2024-10-22
|
43
|
Site Activity Status Update Received
|
|
SOIL SAMPLING RESULTS
|
|
2024-08-16
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
FOLLOW UP SOIL AND GROUNDWATER SAMPLING PROPOSED
|
|
2024-08-12
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2024-07-10
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2024 - 6/30/2024
|
|
2024-03-27
|
43
|
Site Activity Status Update Received
|
|
2023 SUPPLEMENTAL SITE INVESTIGATION FOR PFAS
|
|
2024-01-09
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-08-28
|
99
|
Miscellaneous
|
|
SITE INVESTIGATION STATUS UPDATE REQESTED
|
|
2023-06-30
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-03-02
|
99
|
Miscellaneous
|
|
FAA REVIEW OF SI ACTIVITIES
|
|
2023-01-19
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2023-01-13
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2022-12-19
|
200
|
Push Action Taken
|
|
|
|
2022-08-23
|
99
|
Miscellaneous
|
|
PROJECT TIMELINE UPDATE RECEIVED
|
|
2022-07-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-07-22
|
43
|
Site Activity Status Update Received
|
|
INITIAL PFAS SOIL AND GW RESULTS
|
|
2022-07-22
|
120
|
PFAS Sampling Completed - Actionable Levels Detected
|
|
|
|
2022-07-11
|
99
|
Miscellaneous
|
|
FIELD SAMPLE RESULTS DELAYED
|
|
2022-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2022-01-11
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
|
|
2022-01-11
|
116
|
PFAS Sampling Required
|
|
|
|
2022-01-06
|
199
|
Info. Received or Request Ended (Fee-Based or Closure)
|
|
RECEIVED UPDATED SIWP PROPOSAL
|
|
2022-01-06
|
99
|
Miscellaneous
|
|
UPDATED SIWP PROPOSAL
|
|
2021-12-22
|
198
|
Request for Additional Information (Fee-Based or Closure)
|
|
REQUESTED CHANGES TO SIWP
|
|
2021-11-19
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
|
|
2021-11-19
|
99
|
Miscellaneous
|
|
SIWP PRESS RELEASE
|
|
2021-11-19
|
7
|
Environmental Consultant Hired
|
|
AECOM
|
|
2021-11-19
|
114
|
PFAS Scoping Statement Received
|
|
PFAS SCOPING STATEMENT IN SIWP FROM 11/19/2021
|
|
2021-11-03
|
99
|
Miscellaneous
|
|
SIWP STATUS UPDATE
|
|
2021-08-05
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2021-07-06
|
1
|
Notification of Hazardous Substance Discharge
|
|
|