2023-12-12
|
99
|
Miscellaneous
|
|
CAP MAINTENANCE REPORT RECEIVED.
|
|
2023-11-30
|
99
|
Miscellaneous
|
|
RP QUESTIONS ABOUT FILLING OUT CAP MAINTENANCE FORM-HELP PROVIDED
|
|
2023-10-26
|
-
|
Closure
|
|
|
|
2023-10-11
|
99
|
Miscellaneous
|
|
REVISION TO CMP TEXT REQUESTED AND RECEIVED
|
|
2023-10-11
|
11
|
Activity Closed
|
|
|
|
2023-10-11
|
56
|
Continuing Obligation(s) Applied
|
|
|
|
2023-10-11
|
222
|
Continuing Obligation - Maintain Cap Over Contaminated Area
|
|
|
|
2023-10-11
|
232
|
Continuing Obligation - Residual Soil Contamination
|
|
MAINTAIN CAP ACROSS THE ENTIRE PROPERTY
|
|
2023-10-03
|
199
|
Info. Received or Request Ended (Fee-Based or Closure)
|
|
|
|
2023-09-12
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
PAUSE REVIEW FOR REVISIONS TO CLOSURE PACKET
|
|
2023-08-14
|
79
|
Case Closure Review Request Received
|
|
AUTO-ENTERED
|
|
2023-08-08
|
779
|
Case Closure Review Fee Received
|
|
RECVD CK #078077 $1050
|
|
2023-08-08
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
RECVD CK #078077 $300
|
|
2023-03-10
|
38
|
Site Investigation Report (SIR) Approved
|
|
APPROVAL WITH COMMENTS FOR PREPARATION OF CLOSURE PACKET
|
|
2023-03-10
|
805
|
Historic Waste Site
|
|
CINDERS, ASPHALT RUBBLE, BRICK, GLASS, CONCRETE, FOUNDRY MATERIAL ON SITE
|
|
2023-03-10
|
118
|
PFAS Sampling Not Required At This Time
|
|
|
|
2023-02-22
|
99
|
Miscellaneous
|
|
REVISED CAP MAINTENANCE PLAN FIGURE REQUESTED AND RECEIVED
|
|
2023-02-22
|
199
|
Info. Received or Request Ended (Fee-Based or Closure)
|
|
SIR REC'D WITH DISCUSSIONS MISSING FROM PREVIOUS RPTS
|
|
2023-02-21
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2023-02-21
|
114
|
PFAS Scoping Statement Received
|
|
|
|
2023-02-02
|
99
|
Miscellaneous
|
|
ADDITIONAL INFO NEEDED FOR SIR REVIEW; REPORT TO BE REVISED AND RESUBMITTED
|
|
2022-11-23
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2022-09-16
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
DISCUSSED WITH KAPUR ON 9/16-REVISED SIR COMING
|
|
2022-08-16
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
RECV'D CK #076947 $1050.00
|
|
2022-08-16
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
|
|
2022-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-01-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2021-11-03
|
80
|
Closure Not Recommended
|
|
NFA NOT APPROVED, NR 716 INVESTIGATION REQUIRED, SEE TA LTR
|
|
2021-11-03
|
98
|
Technical Assistance Provided
|
|
THIS SITE MUST PROCEED WITH NR 716 SI TO NR 726 CLOSURE
|
|
2021-10-18
|
199
|
Info. Received or Request Ended (Fee-Based or Closure)
|
|
ADDITIONAL INFORMATION AND RESPONSE TO DNR'S REVIEW OF NFA REQUEST
|
|
2021-09-14
|
99
|
Miscellaneous
|
|
ADDITIONAL EXPLANATION AND ADD'L INFO COMING
|
|
2021-09-10
|
99
|
Miscellaneous
|
|
INFORMATION REQUESTED IN 6/23/21 EMAIL NOT PROVIDED; PROVIDE ADD'L INFO FOR NFA REVIEW
|
|
2021-08-18
|
43
|
Site Activity Status Update Received
|
|
ENVIRONMENTAL ACTIVITIES UPDATE ADDENDUM
|
|
2021-07-09
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-06-23
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
ADDITIONAL INFORMATION NEEDED FOR REVIEW
|
|
2021-06-01
|
97
|
Technical Assistance Request Received (fee)
|
|
REC'D CK #075396 $700.00
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-01-13
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-01-14
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2019-07-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-04-26
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2019-04-19
|
1
|
Notification of Hazardous Substance Discharge
|
|
|