDATE REQUESTED FOR ADDT'L SI ACTIVITES | |
2016-04-01 | 99 | Miscellaneous |
![]() |
REQUEST STATUS UPDATE FOR ADDT'L SITE INVESTIGATION ACTIVITIES | |
2016-02-04 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2015 - 12/31/2015 | |
2015-10-06 | 43 | Site Activity Status Update Received |
![]() |
STATUS UPDATE REC'D: INTERIM ACTIONS BEING CONDUCTED AT SITE | |
2015-09-11 | 99 | Miscellaneous |
![]() |
STATUS UPDATE REQUEST LETTER ISSUED | |
2015-07-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-07-14 | 99 | Miscellaneous |
![]() |
REQUEST STATUS UPDATE | |
2015-02-16 | 99 | Miscellaneous |
![]() |
NEW DNR PROJECT MANAGER ASSIGNED | |
2015-02-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-10-28 | 36 | Site Investigation Workplan (SIWP) Approved |
![]() |
APPROVED W/CONDITIONS | |
2014-10-15 | 199 | Additional Information Received (Fee-Based or Closure) | CONSULTANT PROVIDED INFORMATION REQUESTED BY THE DEPT | ||
2014-09-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-08-19 | 198 | Request for Additional Information (Fee-Based or Closure) | REQUEST FOR ADDT'L INFORMATION | ||
2014-07-10 | 135 | Site Investigation Workplan (SIWP) Received (fee) | |||
2014-03-24 | 99 | Miscellaneous | TELCON WITH CONSULTANT ABOUT VI RESULTS AND FURTHER WORK | ||
2014-01-27 | 43 | Site Activity Status Update Received | TVI MONITORING TO BE COMPLETED ON 2/9/2014. GW MONITORING ON 3/2014 | ||
2013-06-14 | 43 | Site Activity Status Update Received | NEW MWS INSTALLED & TO BE SAMPLED IN JULY 2013 | ||
2013-03-01 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | NOTICE TO PROCEED WITH FINAL WORKPLAN | ||
2013-02-27 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | REVISED FINAL SI WORKPLAN WITH VI WORKPLAN RECEIVED | ||
2013-02-18 | 99 | Miscellaneous | DEPT REVIEW COMMENTS ON SIWP | ||
2013-02-08 | 43 | Site Activity Status Update Received | CONSULTANT MEETING WITH RP ON FEB 11 TO DISCUSS PROPOSED WP | ||
2013-01-25 | 3 | Notice of Noncompliance (NON) Issued | NON - FAILURE TO COMPLETE SI IN A TIMELY MANNER | ||
2012-10-22 | 99 | Miscellaneous | CONSULTANT WORKING ON CONTRACT TO COMPLETE ENVIRONMENTAL WORK | ||
2012-10-19 | 99 | Miscellaneous | STATUS UPDATE REQUESTED | ||
2012-06-14 | 43 | Site Activity Status Update Received | COMPLETING COMPLIANCE AUDIT, VI INVESTIGATION WORK TO START IN JULY 2012 | ||
2012-06-12 | 99 | Miscellaneous | STATUS UPDATED REQUESTED | ||
2011-12-07 | 43 | Site Activity Status Update Received | WELLS SAMPLED IN FALL, LOOKING AT POTENTIAL VI ISSUES | ||
2011-12-06 | 99 | Miscellaneous | STATUS UPDATE REQUESTED | ||
2011-09-08 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2011-01-28 | 43 | Site Activity Status Update Received | ADDITIONAL WEL INSTALLATION POSTPONED TO MARCH 2011 | ||
2010-12-16 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | NTP WITH ADDITIONAL BORINGS AND MONITORING WELLS | ||
2010-12-13 | 37 | Site Investigation Report (SIR) Received (non-fee) | PROJECT STATUS UPDATE: RECENT SI ACTIVITIES | ||
2010-08-02 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | NTP ON SWIP RECEIVED FROM ROBERT E LEE | ||
2010-07-27 | 43 | Site Activity Status Update Received | REL HIRED AS CONSULTANT | ||
2010-07-12 | 2 | Responsible Party (RP) letter sent | |||
2010-07-07 | 1 | Notification of Hazardous Substance Discharge | WATER SAMPLING - 6/22/2010 |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Chromium | Metals | ||
Per- and Polyfluoroalkyl Substances | Industrial Chem | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
JAGEMANN PLATING CO INC 1324 S 26TH ST, MANITOWOC, WI 54220 |
TAUREN BEGGS tauren.beggs@wisconsin.gov |