03-61-000116
JIMS AND CINDYS BAR
|
Activity Type / Status | Jurisdiction |
---|---|
LUST / CLOSED | DNR RR |
Location Name | County | DNR Region |
---|---|---|
JIMS BAR | TAYLOR | NORTHERN |
Address | Municipality |
---|---|
W14764 STH 73 | JUMP RIVER |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the SW 1/4 of Sec 07, T33N, R03W | 45.3532591 | -90.8006414 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
7 |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
861046010 | 54433-9769-64 | 1993-08-19 | 2021-12-10 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
![]() |
![]() |
Name | File |
---|---|
SITE FILE DOCUMENTATION FOR ACTIVITY | ![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2021-12-10 | 11 | Activity Closed | |||
2021-12-10 | 56 | Continuing Obligation(s) Applied |
![]() |
||
2021-12-10 | 224 | Continuing Obligation - Structural Impediment to Cleanup | |||
2021-12-10 | 232 | Continuing Obligation - Residual Soil Contamination | |||
2021-12-10 | 236 | Continuing Obligation - Residual GW Contamination | |||
2021-12-10 | 66 | Continuing Obligations (COs) Apply at Off-site Property(ies) | |||
2021-12-10 | 46 | Impacted Right-of-Way (ROW) Notification | |||
2021-10-13 | 199 | Additional Information Received (Fee-Based or Closure) | INFO REC'D | ||
2021-10-13 | 114 | PFAS Scoping Statement Received | PFAS SCOPING STATEMENT REC'D - W/ CLOSURE REVISION | ||
2021-07-15 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-01-15 | 99 | Miscellaneous |
![]() |
STATUS UPDATE REQUEST LETTER FOR CLOSURE REVISIONS | |
2021-01-13 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-07-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-06-08 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $203.06 - COMMODITY TO REPL SEDIMENT FILTERS AT 8891 BRIDGE RD | |
2020-06-05 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ - COMMODITY COSTS FOR SEDIMENT FILTER REPL AT 8891 BRIDGE RD | |
2020-06-04 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $1,318.76 - COMMODITY ADDT'L MW ABND COSTS, PREV APPRED 4/22/20 | |
2020-06-03 | 99 | Miscellaneous |
![]() |
MW AND SVE VENTS ABANDONMENT FORMS | |
2020-06-02 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ - COMMODITY ADDT'L MW ABND COSTS PREV APPRD 4/22/20 | |
2020-05-28 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $440.00 - VARIANCE TO REBED CARBON FILTER AT CONVENIENCE STORE | |
2020-05-27 | 504 | PECFA Cost Request Received |
![]() |
PECFA VAR COSTS REQ - FOR REBEDDING CARBON FILTER AT CONVENIENCE STORE | |
2020-04-27 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQUEST TO TEST CONV STORE NEW PW | |
2020-04-27 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $1,340.36 - TO TEST CONV STORE NEW PW | |
2020-04-22 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $2875.00 - ABAND SVE, CONCRETE REPAIR(CONV STORE), LAWN REPAIR | |
2020-04-21 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQUEST - ABAND OF SVE, CONCRETE REPAIR (CONV STORE) AND LAWN REPAIR | |
2020-04-21 | 99 | Miscellaneous |
![]() |
COMPLIANCE ASSISTANCE REQ - EXTEND DEADLINE FOR SUBMITTAL OF CLOSURE REVISIONS TO 5/30/20 | |
2020-04-21 | 99 | Miscellaneous |
![]() |
COMPLIANCE ASSISTANCE REQ - OK'D CLOSURE SUBMIT 5/30/20 | |
2020-04-17 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ - VAR TO DISCONNECT ELECTRICAL SERVICE TO SVE SYSTEM | |
2020-04-17 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COST APPR $500.00 - DISCONNECT ELECTRICAL SERVICE TO SVE SYSTEM BY COMMODITY | |
2020-04-03 | 99 | Miscellaneous |
![]() |
MW/PZ ABANDONMENT APPROVED BY CLOSURE COMMITTEE | |
2020-04-02 | 198 | Request for Additional Information (Fee-Based or Closure) | ADDTIONAL INFO REQUESTED | ||
2020-03-26 | 504 | PECFA Cost Request Received |
![]() |
PECFA VARIANCE REQ - H.U. NEW PW TO CONV STORE (8891 BRIDGE ST) | |
2020-03-26 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $975.00 - H.U. NEW PW TO CONV STORE (8891 BRIDGE ST) | |
2020-03-19 | 199 | Additional Information Received (Fee-Based or Closure) | INFO REC'D | ||
2020-03-17 | 198 | Request for Additional Information (Fee-Based or Closure) | ADDT'L INFO REQ | ||
2020-03-16 | 779 | Case Closure Review Fee Received | CK # 7050 | ||
2020-03-16 | 700 | Database Fee Paid for Groundwater Continuing Obligation(s) | CK # 7050 | ||
2020-03-16 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | CK # 7050 | ||
2020-03-16 | 79 | Case Closure Review Request Received | AUTO-ENTERED | ||
2020-03-03 | 43 | Site Activity Status Update Received |
![]() |
STATUS RPT REC'D | |
2020-02-03 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $1,129.60 - PE REVIEW OF CLOSURE PKG | |
2020-01-28 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ - U&C COST FOR PE REVIEW OF CLOSURE PKG | |
2020-01-23 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA REMINDER LETTER | |
2020-01-21 | 99 | Miscellaneous | REC'D INVOICE FOR NEW PW + RESULTS & ORIG WELL FOR CONV STORE | ||
2020-01-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2019-12-13 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COST APPR $800.00 - | |
2019-12-12 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ - | |
2019-12-05 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $11,645.14 - 4 RNDS MONTHLY CONV STORE PW. SVE OPERATION 3 MONTHS | |
2019-12-04 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ - 4 RNDS MONTHLY CONV STORE PW. SVE 3 MONTHS | |
2019-11-13 | 43 | Site Activity Status Update Received |
![]() |
STATUS RPT REC'D | |
2019-10-25 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $1,206.65 - REPLACE CARBON FILTERS AT 8891 BRIDGE RD CONV STORE | |
2019-10-25 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ - ADDT'L LAB DATA REVIEW FOR VI, ORIGINALLY APPR 3/8/16 | |
2019-10-25 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $150.00 - ADDT'L LAB DATA REVIEW FOR VI, ORIGINALLY APPR 3/8/16 | |
2019-10-23 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ - REPLACE CARBON FILTERS AT 8891 BRIDGE RD CONV STORE | |
2019-10-07 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COST APPR $13,857.42 - SURVEY & PW REPLACEMENT , 8891 BRIDGE ST | |
2019-10-04 | 99 | Miscellaneous | PW SAMPLING RESULTS REC'D - CONVENIENCE STORE | ||
2019-09-27 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ - SURVEY & PW REPLACEMENT , 8891 BRIDGE ST | |
2019-08-06 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COST APPR $25,103.00 - 2 RNDS GW ALL WELLS + PW'S, CLOSURE PKG, MW & SVE ABANDONMENT | |
2019-08-05 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ - 2 RNDS GW ALL WELLS + PW'S, CLOSURE PKG, MW & SVE ABANDONMENT | |
2019-07-30 | 43 | Site Activity Status Update Received |
![]() |
STATUS RPT REC'D - INSTALL MW, SOIL VAPOR EXTRACT VENTS, SVE, GW SAMPLING, FILTER REPAIRS | |
2019-07-25 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA REMINDER LETTER | |
2019-07-18 | 99 | Miscellaneous |
![]() |
CONV STORE PW RESULTS FOR JULY | |
2019-07-02 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-05-07 | 99 | Miscellaneous |
![]() |
PW RAW LABS REC'D RE: CONVENIENCE STORE WELL | |
2019-04-12 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $437.83 FOR ELECTRICIAN COSTS T&M FOR THERMOSTAT REPAIR ON SVE SYSTEM | |
2019-04-11 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS FOR ELECTRICIAN T&M FOR THERMOSTAT REPAIR - SVE SYSTEM | |
2019-03-27 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $2,789.18 MONTHLY GW 1 YR CONV STORE, FLOODING COORDINATION VARIANCE | |
2019-03-25 | 504 | PECFA Cost Request Received |
![]() |
REQ 1 YR MONTHLY GW MONITORING - CONV STORE WELL, FLOODING COORDINATION VARIANCE | |
2019-01-23 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA REMINDER LETTER | |
2019-01-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2018 - 12/31/2018 | |
2018-12-10 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $1,570.46 OVERSIGHT ABAND PW AT 14789 STH 73 | |
2018-12-07 | 504 | PECFA Cost Request Received |
![]() |
PECFA COST REQ OVERSIGHT ABAND PRIVATE WELL AT 14789 STH 73 | |
2018-09-04 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $300. FOR LAWN REPAIR DUE TO INSTALL MW | |
2018-09-02 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ FOR LAWN REPAIR DUE TO MW INSTALL | |
2018-08-23 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR - $700.00 FOR ELECTRICAL DISCONNECT KEEPER'S WELL | |
2018-08-18 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ FOR ELECTRICAL DISCONNECT FOR KEEPER'S WELL | |
2018-08-18 | 99 | Miscellaneous |
![]() |
NEW WELL LABS & PICTURES REC'D - W14789 HWY 73 | |
2018-08-08 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $161,795.23M 10-MW'S, SAMPLE ALL + PW'S, SVE INSTALL O&M-1YR | |
2018-08-06 | 504 | PECFA Cost Request Received |
![]() |
REQ TO INSTALL 10 MW'S, SAMPLE ALL + PW'S, SVE INSTALL O&M 1-YR | |
2018-07-25 | 505 | PECFA Cost Request Approved |
![]() |
PECFA COSTS APPR $300.00 FOR TREE BRANCH REMOVAL | |
2018-07-23 | 43 | Site Activity Status Update Received |
![]() |
REC'D STATUS RPT | |
2018-07-23 | 504 | PECFA Cost Request Received |
![]() |
PECFA COSTS REQ FOR TREE BRANCH REMOVAL FOR KEEPER'S PW INSTALL | |
2018-07-16 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2018 - 6/30/2018 | |
2018-07-16 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA REMINDER LETTER | |
2018-06-28 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $247.08, AIR SAMPLING, WASTE PUMP RENTAL OMITTED FROM 5/11/18 APPR | |
2018-06-27 | 504 | PECFA Cost Request Received |
![]() |
REQ COSTS FOR AIR SAMPLING, WASTE DISPOSAL & AIR PUMP RENTAL OMITTED FROM 5/11/18 APPR | |
2018-06-19 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $430.29 FOR DRY WEIGHT SAMPLING LAB. PRE APPR 4/13/18. | |
2018-06-15 | 504 | PECFA Cost Request Received |
![]() |
REQ COSTS FOR LAB DRY WEIGHT SAMPLING FROM PREV APPR 4/13/18 | |
2018-05-30 | 505 | PECFA Cost Request Approved |
![]() |
APPR COSTS $300.00 FOR LAWN CARE REPAIR BY COMMODITY | |
2018-05-29 | 504 | PECFA Cost Request Received |
![]() |
REQ LAWN REPAIR VARIANCE COSTS | |
2018-05-21 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR $4,801.22 - 2 MW'S + 2NDS-GW | |
2018-05-20 | 504 | PECFA Cost Request Received |
![]() |
REQ 2 MW'S + 2 RNDS | |
2018-05-11 | 505 | PECFA Cost Request Approved |
![]() |
APPR COSTS $7,140.16 - ADDT'L MW & 4" SVE VENTS | |
2018-05-01 | 504 | PECFA Cost Request Received |
![]() |
REQ FOR ADDT'L MW, AND 4" SVE VENTS INSTEAD OF 2" PREV APPROVED | |
2018-04-13 | 505 | PECFA Cost Request Approved |
![]() |
APPRV COSTS $51,835.05. 7 NEW MW'S, 2 RNDS-ALL WELL + PW'S, 9 BORINGS, NEW PW-KEEPER, RPT | |
2018-04-11 | 504 | PECFA Cost Request Received |
![]() |
REQ FOR 7 MW'S, 2 RNDS-ALL WELLS + PW'S, 9 BORINGS, NEW PW-KEEPERSLETTER RPT | |
2018-02-09 | 99 | Miscellaneous |
![]() |
SUMMARY NOTES RE: SITE MEETING | |
2018-01-26 | 505 | PECFA Cost Request Approved |
![]() |
COSTS APPR ($2,447.34) FILTER (CONV STORE), BOTTLED WATER (KEEPERS) - 1 YR | |
2018-01-19 | 504 | PECFA Cost Request Received |
![]() |
COST REQUEST FOR FILTERS & BOTTLED WATER - 1 YR | |
2018-01-16 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA REMINDER LETTER | |
2018-01-11 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2017 - 12/31/2017 | |
2018-01-11 | 43 | Site Activity Status Update Received |
![]() |
REC'D PROGRESS RPT | |
2017-07-18 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2017 - 6/30/2017 | |
2017-06-02 | 505 | PECFA Cost Request Approved |
![]() |
APPROVED COSTS ($15,407.29) NEW PZ, 2 RNDS ALL WELLS + PW'S, VAR FOR KEEPER WELL + CONV STORE FILTER | |
2017-06-01 | 504 | PECFA Cost Request Received | COST FOR NEW PZ, RNDS, SAMPLING ALL WELLS + PW'S, VAR FOR KEEPER WELL + CONV STORE FILTERS | ||
2017-01-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2016 - 12/31/2016 | |
2016-12-28 | 43 | Site Activity Status Update Received |
![]() |
STATUS RPT REC'D | |
2016-07-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2016 - 6/30/2016 | |
2016-03-18 | 505 | PECFA Cost Request Approved | APPV'L U&C $3,269.60, BOTTLED WATER CONV STORE SYSTEM & CONV STORE SMPLS. FOR 6 MNTHS, RE-EVALUATE | ||
2016-03-16 | 504 | PECFA Cost Request Received | REC'D U&C + VAR COSTS FOR TEMP INSTALL LGR SYSTEM - CONV STORE & BOTTLED WATER | ||
2016-03-08 | 505 | PECFA Cost Request Approved | APPROVED VARIANCE COSTS ($3,884.42) INCLUDES CHANGE ORDER U&C COST | ||
2016-02-27 | 504 | PECFA Cost Request Received | REC'D VARIANCE REQUEST FOR VI INVESTIGATION | ||
2016-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2015 - 12/31/2015 | |
2015-11-18 | 505 | PECFA Cost Request Approved | APPROVED U&C ($273.50) FOR INCREMENTAL MOB - T&C WATER SYSTEMS | ||
2015-11-12 | 504 | PECFA Cost Request Received | REC'D COSTS FOR INCREMENTAL MOB ASSOCIATED W/ T&C WATER SYSTEMS | ||
2015-10-31 | 505 | PECFA Cost Request Approved | APPROVED U&C + VAR ($9,439.00) FOR GW SAMPLING + PW ASSESSMENT | ||
2015-10-16 | 504 | PECFA Cost Request Received | REC'D U&C FOR GW MONITORING + VAR FOR PW ASSESSMENT | ||
2015-10-08 | 43 | Site Activity Status Update Received | REC'D GW MONITORING RPT | ||
2015-08-24 | 130 | DNR Regulatory Reminder Sent |
![]() |
PECFA SUNSET LETTER | |
2015-08-04 | 99 | Miscellaneous | 3RD ROUND OF SMAPLING COMPLETED ON 7/29/15 | ||
2015-07-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-06-29 | 99 | Miscellaneous | REPORT TO COME BY END OF JULY. MUST REPLACE WATER FILTER/ OBTAIN WELL REPL ESTIMATES | ||
2015-06-17 | 99 | Miscellaneous | EMAILED CONSULTANT RE: TIMELINE FOR LATEST APPROVED SOW | ||
2015-03-18 | 505 | PECFA Cost Request Approved | U&C APPROVAL ($7,143.60) NEW MW + SAMPLE PW N14810, 1 ROUND | ||
2015-03-03 | 505 | PECFA Cost Request Approved | SOW FOR NEW MW TO DEFINE EXTENT + PW SAMPLING (W14810) | ||
2015-02-20 | 504 | PECFA Cost Request Received | U&C NEW WELL + PW SAMPLE (N140180 HWY 73) 1 ROUND EACH | ||
2015-02-19 | 505 | PECFA Cost Request Approved | U&C ($1,157.60) PRE & POST TREATMENT SAMPLING #8891 FOR VERIFICATION | ||
2015-02-18 | 504 | PECFA Cost Request Received | SOW SAMPLING PW #8891 PRE & POST TREATMENT TO VERIFY SYSTEM WORKING | ||
2015-02-12 | 504 | PECFA Cost Request Received | SOW EMERGENCY SITUATION - IMPACTED PW'S (W14789, W14781, #8891) | ||
2015-02-12 | 505 | PECFA Cost Request Approved | APPROVED EMERGENCY COSTS ($2,327.50): $1,500-BOTTLED WATER & INSTALL OF TREATMENT SYSTEM W/4 FILTERS | ||
2015-02-10 | 99 | Miscellaneous | BOTTLED WATER NOTICES FROM DNR TO W14781 & W14789 (SHARED WELL) | ||
2015-01-29 | 99 | Miscellaneous | LATEST GW RESULTS SHOWED >PALS FOR #W14789 & W14781 STH 73. SENT LETTERS TO OWNERS | ||
2015-01-29 | 505 | PECFA Cost Request Approved | APPROVED U&C (891.90) SAMPLING PW'S #8891 & N14789 | ||
2015-01-28 | 504 | PECFA Cost Request Received | REC'D SOW RE: SAMPLING #8891 + #N14789 PW'S | ||
2015-01-22 | 508 | PECFA Cost Cap Adjustment | PECFA COST CAP REDUCTION FROM 12/29/14 APPROVAL FOR PER DIEMS ($859.10) | ||
2015-01-21 | 504 | PECFA Cost Request Received | PECFA COST REQUEST REC'D | ||
2015-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-12-29 | 505 | PECFA Cost Request Approved | PECFA COST CAP APPROVAL FOR OVERNIGHT PER DIEM ($1,516.90) | ||
2014-12-29 | 504 | PECFA Cost Request Received | PECFA COST REQUEST REC'D | ||
2014-11-11 | 99 | Miscellaneous | WAITING FOR PERMISSION FROM LIONS CLUB & LYNES. WANT TO DRILL IN DEC | ||
2014-10-31 | 505 | PECFA Cost Request Approved | U&C APPROVED FOR SAMPLING + 2 GEOPROBES ($21,727.50) | ||
2014-10-08 | 504 | PECFA Cost Request Received | REC'D SOW GW SAMPLING, GEOPROBES, RPT | ||
2014-09-19 | 43 | Site Activity Status Update Received |
![]() |
RESULTS OF RECENT WORK & CHANGE ORDER REC'D | |
2014-09-10 | 99 | Miscellaneous | EMAILED CONSULTANT FOR LATEST SAMPLING RESULTS/REPORT | ||
2014-07-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-06-02 | 99 | Miscellaneous | ADDT'L NW INSTALLED, SAMPLING COMPLETE, RPT COMING SOON | ||
2014-05-30 | 99 | Miscellaneous | EMAILED CONSULTANT FOR UPDATES | ||
2014-02-21 | 99 | Miscellaneous | EMAILED CONSULTANT FOR UPDATES; NEXT SAMPLING ROUND WILL BE IN MARCH 2014 | ||
2013-12-11 | 505 | PECFA Cost Request Approved | |||
2013-09-24 | 505 | PECFA Cost Request Approved | |||
2013-08-28 | 505 | PECFA Cost Request Approved | REC'D PECFA LTR / U&C WORKSHEET | ||
2013-08-22 | 99 | Miscellaneous | REC'D CHANGE ORDER FOR SAMPLING / NEW WELLS/ EXCAVATION | ||
2013-08-22 | 99 | Miscellaneous | REVIEWED CHANGE ORDER, & OK'D W/ ADDT'L PW SAMPLING | ||
2013-08-05 | 99 | Miscellaneous | EMAILED CONSULTANT FOR UPDATES | ||
2013-07-11 | 99 | Miscellaneous | CO/SOW TO BE SUBMITTED BY CONSULTANT | ||
2013-06-19 | 99 | Miscellaneous | OFF SITE PW TO RECEIVE BOTTLED WATER/ HEALTH ADVISORY SENT BY DG | ||
2013-06-04 | 99 | Miscellaneous | REVIEWED LATEST RESULTS | ||
2013-06-03 | 99 | Miscellaneous | REC'D LATEST MONITORING RESULTS: MW'S & PW'S | ||
2013-05-18 | 99 | Miscellaneous | PW SAMPLES WILL BE ANALYZED WITH FULL VOC ANALYSIS | ||
2013-03-07 | 99 | Miscellaneous | ALL PARTIES INVOLVED AGREED TO MODIFIED WP/COSTS. PW'S TO BE SAMPLED | ||
2013-02-01 | 43 | Site Activity Status Update Received | RC'D UPDATED WORK PLAN | ||
2013-02-01 | 99 | Miscellaneous | REVIEWED & OK'D WORK PLAN | ||
2013-01-28 | 99 | Miscellaneous | CONSULTANT SUBMITTED UPDATED SITE MAP | ||
2013-01-22 | 99 | Miscellaneous | REVIEWED & OK'D LATEST SAMPLING RESULTS | ||
2013-01-08 | 99 | Miscellaneous | REC'D WEBREPORT FOR LATEST SAMPLING FROM DSPS | ||
2012-10-19 | 99 | Miscellaneous | NEED TO CONTACT VILLAGE FOR ADDT'L PW INFO | ||
2012-10-18 | 99 | Miscellaneous | EMAILED CONSULTANT FOR UPDATES | ||
2012-08-21 | 99 | Miscellaneous | EXCAVATION WP COMING. SURVEY MAP SENT | ||
2012-01-25 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | |||
2012-01-25 | 37 | Site Investigation Report (SIR) Received (non-fee) | SI REC'D AS PART OF SOW DEVELOPMENT / APPROVAL | ||
2012-01-10 | 43 | Site Activity Status Update Received | |||
2011-10-11 | 99 | Miscellaneous | REC'D PRECERT TAX LETTER FOR BROWNFIELDS | ||
2011-09-26 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | EMAILED CONSULTANT TO GO AHEAD WITH WP | ||
2011-09-23 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | REC'D SI WORKPLAN | ||
2011-09-07 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2010-08-17 | 200 | Push Action Taken | SENT PUSH LETTER. | ||
2007-08-09 | 200 | Push Action Taken | STATUS UPDATE REQUEST/PM CHANGE NOTIFICATION LTR SENT | ||
2001-01-09 | 99 | Miscellaneous | PHONE CONTACT WITH RP RE: STATUS UPDATE LETTER | ||
2000-12-19 | 99 | Miscellaneous | STATUS UPDATE REQUEST LETTER SENT | ||
1998-08-21 | 89 | DSPS (formerly Commerce) Transferred Back to DNR | |||
1996-07-17 | 76 | Activity Transferred to DSPS (formerly Commerce) | |||
1994-12-27 | 33 | Tank System Site Assessment (TSSA) Report Received | TNK CLS/SA REPT RECV'D | ||
1993-08-26 | 2 | Responsible Party (RP) letter sent | R.P. LETTER SEND | ||
1993-08-19 | 1 | Notification of Hazardous Substance Discharge |
Type | Related Activity |
---|---|
ERP to VPLE (On Property) | 06-67-193272 WASHINGTON SQUARE MALL |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Chlorinated Solvents | VOC | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
PECFA Site Name: |
Max. Reimbursement: | Total Amount Paid: |
Occ No | Claim No | Audit Date | Paid Date | Amt Submitted | Amt Ineligible | Amt Paid |
DECADE 80 I LTD/DECADE 80 INC 250 PATRICK BLVD, BROOKFIELD, WI 53045 |
Northern Region Contact: Kathleen Shafel kathleen.shafel@wisconsin.gov |