DEER LAKE CONSERVANCY INC: 319 LMI-Direct Drainage Runoff Reduction Projects
The Deer Lake Conservancy is sponsoring a project to install several best management practices that will reduce runoff into Deer Lake.
Project activities:
1)Shoreline buffer restoration, 2) Design and installation of raingardens and infiltration practices, 3) Culvert extension and road shoulder stabilization, 4) Sediment basin design and installation
Project deliverables include:
Design plans, Pre/post photographs, copies of landowner contracts, and a summary report with phosphorus loading reductions
Specific project conditions:
\2022 Buffer restoration shall follow Wisconsin Biology Technical Note 1: Shoreland Habitat.
\2022 All permits must be issued before construction, and all regulatory requirements apply.
\2022 The DNR logo should be used for promotion and publicity and DNR recognized as a funding source.
\2022 Projects that do not qualify as Healthy Lakes Best Practices require a 25-year operation & maintenance plan recorded on the property deed.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables
Project Type
|
LAKE_GRANT
-
Lake Protection Grant
|
Project ID
|
LPT62619
|
Year Started
|
2019
|
Status
|
COMPLETE
|
Final Report and Products
People/Organizations Involved