ACTIVITY DETAILS

 
02-36-578316 HAMILTON INDUSTRIES SITE (FORMER)
Activity Type / Status Jurisdiction
ERP  OPEN DNR RR
Location Name County DNR Region
FISHER HAMILTON LLC MAIN PLT MANITOWOC NORTHEAST
Address Municipality
1316 18TH STREET TWO RIVERS
PLSS Description Latitude (WGS84) Longitude (WGS84) Google Maps RR Sites Map
SE 1/4 of the NE 1/4 of Sec 01, T19N, R24E 44.1478109 -87.5646683 Click to view on Google Maps using Lat/Long Click to View RR Sites Map
Additional Location Description
INTER 16TH ST & E RIVER ST(VACATED)
Additional Activity Details Acres
Electronic Only - No Hard File UNKNOWN
Facility ID PECFA No. EPA ID Start Date End Date
436034060 2016-10-25
Characteristics
Above Ground
Petrol Tank

Drycleaner
EPA
NPL Site
EPA
Superfund
PECFA Funds
Eligible

PFAS

ROW Impact

Sediments
Underground
Petrol Tank
WI DOT
Site
  PFAS flag
Actions and Documents
Date Code Name File Comment
2024-07-23 98 Technical Assistance Provided Download PDF file FOR OFF-SITE EVALUATION OF PFAS
2024-07-05 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2024 - 6/30/2024
2024-05-10 97 Technical Assistance Request Received (fee) Download PDF file OFF-SITE EVALUATION OF PFAS
2024-05-03 43 Site Activity Status Update Received Download PDF file ANNUAL REPORT - JANUARY TO DECEMBER 2023 (QUARTERLY GROUNDWATER MONITORING)
2024-03-08 99 Miscellaneous Download PDF file COMMENTS FOR PROPOSED WELL LOCATIONS
2024-03-06 43 Site Activity Status Update Received Download PDF file ADDITIONAL MONITORING WELL LOCATIONS PROPOSED FOR PFAS INVESTIGATION & GENERAL COMMENTS TO PLAN
2024-02-16 64 Inject/Infiltrate Request Approved Download PDF file INJECTION TO GROUNDWATER FOR CVOC REMEDIATION
2024-01-22 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2023 - 12/31/2023
2024-01-16 63 Inject/Infiltrate Request Received (fee) Download PDF file INJECTION TO GROUNDWATER FOR CVOC REMEDIATION
2023-10-09 99 Miscellaneous Download PDF file RESPONSE TO ADDITIONAL INVESTIGATION RESULTS FOR PCBS AND PFAS SUBMITTED IN AUGUST 2023
2023-08-24 43 Site Activity Status Update Received Download PDF file GROUNDWATER ANALYTICAL RESULTS FOR POLYFLUORINATED ALKYL SUBSTANCES (PFAS)
2023-08-22 43 Site Activity Status Update Received Download PDF file ADDITIONAL SITE INVESTIGATION RESULTS (PCBS)
2023-07-31 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 01/01/2023 - 06/30/2023
2023-07-07 43 Site Activity Status Update Received Download PDF file ADDITIONAL PRE-REMEDIAL DESIGN INVESTIGATION ACTIVITIES IN CENTRAL VOC GROUNDWATER PLUME AREA
2023-06-02 99 Miscellaneous Download PDF file DNR RESPONSE TO ADDITIONAL EVALUATION OF PFAS
2023-04-12 43 Site Activity Status Update Received Download PDF file ADDITIONAL EVALUATION OF PFAS
2023-02-17 99 Miscellaneous Download PDF file CONCURRENCE THAT FURTHER EVALUATION OF SURFACE WATER AND SEDIMENT IS NOT WARRANTED
2023-01-30 43 Site Activity Status Update Received Download PDF file EAST TWIN RIVER AND HARBOR SEDIMENT STUDY - SURFACE WATER AND SEDIMENT EVALUATION
2023-01-30 43 Site Activity Status Update Received Download PDF file STATUS UPDATE ON WORK COMPLETED FROM 8/30/2022 WORK PLAN
2023-01-23 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2022 - 12/31/2022
2022-09-16 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2022-08-30 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file 2022 WORK PLAN ADDENDUM II - PRE-DESIGN GROUNDWATER AND SOIL INVESTIGATION
2022-08-22 43 Site Activity Status Update Received Download PDF file WORK PLAN TO BE SUBMITTED THIS WEEK
2022-07-22 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2022 - 6/30/2022
2022-05-04 98 Technical Assistance Provided Download PDF file RESPONSE TO CONTAMINANTS OF CONCERN AND MEDIA EVALUATION IN REPORT RECEIVED ON 3/18/2022
2022-03-18 97 Technical Assistance Request Received (fee) Download PDF file OCTOBER AND NOVEMBER 2021 ADDITIONAL GROUNDWATER AND SOIL INVESTIGATION REPORT
2022-03-18 120 PFAS Sampling Completed - Actionable Levels Detected
2022-01-24 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2021 - 12/31/2021
2021-12-10 43 Site Activity Status Update Received Download PDF file FOR ADDITIONAL SITE INVESTIGATION WORK
2021-09-23 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2021-09-10 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file ADDITIONAL SAMPLING IN SOIL AND/OR GW FOR METALS, PAHS, PCBS, PFAS, AND 1,4 DIOXANE
2021-07-28 28 Phase I Environmental Site Assessment (ESA) Rpt Received Download PDF file DATED FEBRUARY 1993, USED AS SUPPLEMENTAL INFO FOR SITE INVESTIGATION SCOPING
2021-07-26 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2021 - 6/30/2021
2021-07-16 40 Remedial Action Options Report (RAOR) Approved Download PDF file
2021-07-16 140 Site Investigation Report (SIR) Not Approved SEE REMEDIAL ACTION OPTIONS LETTER WITH THE SAME DATE FOR DOCUMENTATION
2021-07-16 116 PFAS Sampling Required AND 1,4 DIOXANE, DETERMINATION INCLUDED IN SI NOT APPROVED LETTER DATED 7/16/2021
2021-06-18 114 PFAS Scoping Statement Received Download PDF file
2021-06-18 199 Additional Information Received (Fee-Based or Closure)
2021-06-09 98 Technical Assistance Provided Download PDF file NO VAPOR MITIGATION REQUIRED AS A CONTINUING OBLIGATION FOR OFF-SITE HOTEL DEVELOPMENT
2021-05-20 198 Request for Additional Information (Fee-Based or Closure) Download PDF file NEED EMERGING CONTAMINANT SCOPING TO COMPLETE REVIEW OF REMEDIAL ACTION OPTIONS REPORT
2021-05-11 143 Remedial Action Options Report (RAOR) Received (fee) Download PDF file
2021-05-11 137 Site Investigation Report (SIR) Received (fee) SEE AC 143 OF SAME DATE FOR DOCUMENTATION
2021-05-03 99 Miscellaneous Download PDF file CLARIFICATIONS ON SUBMITTAL OF FEE FOR RAOR AND EMERGING CONTAMINANT SCOPING
2021-04-07 199 Additional Information Received (Fee-Based or Closure) Download PDF file VAPOR INTRUSION ASSESSMENT RESULTS REPORT RECEIVED FOR OFF-SITE HOTEL DEVELOPMENT
2021-04-06 130 DNR Regulatory Reminder Sent Download PDF file VAPOR INTRUSION AND TCE REMINDER LETTER
2021-03-29 43 Site Activity Status Update Received Download PDF file TIMELINE FOR SUBMITTING REPORT FOR ADDT'L SITE INVESTIGATION AND REMEDIAL ACTION OPTIONS EVALUATION
2021-01-25 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2020 - 12/31/2020
2020-11-11 99 Miscellaneous Download PDF file FOLLOW UP NEEDED FOR VAPOR ASSESSMENT/MITIGATION FOR TECHNICAL ASSISTANCE REQUEST FOR OFF-SITE HOTEL
2020-10-09 99 Miscellaneous Download PDF file EMERGING CONTAMINANT SCOPING REQUIRED FOR THE SITE INVESTIGATION
2020-10-08 43 Site Activity Status Update Received Download PDF file CLARIFICATIONS ON ACCESS AND OWNERSHIP OF MONITORING WELLS IN THE CITY OF TWO RIVERS ROW
2020-10-06 198 Request for Additional Information (Fee-Based or Closure) Download PDF file CALL NEEDED TO DISCUSS VAPOR ISSUES PRIOR TO ISSUING TECHNICAL ASSISTANCE LETTER FOR OFF-SITE HOTEL
2020-08-24 97 Technical Assistance Request Received (fee) Download PDF file OFF-SITE HOTEL REDEVELOPMENT VAPOR ASSESSMENT & MITIGATION DUE TO CVOC CONTAMINATION FROM THIS CASE
2020-08-17 130 DNR Regulatory Reminder Sent Download PDF file EMERGING CONTAMINANTS REMINDER LETTER
2020-07-14 43 Site Activity Status Update Received Download PDF file QUARTERLY GROUNDWATER MONITORING REPORT
2020-07-01 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2020 - 6/30/2020
2020-05-27 43 Site Activity Status Update Received Download PDF file UPDATE ON PROGRESS OF SITE INVESTIGATION WORK
2020-02-04 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2020-01-23 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file VAPOR INTRUSION EVALUATION WORK PLAN ADDENDUM 1
2020-01-02 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2019 - 12/31/2019
2019-09-13 43 Site Activity Status Update Received Download PDF file UTILITY INFORMATION FROM CITY OF TWO RIVERS
2019-08-23 99 Miscellaneous Download PDF file SITE INVESTIGATION CLARIFICATIONS
2019-08-08 43 Site Activity Status Update Received Download PDF file 5TH QUARTERLY GW SAMPLING EVENT AND ADDITIONAL NORTH INVESTIGATION SUMMARY
2019-07-22 43 Site Activity Status Update Received Download PDF file MW-22S ABANDONMENT PLAN CORRESPONDENCE BETWEEN DNR, CITY OF TWO RIVERS, AND ERM
2019-07-02 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2019 - 6/30/2019
2019-05-13 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2019-05-10 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file ADDITIONAL SI ON NORTH SIDE OF SITE
2019-04-25 140 Site Investigation Report (SIR) Not Approved Download PDF file ADD'L SI FOR CVOCS, CPAH ASSESS NO FURTHER SI FOR PAHS
2019-04-24 43 Site Activity Status Update Received Download PDF file REVISED SIGNATURE PAGE FOR 3/8/2019 SIR
2019-04-11 43 Site Activity Status Update Received Download PDF file REVISED PAH SOIL TABLE AND CPAH ASSESSMENT TABLES FOR 3/8/2019 SIR
2019-04-11 99 Miscellaneous Download PDF file REQUEST TO TWO RIVERS FOR INVESTIGATION OF MW-2 LNAPL AREA OFF-SITE
2019-03-08 137 Site Investigation Report (SIR) Received (fee) Download PDF file
2019-01-11 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2018 - 12/31/2018
2018-08-09 99 Miscellaneous Download PDF file SI UPDATE, INTEGRATION OF OFF-SITE DATA, & NO CURRENT VAPOR CONCERNS DUE TO BUILDING DEMO OFF-SITE
2018-08-06 99 Miscellaneous Download PDF file CORRESP WITH TWO RIVERS ON REDEVELOPMENT PLANS AND POTENTIAL VAPOR CONCERNS OFF-SITE
2018-07-25 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2018 - 6/30/2018
2018-05-11 99 Miscellaneous Download PDF file NOTIFICATION TO TWO RIVERS AND RP THAT TWO CITY PHASE II ESA'S INFO INTEGRATED INTO THIS CASE
2018-04-20 99 Miscellaneous Download PDF file VAPOR SAMPLING CLARIFICATIONS
2018-04-11 43 Site Activity Status Update Received Download PDF file SUETTINGER PHASE I ESA & CITY ROW ASSESSMENT INFORMATION RELEVANT TO CASE
2018-03-22 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2018-03-19 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file
2018-02-12 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file ADDITIONAL SI REPORT
2018-01-08 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2017 - 12/31/2017
2017-11-13 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2017-11-13 43 Site Activity Status Update Received Download PDF file NO SURFACE WATER CONCERNS FOR INVESTIGATION
2017-11-13 43 Site Activity Status Update Received Download PDF file UPDATE ON DELINEATION OF GW CONTAMINATION
2017-11-07 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file
2017-08-18 43 Site Activity Status Update Received Download PDF file CLARIFICATIONS FOR SI WORKPLAN
2017-08-18 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2017-08-17 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file
2017-07-05 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 1/1/2017 - 6/30/2017
2017-06-14 37 Site Investigation Report (SIR) Received (non-fee) Download PDF file
2017-05-24 43 Site Activity Status Update Received Download PDF file UPDATE FOR SI AND FREE PRODUCT
2017-04-27 43 Site Activity Status Update Received Download PDF file PETROLEUM LNAPL FOUND IN MW-2
2017-03-22 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2017-03-22 43 Site Activity Status Update Received Download PDF file RESPONSE TO SI WORKPLAN NOTICE TO PROCEED
2017-03-17 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file REVISED SI WORKPLAN
2017-02-22 29 Phase II Environmental Site Assessment (ESA) Rpt Received Download PDF file CITY OF TWO RIVERS PHASE II ESA ASSESSMENT ADJACENT TO SITE
2017-01-16 195 Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met Open NR700 Report Period: 7/1/2016 - 12/31/2016
2017-01-09 30 Site Investigation Workplan (SIWP) Notice to Proceed (NTP) Download PDF file
2017-01-06 35 Site Investigation Workplan (SIWP) Received (non-fee) Download PDF file
2017-01-06 43 Site Activity Status Update Received Download PDF file CITY PROVIDED UPDATE ON THEIR ADDITIONAL SAMPLING BEING DONE ADJACENT TO THE SITE
2016-12-19 7 Environmental Consultant Hired Download PDF file ERM
2016-11-18 2 Responsible Party (RP) letter sent Download PDF file
2016-11-09 99 Miscellaneous Download PDF file NOTIFICATION TO CONSULTANT AND OWNER THAT NEW CASE WILL BE CREATED AND RP LETTER ISSUED
2016-11-07 43 Site Activity Status Update Received Download PDF file UPDATE ON CITYS SAMPLING PLANS ADJACENT TO SITE
2016-10-31 43 Site Activity Status Update Received Download PDF file ADDITION INFORMATION FOR RELEASE NOTIFICATION REPORT
2016-10-31 43 Site Activity Status Update Received Download PDF file SPLIT SAMPLING DATA FOR RELEASE NOTIFICATION
2016-10-25 1 Notification of Hazardous Substance Discharge UTILITY EXCAVATION FOR CITY WATER LINE - 10/1/2016
2016-08-31 43 Site Activity Status Update Received Download PDF file NOTIFICATION OF RESULTS FROM CITY FOR CONTAMINATION POTENTIALLY MIGRATING FROM OFF-SITE SOURCE
2016-04-01 99 Miscellaneous Download PDF file ECONOMIC DEVELOPMENT NEWS ARTICLE
Substances
Substance Type Amt Released Units
1,4-Dioxane Industrial Chem
Lead (Pb) Metals
Metals Metals
Per- and Polyfluoroalkyl Substances Industrial Chem
Polychlorinated Biphenyl PCB
Polynuclear Aromatic Hydrocarbons Petroleum
Tetrachloroethene (Perchloroethylene) VOC
Trichloroethylene Industrial Chem
Volatile Organic Compounds VOC
Responsible Party
THERMO FISHER SCIENTIFIC 81 WYMAN ST, WALTHAM, MA 02451
DNR Project Manager
TAUREN BEGGS  tauren.beggs@wisconsin.gov
578316 | 02-36-578316