02-68-245535
DISTINCTIVE CLEANERS
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / CLOSED | DNR RR |
Location Name | County | DNR Region |
---|---|---|
DISTINCTIVE CLEANERS | WAUKESHA | SOUTHEAST |
Address | Municipality |
---|---|
13855 W NORTH AVE | BROOKFIELD |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the NW 1/4 of Sec 24, T07N, R20E | 43.0600146 | -88.084939 |
![]() |
![]() |
Additional Location Description |
---|
13925 W NORTH AVE |
Additional Activity Details | Acres |
---|---|
1.1 |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
268204310 | 2000-02-10 | 2017-11-30 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Name | File |
---|---|
SITE FILE DOCUMENTATION FOR ACTIVITY | ![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2023-09-27 | 187 | Continuing Obligation(s) Compliance Audit Follow-up Complete |
![]() |
REC'D COMPLETED INSPECTION FORMS | |
2023-08-24 | 185 | Continuing Obligation(s) Compliance Audit Complete |
![]() |
||
2023-08-24 | 186 | Continuing Obligation(s) Compliance Audit Follow-up Needed |
![]() |
REQUESTED COMPLETION AND INSPECTION OF INSPECTION FORMS INVESTIGATE RESIDUAL CONTAMINATION | |
2023-08-24 | 285 | CO Compliance Audit Complete - Vapor Only |
![]() |
VMS AUDIT | |
2022-09-13 | 288 | DERF - Cost Reimbursement Paid | DC-681 PAYMENT SENT OUT | ||
2020-10-27 | 130 | DNR Regulatory Reminder Sent |
![]() |
DERF FUNDING STATUS LTR | |
2019-08-29 | 218 | DERF - Cost Reimbursement Application Approved | DC-681 AUDIT APPROVAL LETTER SENT. | ||
2019-08-29 | 218 | DERF - Cost Reimbursement Application Approved | DC-681 | ||
2018-08-28 | 288 | DERF - Cost Reimbursement Paid | DC-641 | ||
2018-08-23 | 218 | DERF - Cost Reimbursement Application Approved | DC-641 | ||
2018-04-18 | 217 | DERF - Cost Reimbursement Application Received | DC-681 | ||
2017-11-30 | 199 | Additional Information Received (Fee-Based or Closure) | |||
2017-11-30 | 11 | Activity Closed | |||
2017-11-30 | 222 | Continuing Obligation - Maintain Cap Over Contaminated Area | |||
2017-11-30 | 226 | Continuing Obligation - Vapor Intrusion Response | |||
2017-11-30 | 232 | Continuing Obligation - Residual Soil Contamination | |||
2017-11-30 | 236 | Continuing Obligation - Residual GW Contamination | |||
2017-11-30 | 56 | Continuing Obligation(s) Applied |
![]() |
||
2017-11-30 | 66 | Continuing Obligations (COs) Apply at Off-site Property(ies) | auto-populated on 08/01/2019 per activity relationship to off-site(s) | ||
2017-07-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2017 - 6/30/2017 | |
2017-04-04 | 198 | Request for Additional Information (Fee-Based or Closure) | REQUEST INFO | ||
2017-02-14 | 79 | Case Closure Review Request Received | AUTO-ENTERED | ||
2017-02-08 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2016 - 12/31/2016 | |
2017-01-26 | 700 | Database Fee Paid for Groundwater Continuing Obligation(s) | REC'D CK # 9003 $350.00 | ||
2017-01-26 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | REC'D CK # 9003 $300.00 | ||
2017-01-26 | 779 | Case Closure Review Fee Received | REC'D CK # 9003 $1050.00 | ||
2016-12-05 | 288 | DERF - Cost Reimbursement Paid | DERF PAYMENT MADE | ||
2016-07-14 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2016 - 6/30/2016 | |
2016-07-06 | 217 | DERF - Cost Reimbursement Application Received | |||
2016-05-06 | 112 | DERF - Change Order Received | VARIANCE REQUEST | ||
2015-09-14 | 218 | DERF - Cost Reimbursement Application Approved | |||
2015-07-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-06-12 | 214 | DERF - Interim Action Workplan Approved | |||
2015-05-14 | 99 | Miscellaneous | VAPOR INTRUSION PILOT TEST RESULTS | ||
2015-03-19 | 218 | DERF - Cost Reimbursement Application Approved | |||
2015-01-15 | 99 | Miscellaneous | VAPOR INTRUSION PILOT TEST | ||
2015-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-12-01 | 217 | DERF - Cost Reimbursement Application Received | |||
2014-09-11 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-07-11 | 218 | DERF - Cost Reimbursement Application Approved | |||
2014-04-07 | 217 | DERF - Cost Reimbursement Application Received | |||
2014-01-30 | 130 | DNR Regulatory Reminder Sent | DERF FUNDING STATUS LTR | ||
2013-05-23 | 218 | DERF - Cost Reimbursement Application Approved | DERF PAYMENT ISSUED $73,698.13 | ||
2013-03-20 | 99 | Miscellaneous | REC'D INJECTION DOC RPT | ||
2012-11-14 | 99 | Miscellaneous | DREC'D INJECTION PERMIT APPLICATION | ||
2012-08-13 | 218 | DERF - Cost Reimbursement Application Approved | DC-480 APPROVED W/EDITS - CHECK BEING PROCESSED | ||
2011-09-07 | 130 | DNR Regulatory Reminder Sent | Vapor Intrusion (VI) Assessment Notification Ltr Sent | ||
2011-09-01 | 214 | DERF - Interim Action Workplan Approved | LTR SENT - INTERIM ACTION APPROVED | ||
2011-08-05 | 213 | DERF - Interim Action Workplan Received | |||
2006-03-14 | 218 | DERF - Cost Reimbursement Application Approved | |||
2005-08-26 | 217 | DERF - Cost Reimbursement Application Received | FOR SI & PREDISCOVERY | ||
2005-04-19 | 38 | Site Investigation Report (SIR) Approved | SI & RAOR | ||
2002-07-12 | 214 | DERF - Interim Action Workplan Approved | INTERIM ACTION PLAN APPROVED | ||
2002-05-29 | 110 | DERF - Potential Claim Form Approved | |||
2002-05-09 | 4 | Enforcement Conference Held | ENFORCEMENT CONFERENCE | ||
2000-03-14 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received | |||
2000-03-13 | 2 | Responsible Party (RP) letter sent | |||
2000-02-10 | 1 | Notification of Hazardous Substance Discharge | |||
2000-01-05 | 28 | Phase I Environmental Site Assessment (ESA) Rpt Received |
Type | Related Activity |
---|---|
Property Affected -> | 13-68-581694 13845 W NORTH AVE |
Property Affected -> | 13-68-581695 13785 W NORTH AVE |
Reasons when Action Code 234 is Present |
---|
MW WAS NOT ABLE TO BE LOCATED |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
(A) Exceedence of Vapor Risk Levels - Vapor Mitigation Required: Vapor mitigation is required due to sub-slab or nearby soil vapor concentrations exceeding vapor risk screening levels. |
(D) Site Specific Exposure Assumptions Used - Commercial/Industrial Restriction: Property use restricted to commercial or industrial. Specific vapor inhalation exposure assumptions used (including commercial or industrial use). Notification of DNR required for change in property use. Vapor evaluation is required. Further cleanup may be required. |
(E) Future Redevelopment of Property – Vapor Control Technology Required for Construction: DNR requires notification prior to new building construction or building modifications. Potential for vapor intrusion exists due to residual contamination. Vapor control technologies are required to be installed or modified, and verified protective unless a vapor evaluation is accepted by DNR. |
Category | Fiscal Year | Amount |
---|---|---|
DERF Reimbursements:Grant | 2006 | $15,046 |
DERF Reimbursements:Grant | 2013 | $73,698 |
DERF Reimbursements:Grant | 2013 | $13,839 |
DERF Reimbursements:Grant | 2013 | $8,941 |
DERF Reimbursements:Grant | 2015 | $17,933 |
DERF Reimbursements:Grant | 2015 | $22,282 |
DERF Reimbursements:Grant | 2016 | $17,848 |
DISTINCTIVE DRY CLEANER 13831 W NORTH AVE, BROOKFIELD, WI 53005 |
Southeast Region Contact: Jenny Meyer jennifer.meyer1@wisconsin.gov |