02-30-000327
CHRYSLER KENOSHA MAIN PLT
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
FORMER KENOSHA ENGINE PLANT | KENOSHA | SOUTHEAST |
Address | Municipality |
---|---|
5555 30TH AVE | KENOSHA |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
SW 1/4 of the SE 1/4 of Sec 36, T02N, R22E | 42.5827671 | -87.843962 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
230004500 | 1989-08-17 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-07-15 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-04-26 | 198 | Request for Additional Information (Fee-Based or Closure) | REQUESTED CLARIFICATIONS AND PLAN MODIFICATION | ||
2024-04-26 | 198 | Request for Additional Information (Fee-Based or Closure) |
![]() |
REQUESTED CLARIFICATIONS AND PLAN MODIFICATION | |
2024-04-11 | 43 | Site Activity Status Update Received |
![]() |
ANNUAL GROUNDWATER MONITORING REPORT | |
2024-03-12 | 854 | Materials Management Plan Request Recvd with Fee |
![]() |
REC'D CK #217953 $700, KENOSHA INNOVATION CENTER | |
2024-03-12 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | REC'D CK #217953 $300, KENOSHA INNOVATION CENTER | ||
2024-03-12 | 854 | Materials Management Plan Request Recvd with Fee |
![]() |
REC'D CK #217953 $700, REUSE OF SOIL - KENOSHA INNOVATION NEIGHBORHOOD INFRASTRUCTURE CONSTRUCTION | |
2024-03-12 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | REC'D CK #217953 $300, REUSE OF SOIL | ||
2024-01-09 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-12-15 | 43 | Site Activity Status Update Received |
![]() |
KEP GROUNDWATER POST-REMEDIATION SAMPLE RESULTS – OCTOBER 2023 | |
2023-10-12 | 43 | Site Activity Status Update Received |
![]() |
KEP GROUNDWATER POST-REMEDIATION SAMPLE RESULTS – JULY 2023 | |
2023-07-24 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-06-20 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER POST-REMEDIATION SAMPLE RESULTS - APRIL 2023 | |
2023-05-31 | 81 | Site Investigation Workplan (SIWP) Not Approved |
![]() |
DNR CANNOT PROVIDE RESPONSE - NEED TO CONSULT WITH EPA INSTEAD. | |
2023-05-02 | 135 | Site Investigation Workplan (SIWP) Received (fee) |
![]() |
RECV'D CK #211950 $700.00 | |
2023-03-14 | 43 | Site Activity Status Update Received |
![]() |
ANNUAL GROUNDWATER MONITORING REPORT | |
2023-01-26 | 43 | Site Activity Status Update Received |
![]() |
KEP GROUNDWATER POST-REMEDIATION SAMPLE RESULTS - OCTOBER 2022 | |
2023-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2022-11-08 | 98 | Technical Assistance Provided |
![]() |
||
2022-10-18 | 97 | Technical Assistance Request Received (fee) |
![]() |
RECVD CK #207846 $700.00REDEVELOPMENT PLAN - PHASE I INFRASTRUCTURE CONSTRUCTION | |
2022-10-12 | 43 | Site Activity Status Update Received |
![]() |
KEP GROUNDWATER POST-REMEDIATION SAMPLE RESULTS - JULY 2022 | |
2022-08-01 | 99 | Miscellaneous |
![]() |
CONSTRUCTION DOCUMENTS | |
2022-07-18 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-01-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2022-01-12 | 43 | Site Activity Status Update Received |
![]() |
KEP PERIMETER GW SAMPLE RESULTS OCT 2021 | |
2021-08-31 | 64 | Inject/Infiltrate Request Approved |
![]() |
||
2021-08-20 | 99 | Miscellaneous |
![]() |
REC'D ADD'L INFO FOR INJECTION APPROVAL | |
2021-08-18 | 99 | Miscellaneous |
![]() |
REC'D ADD'L INFO FOR INJECTION APPROVAL | |
2021-08-17 | 63 | Inject/Infiltrate Request Received (fee) |
![]() |
REC'D CK #003153 $700.00 | |
2021-08-03 | 99 | Miscellaneous |
![]() |
REQUESTED ADD'L INFO FOR INJECTION APPROVAL | |
2021-07-20 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-01-19 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2021-01-12 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 2020 GW SAMPLE RESULTS - KEP WELLS AND PIEXOMETERS INSTALLED, BASELINE EVENT | |
2020-12-03 | 43 | Site Activity Status Update Received |
![]() |
NOVEMBER 2020 SEMI-ANNUAL PERIMETER GROUNDWATER MONITORING REPORT | |
2020-10-21 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
||
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-07-17 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-07-16 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
SEMI-ANNUAL OPERATION, MAINTENANCE AND MONITORING REPORT, JULY - DECEMBER 2019 | |
2020-07-16 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2020 SEMI-ANNUAL PERIMETER GROUNDWATER MONITORING REPORT | |
2020-06-29 | 99 | Miscellaneous |
![]() |
PROJECT UPDATE RECEIVED | |
2020-06-11 | 857 | Materials Management Plan Approved |
![]() |
718.12 AND 718.15 EXEMPTION GRANTED FOR ON-SITE SOIL MANAGEMENT | |
2020-06-11 | 56 | Continuing Obligation(s) Applied | |||
2020-06-11 | 222 | Continuing Obligation - Maintain Cap Over Contaminated Area | |||
2020-06-11 | 226 | Continuing Obligation - Vapor Intrusion Response | FUTURE REDEVELOPMENT - NOTIFICATION REQUIRED | ||
2020-06-11 | 232 | Continuing Obligation - Residual Soil Contamination | |||
2020-06-08 | 199 | Additional Information Received (Fee-Based or Closure) |
![]() |
REC'D REQUESTED INFO | |
2020-06-04 | 99 | Miscellaneous |
![]() |
FOLLOW-UP REQUEST FOR INFO ON ON-SITE MATERIAL MANAGEMENT | |
2020-05-28 | 99 | Miscellaneous |
![]() |
REC'D ADD'L INFORMATION REGARDING ON-SITE MATERIAL MANAGEMENT | |
2020-05-18 | 198 | Request for Additional Information (Fee-Based or Closure) |
![]() |
REQ ADDITIONAL INFO REGARDING MATERIAL MANAGEMENT PLAN | |
2020-04-14 | 854 | Materials Management Plan Request Recvd with Fee |
![]() |
REC'D CK #14520582 $700.00 | |
2020-04-14 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | REC'D CK #14520582 $300.00, MMP | ||
2020-02-12 | 99 | Miscellaneous |
![]() |
CONDITIONAL APPROVAL OF REMEDIAL DESIGN REPORT (GROUNDWATER) | |
2020-01-17 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2019-12-30 | 99 | Miscellaneous |
![]() |
RESPONSE TO COMMENTS LTR AND GW REMEDIAL DESIGN RPT REVISIONS | |
2019-12-03 | 43 | Site Activity Status Update Received |
![]() |
REC'D OCTOBER 2019 SEMI ANNUAL PERIMETER GW MONITORING RPT | |
2019-10-16 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
REC'D SEMI-ANNUAL OPERATION AND MONITORING RPT JANUARY - JUNE 2019 | |
2019-09-23 | 99 | Miscellaneous |
![]() |
REVIEW OF REMEDIAL DESIGN REPORT (GROUNDWATER) | |
2019-07-25 | 147 | Remedial Action (RA) Design Report Received (non-fee) |
![]() |
REMEDIAL DESIGN REPORT (GROUNDWATER) | |
2019-07-25 | 99 | Miscellaneous | KEP SITEWIDE GROUNDWATER REMEDIATION: TECHNICAL SPECIFICATIONS AND PLANS | ||
2019-07-25 | 99 | Miscellaneous | PUBLIC NOTICE REGARDING ENVIRONMENTAL CLEANUP WISCONSIN READY FOR REUSE PROGRAM | ||
2019-07-25 | 99 | Miscellaneous | ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES, GROUNDWATER REMEDIATION | ||
2019-07-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-06-07 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
JULY-DEC 2018 O&M REPORT | |
2019-06-07 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2019 PERIMETER GW SAMPLING SUMMARY | |
2019-03-14 | 99 | Miscellaneous |
![]() |
APPROVAL OF 2019 REMEDIATION SYSTEM MAINTENANCE COST | |
2019-02-08 | 43 | Site Activity Status Update Received |
![]() |
OCT 2018 PERIMETER GW SAMPLING SUMMARY | |
2019-02-06 | 99 | Miscellaneous |
![]() |
SUPPLEMENT TO KEP SMP; REQUEST FOR APPROVAL OF AN ADDITIONAL SOURCE OF TOPSOIL | |
2019-01-02 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
JULY-DEC 2017 O&M REPORT | |
2019-01-02 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
JAN-JUNE 2018 O&M REPORT | |
2018-11-28 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) |
![]() |
O&M RPT, JAN-JUNE 2017 | |
2018-10-08 | 43 | Site Activity Status Update Received |
![]() |
ENHANCED REDUCTIVE DECHLORINATION PILOT TEST DOCUMENTATION REPORT | |
2018-09-20 | 43 | Site Activity Status Update Received |
![]() |
REC'D MAY 2018 PERIMETER GW SAMPLING SUMMARY | |
2018-07-30 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
REC'D REM DOC RPT FOR GROUP AREAS A, B, C, E, J & K | |
2018-05-31 | 43 | Site Activity Status Update Received |
![]() |
REC'D SEMI-ANNUAL O&M REPORT, JULY TO DECEMBER 2016 | |
2018-04-04 | 99 | Miscellaneous | APPROVED USE OF BANK. ESCROW FUNDS FOR KEP SOIL REMED.-CONTINUATION. | ||
2018-04-04 | 99 | Miscellaneous | APPROVED FUNDING CHANGE FOR 2018 O&M OF GW RECOVERY SYSTEMS. | ||
2018-04-03 | 99 | Miscellaneous | REC'D REQ. FOR KEP SOIL REMEDIATION - CONTINUATION USING BANKRUPTCY ESCROW ACCT. | ||
2018-03-28 | 99 | Miscellaneous |
![]() |
APPROVED R4R FUNDING APPR REQ FOR GW RECOVERY SYSTEMS O&M AND FOR GW REMEDIATION | |
2018-03-27 | 43 | Site Activity Status Update Received |
![]() |
REC'D IN-SITU CHEM. OXIDATION PILOT TEST DOCUMENTATION REPORT | |
2018-01-31 | 99 | Miscellaneous |
![]() |
REC'D R4R FUNDING APPR REQ FOR GW RECOVERY SYSTEMS O&M AND FOR GW REMEDIATION | |
2017-11-28 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
REC'D PCB TRANSFORMER PAD AND SOIL REMOVAL DOCUMENTATION REPORT | |
2017-04-11 | 99 | Miscellaneous | REC'D PCB TRANSFORMER PAD & SOIL REMOVAL WORK PLAN | ||
2017-04-10 | 43 | Site Activity Status Update Received | REC'D NOV. 2016 PERIMETER GW SAMPLING SUMMARY | ||
2017-02-24 | 99 | Miscellaneous | DNR APPROVES WK. PLAN FOR AUTHORIZATION OF EXPENDITURE - GW RECOVERY SYSTEMS O&M | ||
2017-02-22 | 99 | Miscellaneous | REC'D WK. PLAN FOR AUTHORIZATION OF EXPENDITURE - GW RECOVERY SYSTEMS O&M | ||
2016-12-02 | 64 | Inject/Infiltrate Request Approved |
![]() |
||
2016-11-15 | 43 | Site Activity Status Update Received | REC'D SEMI-ANNUAL OPERATION AND MONITORING REPORT, JAN - JUNE 2016 | ||
2016-10-24 | 63 | Inject/Infiltrate Request Received (fee) | REC'D CK#162289 $700.00 | ||
2016-10-20 | 99 | Miscellaneous | APPROVED WORK AUTHORIZATION REQUEST FOR KEP GROUNDWATER MONITORING PLAN 2016-17 | ||
2016-10-07 | 99 | Miscellaneous |
![]() |
APPROVED REV. SOIL MANAGEMENT PLAN & NR718.12 EXEMPT REQ. | |
2016-09-30 | 99 | Miscellaneous |
![]() |
REC'D SOLID WASTE DISPOSAL LOCATION FOR KEP CONT. SOIL | |
2016-09-28 | 99 | Miscellaneous |
![]() |
REC'D OFFSITE BACKFILL & TOPSOIL WASTE DETERMINATION | |
2016-09-16 | 99 | Miscellaneous |
![]() |
CONDITIONAL APPROVAL OF AUTH. REQ. - KEP SOIL REMEDIATION | |
2016-09-16 | 99 | Miscellaneous | REC'D SOIL & MATERIAL MANAGEMENT PLAN - REVISION 1 | ||
2016-09-16 | 99 | Miscellaneous | REC'D NR 718 EXEMPTION REQUEST FOR KEP | ||
2016-09-14 | 99 | Miscellaneous | REC'D WORK AUTHORIZATION REQUEST FOR KEP GROUNDWATER MONITORING PLAN 2016-17 | ||
2016-08-29 | 99 | Miscellaneous | REC'D WK AUTHORIZATION REQ. - KEP SOIL REMEDIATION | ||
2016-07-20 | 43 | Site Activity Status Update Received |
![]() |
REC'D APRIL 2016, GW SAMPLING SUMMARY | |
2016-07-20 | 99 | Miscellaneous | REC'D RESPONSE TO WDNR COMMENTS DATED 5-17-16, & SOILS AND MATERIALS MNGMT WK. PLAN ADDENDUM | ||
2016-07-18 | 99 | Miscellaneous | REC'D RESPONSE TO EPA MEMO (TECH REV. COMMENTS ON PROPOSED PILOT TEST) & REVISED FUNDING REQUEST | ||
2016-05-17 | 99 | Miscellaneous |
![]() |
DNR REQUESTS REVISION OF SOIL & MATERIAL MANAGEMENT PLAN | |
2016-03-29 | 99 | Miscellaneous | REC'D SOIL & MATERIAL MANAGEMENT PLAN | ||
2016-02-22 | 43 | Site Activity Status Update Received | REC'D SEMI-ANN. O&M REPORT, JULY-DEC. 2015 | ||
2016-02-19 | 99 | Miscellaneous | DNR APPROVES WASTE CHARACTERIZATION S&A PLAN FOR SOIL REMEDIATION | ||
2016-02-19 | 99 | Miscellaneous | DNR APPROVES AUTH. REQ. - RESPONSE TO COMMENTS &/OR WK. PLAN REVISION OF GW PILOT TESTS | ||
2016-02-19 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
REC'D CS2 REMEDIAL ACTION DOCUMENTATION REPORT | |
2016-02-10 | 99 | Miscellaneous | REC'D WK. AUTHORIZATION REQ. - RESPONSE TO COMMENTS AND/OR WK. PLAN REVISION OF GW PILOT TESTS | ||
2016-02-05 | 99 | Miscellaneous | REC'D WK. AUTHORIZATION REQ. - WASTE CHARACTERIZATION SAMPLING & ANALYSIS PLAN FOR SOIL REMEDIATION | ||
2016-01-27 | 99 | Miscellaneous | REQUESTED REVISION OF WK. PLAN FOR INVESTIGATION OF TRIBUTARY TO PIKE CREEK | ||
2016-01-18 | 99 | Miscellaneous | REC'D EPA TECH. REVIEW COMMENTS ON PROPOSED PILOT TEST FOR KEP SITE | ||
2016-01-08 | 99 | Miscellaneous | DNR APPROVES WK. PLAN FOR AUTHORIZATION OF EXPENDITURE - GW RECOVERY SYSTEMS O&M | ||
2015-12-18 | 99 | Miscellaneous | REC'D SITE WIDE STORM AND SANITARY SEWER EVALUATION AND SUMMARY REPORT | ||
2015-12-18 | 99 | Miscellaneous | REC'D TRANSFORMER PAD PCB SAMPLING RESULTS | ||
2015-12-18 | 99 | Miscellaneous | REC'D PCB NOTICE OF RELEASE & REQUEST FOR A TSCA-COORDINATED APPROVAL UNDER 40CFR 761.77(A)(1) | ||
2015-12-17 | 99 | Miscellaneous | REC'D WK. PLAN FOR AUTHORIZATION OF EXPENDITURE - GW RECOVERY SYSTEMS O&M | ||
2015-12-11 | 99 | Miscellaneous | DNR APPROVES REVISED PLAN FOR PZ IN JOCKEY AREA | ||
2015-12-03 | 99 | Miscellaneous | REC'D REVISED PLAN FOR PZ IN JOCKEY AREA | ||
2015-11-25 | 99 | Miscellaneous | DNR APPROVES 11/24/15 WORK PLAN - KEP SOIL REMEDIATION | ||
2015-11-25 | 99 | Miscellaneous | DNR APPROVES PART OF WORK PLAN TO ADDRESS VPLE INVEST. ADDITIONS, REQUESTS REVISION ON 2 ITEMS. | ||
2015-11-24 | 99 | Miscellaneous | WORK PLAN - KEP SOIL REMEDIATION | ||
2015-11-17 | 99 | Miscellaneous | WORK PLAN - FUNDING AUTHORIZATION REQUEST FOR FEASIBILITY STUDY - GW PILOT TESTING | ||
2015-11-02 | 99 | Miscellaneous | REC'D DOCUMENTATION OF BERM SOIL FROM CS7 QUALITY AT KEP USED AS EXCAVATION BACKFILL (CS2) | ||
2015-10-21 | 99 | Miscellaneous | REC'D GW PILOT TEST WORK PLAN | ||
2015-10-06 | 99 | Miscellaneous | REC'D WORK PLAN TO ADDRESS VPLE INVESTIGATION ADDITIONS | ||
2015-09-25 | 43 | Site Activity Status Update Received | REC'D JAN-JUNE 2015 SEMI-ANNUAL O&M REPORT | ||
2015-09-25 | 99 | Miscellaneous | REC'D LABORATORY SCALE TREATABILITY STUDY RESULTS FOR GW REMEDIATION | ||
2015-08-03 | 99 | Miscellaneous | REC'D ADD. SAMPLING RESULTS OF SOUTHPORT PARK SOILS | ||
2015-07-27 | 99 | Miscellaneous | APPROVED WK. PLAN FOR CS2 SOIL REMEDIATION | ||
2015-07-27 | 99 | Miscellaneous | APPROVED WK. PLAN FOR GW MONITORING - REVISION OF MARCH 12, 2015 WK. PLAN | ||
2015-07-22 | 99 | Miscellaneous | REC'D WK. PLAN FOR CS2 SOIL REMEDIATION | ||
2015-07-22 | 99 | Miscellaneous | REC'D WK. PLAN FOR GW MONITORING - REVISION OF MARCH 12, 2015 WK. PLAN | ||
2015-07-17 | 99 | Miscellaneous | REQUESTED ADDITIONAL SAMPLING OF SOUTHPORT PARK SOILS | ||
2015-07-07 | 99 | Miscellaneous | REC'D REQUEST TO USE SOUTHPORT PARK SOILS AS FILL FOR CS 2 REMEDIAL EXCAVATIONS | ||
2015-06-18 | 40 | Remedial Action Options Report (RAOR) Approved | |||
2015-06-18 | 99 | Miscellaneous |
![]() |
REC'D DESIGN REPORT FOR ONLY SOIL REMEDIATION | |
2015-06-15 | 43 | Site Activity Status Update Received | REC'D MARCH 2015 GW SAMPLING SUMMARY | ||
2015-05-12 | 140 | Site Investigation Report (SIR) Not Approved | MET WITH CITY TO DISCUSS ADDITIONAL WORK REQUIRED TO COMPLETE SI, AND POTENTIAL ENTRY INTO VPLE | ||
2015-04-23 | 99 | Miscellaneous | APPROVED WK. PLAN FOR GW RECOVERY SYSTEMS O&M | ||
2015-04-23 | 99 | Miscellaneous | APPROVED REQUEST TO TEMPORARILY SUSPEND THE OPERATION OF 2 GW RECOVERY SYSTEMS | ||
2015-04-22 | 99 | Miscellaneous | APPROVED WK. PLAN FOR PRE-DESIGN STUDIES FOR GW TREATMENT, FOR PREP. OF REMED. DSGN. RPT. & BID DOCS | ||
2015-04-13 | 99 | Miscellaneous | REC'D WK. PLAN FOR GW RECOVERY SYSTEMS O&M | ||
2015-04-13 | 99 | Miscellaneous | REC'D WK. PLAN FOR PRE-DESIGN STUDIES FOR GW TREATMENT, FOR PREP. OF REMEDIAL DESIGN RPT. & BID DOCS | ||
2015-04-13 | 99 | Miscellaneous | REC'D RPT. DOCUMENTING SOIL REMOVAL UNDER FMR. BUILDING 53 | ||
2015-04-10 | 43 | Site Activity Status Update Received | REC'D JULY-DEC. 2014 SEMI-ANNUAL O&M REPORT | ||
2015-04-10 | 99 | Miscellaneous | REC'D GW RECOVERY SYSTEM PERMIT MODIFICATION REQUEST | ||
2015-04-09 | 39 | Remedial Action Options Report (RAOR) Received (non-fee) |
![]() |
||
2015-03-17 | 99 | Miscellaneous | APPROVED ONLY THE MARCH 2015 GW MONITORING NOT THE ENTIRE YEAR. | ||
2015-03-17 | 43 | Site Activity Status Update Received | REC'D DECEMBER 2014 GW SAMPLING SUMMARY | ||
2015-03-12 | 99 | Miscellaneous | REC'D WK. PLAN FOR 2015 GW MONITORING, ANALYSES & REPORTING | ||
2015-02-24 | 37 | Site Investigation Report (SIR) Received (non-fee) | |||
2015-01-15 | 99 | Miscellaneous | REC'D WK. PLAN FOR MW NETWORK REVIEW & 2015 GW MONITORING PLAN PREPARATION | ||
2014-11-26 | 43 | Site Activity Status Update Received | REC'D SEMI ANNUAL OPERATION AND MONITORING REPORT | ||
2014-10-06 | 99 | Miscellaneous | APPROVED WK. PLANS FOR UPSTREAM STORM & SANITARY SEWER SAMPLING & FOR TRANSF. PAD CONCRETE SAMPLING | ||
2014-09-22 | 99 | Miscellaneous | REC'D WK. PLANS FOR UPSTREAM STORM & SANITARY SEWER SAMPLING & FOR TRANSFORMER PAD CONCRETE SAMPLING | ||
2014-09-12 | 99 | Miscellaneous | APPROVED WK. PLAN FOR 2 QTRS OF GW SAMPLING & FOR HYDRAULIC CONDUCTIVITY TESTING | ||
2014-09-08 | 99 | Miscellaneous | APPROVED WK. PLAN FOR PRELIMINARY REMEDIAL ACTION OF PB-IMPACTED SOIL IN BUILDING 53 AREA | ||
2014-09-08 | 99 | Miscellaneous | REC'D WK. PLAN FOR HYDRAULIC CONDUCTIVITY TESTING | ||
2014-08-28 | 99 | Miscellaneous | REC'D WK. PLAN FOR 2 QTRS OF GW SAMPLING | ||
2014-07-23 | 99 | Miscellaneous | REC'D WK. PLAN FOR EXCAVATION, PRE-TREATMENT & DISPOSAL OF PB-IMPACTED SOIL IN BUILDING 53 AREA | ||
2014-07-22 | 99 | Miscellaneous | APPROVED WK. PLAN FOR PREP. OF PRELIM. RAOR | ||
2014-07-18 | 99 | Miscellaneous | REC'D WK. PLAN FOR PREP. OF PRELIM. RAOR | ||
2014-06-24 | 99 | Miscellaneous | REC'D POST-EXCAVATION SOIL SAMPLING PLAN FOR PETROLEUM-IMPACTED SOILS (LNAPL EXCAVATIONS) | ||
2014-06-24 | 99 | Miscellaneous | APPROVED POST-EXCAVATION SOIL SAMPLING PLAN | ||
2014-01-22 | 43 | Site Activity Status Update Received | REC'D PROGRESS RPT 4TH QTR 2013 | ||
2014-01-13 | 43 | Site Activity Status Update Received | REC'D PROGRESS RPT 3RD QTR 2013 | ||
2013-10-18 | 43 | Site Activity Status Update Received | REC'D PROGRESS RPT 2ND QTR 2013 | ||
2013-06-19 | 43 | Site Activity Status Update Received | REC'D REM PERFORMANCE & MONITOR. PROGRESS REPT FIRST QTR 2013 | ||
2013-06-19 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | APPROVED REVISED SI WORK PLAN | ||
2013-05-29 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | REC'D REVISED SI WORK PLAN | ||
2013-02-11 | 43 | Site Activity Status Update Received | REC'D PROGRESS RPT 4TH QTR 2012 | ||
2013-01-23 | 43 | Site Activity Status Update Received | REC'D PROGRESS RPT 3RD QTR 2012 | ||
2012-08-02 | 43 | Site Activity Status Update Received | SEE 02-30-108645 02-30-287532 | ||
2012-06-22 | 43 | Site Activity Status Update Received | REC'D COMPLETION RPT-INTERIM ACTIONS, ETC | ||
2012-03-01 | 43 | Site Activity Status Update Received | |||
2011-11-17 | 43 | Site Activity Status Update Received | PROGRESS REPT 3RD QTR 2011 | ||
2011-09-22 | 43 | Site Activity Status Update Received | ADDTNL GW DOC REC'D, ALSO APPLY TO BRRTS# 02-30-108645, 02-30-287532, 02-30-000625, 03-30-261138 | ||
2011-09-07 | 130 | DNR Regulatory Reminder Sent | Vapor Intrusion (VI) Assessment Notification Ltr Sent | ||
2011-08-17 | 43 | Site Activity Status Update Received | GW SMPLG RPT REC'D FOR BRRTS# 03-30-000625, 02-30-000983, 03-30-167597, 03-30-000106, 02-30-000108 | ||
2011-06-02 | 43 | Site Activity Status Update Received | SEE BRRT'S #02-03-00147 - 02-03-108645 - 02-30-0287532 -03-30-000625 -03-30-261138 | ||
2011-05-18 | 43 | Site Activity Status Update Received | |||
2011-03-16 | 43 | Site Activity Status Update Received | SUPPLEMENTAL SAMP RPT SEE BRRTS # 02-30-00147, 02-30-108645, 02-30-287532, 03-30-000625,03-30-261138 | ||
2011-03-04 | 28 | Phase I Environmental Site Assessment (ESA) Rpt Received |
![]() |
MARCH 2011 PHASE I ESA | |
2011-02-04 | 43 | Site Activity Status Update Received | SEE 02-30-001147, 108645, 287532, 03-30-000625, 261138, 04-30-048728 | ||
2010-12-17 | 99 | Miscellaneous | DOJ SENT LETTERS TO LIQ. TRUST & CHRYSLER GP. LLC NOTIFYING THEM OF THEIR RESPONSIBILITIES | ||
2010-11-04 | 43 | Site Activity Status Update Received | SEE 02-30-001147, 108645, 287532, 03-30-000625, 261138, 04-30-048728 | ||
2010-07-26 | 43 | Site Activity Status Update Received | REM. PERF./MON.PROG.REPT. SEE 02-30-001147, 108645, 287532, 03-30-000625, 261138 | ||
2010-07-16 | 99 | Miscellaneous | REC'D NOTIFICATION OF HIRING ENV. CONSULTANT | ||
2010-06-16 | 2 | Responsible Party (RP) letter sent | DV. SENT RP LETTER TO LIQUIDATION TRUST | ||
2010-06-03 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) | REC'D AS-BUILT DRAWINGS FOR SOUTHERN & CENTRAL REMEDIATION SYSTEMS. | ||
2010-05-07 | 99 | Miscellaneous | DV. REQUEST FOR REMED. SYSTEM AS BUILT REPORTS & CHANGE IN GW P&T REPORTING FROM ANN. TO 1/4LY | ||
2010-05-07 | 99 | Miscellaneous | DV. SENT COPY OF 5/5/10 SITE VISIT PHOTOS TO JONES DAY | ||
2010-03-11 | 43 | Site Activity Status Update Received | DV. 3.15.10 REC'D ANNUAL REM. PERFORMANCE MONITORING REPORT | ||
2008-03-24 | 43 | Site Activity Status Update Received | REC'D ANNUAL REM. PERFORMANCE MONITORING REPT | ||
2008-03-19 | 43 | Site Activity Status Update Received | REC'D UPDATE REPT | ||
2007-03-30 | 43 | Site Activity Status Update Received | REC'D ANNUAL REM PERF. MONITORING REPT 10/1 - 09/30/06 | ||
2006-06-30 | 43 | Site Activity Status Update Received | |||
2001-09-14 | 43 | Site Activity Status Update Received | SEE GENERAL FILE FOR GW REPORT FOR SITE | ||
1999-03-30 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | mw | ||
1998-10-29 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) | N AREA GW RECOV/TREAT SYS & IMMED ACTION RPT;60TH ST SEWER EXCAV | ||
1998-09-17 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
||
1998-09-08 | 99 | Miscellaneous |
![]() |
REMEDIAL WORK PLAN | |
1998-03-11 | 92 | Operation & Maintenance (O&M) Report Received (non-fee) | |||
1997-09-03 | 43 | Site Activity Status Update Received | |||
1996-10-15 | 99 | Miscellaneous |
![]() |
AIR EMISSIONS CALCULATIONS FOR SOIL AND GW REMEDIATION | |
1996-06-27 | 99 | Miscellaneous |
![]() |
EXISTING PROFILE EXTENSION REQ #4 | |
1996-06-14 | 43 | Site Activity Status Update Received |
![]() |
GW MONITORING RPT MARCH 1996 QUARTERLY SAMPLING | |
1996-06-07 | 99 | Miscellaneous |
![]() |
PRELIMINARY REMEDIAL INVESTIGATION WORKPLAN | |
1996-05-16 | 99 | Miscellaneous |
![]() |
AIR EMISSIONS CALCULATIONS FOR SOIL AND GW REMEDIATION | |
1996-03-19 | 99 | Miscellaneous |
![]() |
ADDL DATA FOR EXISTING PROFILE EXTENSION REQ #3 | |
1996-02-02 | 99 | Miscellaneous |
![]() |
EXISTING PROFILE EXTENSION REQ #3 | |
1996-01-22 | 43 | Site Activity Status Update Received |
![]() |
GW MONITORING RPT DECEMBER 1995 QUARTERLY SAMPLING RPT | |
1996-01-15 | 99 | Miscellaneous |
![]() |
AIR EMISSIONS CALCULATIONS FOR SOIL AND GW REMEDIATION SYSTEMS | |
1995-12-19 | 43 | Site Activity Status Update Received |
![]() |
GW MONITORING RPT SEPT 19995 QUARTERLY SAMPLING | |
1995-10-16 | 99 | Miscellaneous |
![]() |
AIR EMISSIONS CALCULATIONS FOR SOIL AND GW REMEDIATION | |
1995-10-01 | 99 | Miscellaneous |
![]() |
INTERIM REMEDIAL ACTION EVALUATION RPT | |
1995-06-06 | 99 | Miscellaneous |
![]() |
SOLID WASTE STORAGE EXEMPTION | |
1995-05-04 | 43 | Site Activity Status Update Received |
![]() |
MARCH 1995 QUARTERLY | |
1995-03-27 | 99 | Miscellaneous |
![]() |
SOIL VAPOR EXTRACTION PROPOSAL | |
1995-02-24 | 99 | Miscellaneous |
![]() |
PHONE CALL ENCOUNTERED FREE PRODUCT DURING CONSTRUCTION | |
1995-01-26 | 99 | Miscellaneous |
![]() |
AIR EMISSIONS CALCULATIONS FROM GW TREATMENT SYSTEMS | |
1995-01-24 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 1994 QUARTERLY | |
1994-12-20 | 43 | Site Activity Status Update Received |
![]() |
GW MONITORING UPDATE | |
1994-11-17 | 99 | Miscellaneous |
![]() |
VARIANCE SOIL DISPOSAL REQ | |
1994-10-31 | 43 | Site Activity Status Update Received |
![]() |
SEPT 1994 QUARTERLY | |
1994-08-16 | 43 | Site Activity Status Update Received |
![]() |
JUNE QUARTERLY 1994 | |
1994-07-14 | 99 | Miscellaneous |
![]() |
MEETING | |
1994-07-05 | 99 | Miscellaneous |
![]() |
VARIANCE SOIL DISPOSAL APPR | |
1994-06-23 | 99 | Miscellaneous |
![]() |
REQ FOR VARIANCE SOIL DISPOSAL | |
1994-06-20 | 147 | Remedial Action (RA) Design Report Received (non-fee) |
![]() |
SOIL REMEDIAL ACTION WP | |
1994-06-01 | 43 | Site Activity Status Update Received |
![]() |
MARCH QUARTERLY | |
1994-06-01 | 99 | Miscellaneous |
![]() |
SITE VISIT | |
1994-02-28 | 99 | Miscellaneous |
![]() |
INVESTIGATION AND REMEDIATION REVIEW | |
1994-02-17 | 99 | Miscellaneous |
![]() |
SUMMARY OF 2/15 MEETING | |
1994-01-25 | 99 | Miscellaneous |
![]() |
GW RESULTS | |
1994-01-20 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 1993 QUARTERLY | |
1994-01-06 | 99 | Miscellaneous |
![]() |
BOREHOLE/GEOPROBE INVESTIGATION | |
1994-01-01 | 99 | Miscellaneous |
![]() |
SUBSURFACE INVESTIGATION AND REMEDIATION PLAN | |
1993-12-01 | 99 | Miscellaneous |
![]() |
GW ANALYTICAL RESULTS | |
1993-11-19 | 99 | Miscellaneous |
![]() |
UST CLOSURE | |
1993-11-12 | 43 | Site Activity Status Update Received |
![]() |
SEPT 1993 QUARTERLY RPT | |
1993-11-01 | 33 | Tank System Site Assessment (TSSA) Report Received |
![]() |
TSSA | |
1993-08-13 | 43 | Site Activity Status Update Received |
![]() |
JUNE 1993 QUARTERLY | |
1993-07-29 | 99 | Miscellaneous |
![]() |
SOILS TREATMENT PLAN | |
1993-07-26 | 99 | Miscellaneous |
![]() |
GW TREATMENT PLAN | |
1993-07-19 | 998 | Activity Transferred from Spill Activity | 04-30-048728 | ||
1993-07-07 | 99 | Miscellaneous |
![]() |
ADDL INFO RECD | |
1993-06-10 | 43 | Site Activity Status Update Received |
![]() |
MARCH 1993 QUARTERLY | |
1993-04-02 | 43 | Site Activity Status Update Received |
![]() |
DEC 1992 QUARTERLY | |
1992-11-05 | 43 | Site Activity Status Update Received |
![]() |
JULY 1992 GWM RPT | |
1992-11-01 | 147 | Remedial Action (RA) Design Report Received (non-fee) |
![]() |
RADR NORTH AREA | |
1989-08-17 | 1 | Notification of Hazardous Substance Discharge |
Type | Related Activity |
---|---|
ERP to Spill | 04-30-048728 5555 30TH AVE |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Diesel Fuel | Petroleum | ||
Engine Waste Oil | Petroleum | ||
Gasoline - Unleaded and Leaded | Petroleum | ||
Metals | Metals | ||
Non-Chlorinated Solvents | VOC | ||
Petroleum - Unknown Type | Petroleum | ||
Polychlorinated Biphenyl | PCB | ||
Resource Conservation and Recovery Act Subtitle C Wastes | RCRA | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem | ||
Volatile Organic Compounds | VOC |
(E) Future Redevelopment of Property – Vapor Control Technology Required for Construction: DNR requires notification prior to new building construction or building modifications. Potential for vapor intrusion exists due to residual contamination. Vapor control technologies are required to be installed or modified, and verified protective unless a vapor evaluation is accepted by DNR. |
CHRYSLER GROUP LLC 800 CHRYSLER DRIVE, AUBURN HILLS, MI 48326 |
PAUL GRITTNER paul.grittner@wisconsin.gov |