02-41-579429
SUNRISE SHOPPING CENTER - HF & FMR OPERATION
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / CLOSED | DNR RR |
Location Name | County | DNR Region |
---|---|---|
SUNRISE SHOPPING CENTER | MILWAUKEE | SOUTHEAST |
Address | Municipality |
---|---|
2410 - 2424 10TH AVE | SOUTH MILWAUKEE |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NE 1/4 of the SW 1/4 of Sec 11, T05N, R22E | 42.9068373 | -87.861956 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
3.5 |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
241828620 | 2017-05-16 | 2023-12-20 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2023-12-20 | 11 | Activity Closed | |||
2023-12-20 | 56 | Continuing Obligation(s) Applied |
![]() |
||
2023-12-20 | 222 | Continuing Obligation - Maintain Cap Over Contaminated Area | |||
2023-12-20 | 226 | Continuing Obligation - Vapor Intrusion Response | |||
2023-12-20 | 232 | Continuing Obligation - Residual Soil Contamination | |||
2023-12-20 | 236 | Continuing Obligation - Residual GW Contamination | |||
2023-12-11 | 199 | Additional Information Received (Fee-Based or Closure) | |||
2023-10-16 | 198 | Request for Additional Information (Fee-Based or Closure) | PAUSED FOR CLOSURE REVISIONS | ||
2023-10-05 | 805 | Historic Waste Site | |||
2023-08-30 | 79 | Case Closure Review Request Received |
![]() |
AUTO-ENTERED | |
2023-08-15 | 779 | Case Closure Review Fee Received | REC'D CK #12535 $1050 | ||
2023-08-15 | 700 | Database Fee Paid for Groundwater Continuing Obligation(s) | REC'D CK #12535 $350 | ||
2023-08-15 | 710 | Database Fee Paid for Soil Continuing Obligation(s) | REC'D CK #12535 $300 | ||
2023-07-21 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2022-07-22 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-06-09 | 43 | Site Activity Status Update Received |
![]() |
MAY 2022 MONTHLY DISCHARGE MONITORING REPORT | |
2022-06-08 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (APRIL 2022 RESULTS) | |
2022-05-10 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2022 MONTHLY DISCHARGE MONITORING REPORT | |
2022-04-07 | 99 | Miscellaneous | DNR RESPONDED TO EMERGING CONTAMINANT EVALUATION REPORT ADDENDUM | ||
2022-04-06 | 43 | Site Activity Status Update Received |
![]() |
MARCH 2022 MONTHLY DISCHARGE MONITORING REPORT | |
2022-03-29 | 43 | Site Activity Status Update Received |
![]() |
EMERGING CONTAMINANT EVALUATION REPORT ADDENDUM | |
2022-03-08 | 43 | Site Activity Status Update Received |
![]() |
FEBRUARY 2022 MONTHLY DISCHARGE MONITORING REPORT | |
2022-03-01 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GW SAMPLING, JAN-FEB 2022 | |
2022-02-08 | 43 | Site Activity Status Update Received |
![]() |
JANUARY 2022 MONTHLY DISCHARGE MONITORING REPORT | |
2022-01-20 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2022-01-18 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2022-01-13 | 43 | Site Activity Status Update Received |
![]() |
REC'D DISCHARGE MONITORING RPT FOR OCTOBER 2021 | |
2022-01-13 | 43 | Site Activity Status Update Received |
![]() |
REC'D DISCHARGE MONITORING RPT FOR NOVEMBER 2021 | |
2022-01-13 | 43 | Site Activity Status Update Received |
![]() |
REC'D DISCHARGE MONITORING RPT FOR DECEMBER 2021 | |
2021-12-14 | 43 | Site Activity Status Update Received |
![]() |
NOVEMBER 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-11-08 | 43 | Site Activity Status Update Received |
![]() |
OCTOBER 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-10-18 | 43 | Site Activity Status Update Received |
![]() |
EMERGING CONTAMINANT EVALUATION REPORT AMENDMENT | |
2021-10-14 | 43 | Site Activity Status Update Received |
![]() |
SEPTEMBER 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-09-14 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-08-10 | 43 | Site Activity Status Update Received |
![]() |
JULY 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-07-20 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-07-19 | 114 | PFAS Scoping Statement Received |
![]() |
SEE ALSO AC 35 1/25/2021 | |
2021-07-06 | 43 | Site Activity Status Update Received |
![]() |
JUNE 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-06-30 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (MAY 2021) | |
2021-06-15 | 43 | Site Activity Status Update Received |
![]() |
MAY 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-05-19 | 116 | PFAS Sampling Required |
![]() |
||
2021-05-04 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-04-16 | 120 | PFAS Sampling Completed - Actionable Levels Detected | SEE AC 43 DOCUMENT | ||
2021-04-16 | 43 | Site Activity Status Update Received |
![]() |
EMERGING CONTAMINANT EVALUATION REPORT | |
2021-04-09 | 43 | Site Activity Status Update Received |
![]() |
MARCH 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-04-05 | 151 | Remedial Action (RA) Documentation Report Received (non-fee) |
![]() |
REMEDIAL CONSTRUCTION REPORT ADDENDUM | |
2021-03-10 | 43 | Site Activity Status Update Received |
![]() |
FEBRUARY 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-03-03 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (JANUARY 2021) | |
2021-02-10 | 43 | Site Activity Status Update Received |
![]() |
JANUARY 2021 MONTHLY DISCHARGE MONITORING REPORT | |
2021-01-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2021-01-29 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | NOTICE TO PROCEED - EMERGING CONTAMINANTS WORK PLAN | ||
2021-01-25 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
EMERGING CONTAMINANT EVALUATION WORK PLAN | |
2021-01-15 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 2020 DISCHARGE MONITORING REPORT | |
2020-12-09 | 43 | Site Activity Status Update Received |
![]() |
NOVEMBER 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-11-23 | 154 | Remedial Action (RA) Documentation Report Not Approved |
![]() |
ADDITIONAL ACTIONS REQUIRED | |
2020-11-20 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (OCTOBER 2020) | |
2020-11-19 | 43 | Site Activity Status Update Received |
![]() |
OCTOBER 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-10-15 | 43 | Site Activity Status Update Received |
![]() |
SEPTEMBER 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-09-28 | 152 | Remedial Action Documentation Report Received (fee) |
![]() |
FEE PAID UNDER BRRTS #02-41-576336 | |
2020-09-16 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-08-17 | 43 | Site Activity Status Update Received |
![]() |
JULY 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-07-31 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (JULY 2020) | |
2020-07-21 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-07-21 | 43 | Site Activity Status Update Received |
![]() |
JUNE 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-06-15 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (MAY 2020) | |
2020-06-08 | 43 | Site Activity Status Update Received |
![]() |
MAY 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-05-11 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-04-13 | 43 | Site Activity Status Update Received |
![]() |
MARCH 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-03-11 | 43 | Site Activity Status Update Received |
![]() |
FEBRUARY 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-03-04 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT (JANUARY 2020) | |
2020-02-10 | 43 | Site Activity Status Update Received |
![]() |
JANUARY 2020 MONTHLY DISCHARGE MONITORING REPORT | |
2020-01-21 | 99 | Miscellaneous | DISCUSSION RE: REMEDIAL ACTIONS/NEXT STEPS & PAH INVESTIGATION | ||
2020-01-20 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2020-01-09 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-12-04 | 43 | Site Activity Status Update Received |
![]() |
NOVEMBER 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-11-21 | 43 | Site Activity Status Update Received |
![]() |
4TH QUARTERLY GROUNDWATER SAMPLING REPORT (OCTOBER 2019) | |
2019-11-18 | 99 | Miscellaneous | DISCUSSION REGARDING REMEDIAL ACTIONS - CONSULTANT PROPOSING DIRECT SOIL MIXING | ||
2019-11-12 | 43 | Site Activity Status Update Received |
![]() |
OCTOBER 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-10-04 | 43 | Site Activity Status Update Received |
![]() |
SEPTEMBER 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-09-12 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-08-22 | 43 | Site Activity Status Update Received |
![]() |
3RD QUARTERLY GROUNDWATER SAMPLING REPORT (JULY 2019) | |
2019-08-06 | 43 | Site Activity Status Update Received |
![]() |
JULY 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-07-19 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-07-08 | 43 | Site Activity Status Update Received |
![]() |
JUNE 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-06-13 | 43 | Site Activity Status Update Received |
![]() |
MAY 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-05-17 | 43 | Site Activity Status Update Received |
![]() |
2ND QUARTERLY GROUNDWATER SAMPLING REPORT | |
2019-05-01 | 43 | Site Activity Status Update Received |
![]() |
MARCH 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-05-01 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-04-10 | 99 | Miscellaneous |
![]() |
WPDES AMENDMENT | |
2019-03-13 | 43 | Site Activity Status Update Received |
![]() |
JANUARY 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-03-13 | 43 | Site Activity Status Update Received |
![]() |
FEBRUARY 2019 MONTHLY DISCHARGE MONITORING REPORT | |
2019-02-14 | 43 | Site Activity Status Update Received |
![]() |
1ST QUARTERLY GROUNDWATER SAMPLING REPORT | |
2019-01-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2018 - 12/31/2018 | |
2019-01-09 | 43 | Site Activity Status Update Received |
![]() |
DECEMBER 2018 MONTHLY DISCHARGE MONITORING REPORT | |
2018-12-24 | 43 | Site Activity Status Update Received |
![]() |
NOVEMBER 2018 MONTHLY DISCHARGE MONITORING REPORT | |
2018-12-19 | 149 | Remedial Action (RA) Design Report Approved |
![]() |
||
2018-11-12 | 43 | Site Activity Status Update Received |
![]() |
OCTOBER 2018 MONTHLY DISCHARGE MONITORING REPORT | |
2018-10-31 | 147 | Remedial Action (RA) Design Report Received (non-fee) |
![]() |
FEE PAID UNDER BRRTS# 02-41-576336 | |
2018-10-29 | 43 | Site Activity Status Update Received |
![]() |
QUARTERLY GROUNDWATER SAMPLING REPORT | |
2018-10-11 | 43 | Site Activity Status Update Received |
![]() |
SEPTEMBER 2018 DISCHARGE MONITORING REPORT | |
2018-09-26 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2018 DISCHARGE MONITORING REPORT | |
2018-09-26 | 43 | Site Activity Status Update Received |
![]() |
NR 140 EXEMPTION POST-INJECTION REPORT | |
2018-09-14 | 98 | Technical Assistance Provided | TA MEETING | ||
2018-08-28 | 97 | Technical Assistance Request Received (fee) |
![]() |
FEE PAID UNDER 02-41-576336 | |
2018-08-21 | 43 | Site Activity Status Update Received |
![]() |
3RD QUARTERLY 2018 GW MONITORING REPORT | |
2018-08-13 | 43 | Site Activity Status Update Received |
![]() |
JULY 2018 DISCHARGE MONITORING REPORT | |
2018-07-18 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2018 - 6/30/2018 | |
2018-07-09 | 99 | Miscellaneous |
![]() |
AMENDED INJECTION APPROVAL | |
2018-06-27 | 64 | Inject/Infiltrate Request Approved |
![]() |
SEE ALSO AMENDED INJECTION APPROVAL 07/09/2018 | |
2018-06-06 | 99 | Miscellaneous |
![]() |
WPDES PERMIT | |
2018-05-29 | 63 | Inject/Infiltrate Request Received (fee) |
![]() |
FEE PAID UNDER BRRTS #02-41-576336 | |
2018-05-14 | 43 | Site Activity Status Update Received |
![]() |
2ND QUARTERLY 2018 REPORT | |
2018-04-24 | 38 | Site Investigation Report (SIR) Approved |
![]() |
||
2018-04-17 | 99 | Miscellaneous | PHONE CALL WITH CONSULTANT TO DISCUSS REVIEW OF RAOR AND FUTURE RAP, AND DISCUSSED AMENDED SIR | ||
2018-04-10 | 39 | Remedial Action Options Report (RAOR) Received (non-fee) |
![]() |
RAOR REC'D | |
2018-03-12 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
SITE INVESTIGATION REPORT AMENDMENT ADDENDUM | |
2018-01-23 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | PROVIDED FURTHER COMMENTS AND NOTICE TO PROCEED | ||
2018-01-03 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
REC'D SIWP | |
2017-12-05 | 99 | Miscellaneous |
![]() |
SI COMMENTS PROVIDED IN LETTER, UNDER FEE FOR 02-41-576336 | |
2017-11-17 | 99 | Miscellaneous |
![]() |
REC'D ADD'L INFO | |
2017-11-09 | 99 | Miscellaneous | TELECONFERENCE: REQUESTED ADDITIONAL INFORMATION (TEXT AND FIGURE REVISIONS) | ||
2017-10-09 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
FEE PAID UNDER BRRTS # 0241576336 | |
2017-07-31 | 43 | Site Activity Status Update Received |
![]() |
SI STATUS RPT REC'D | |
2017-05-23 | 99 | Miscellaneous | DELINEATION OF PAHS TO OCCUR, SEE WORKPLAN UNDER 02-41-576336 | ||
2017-05-18 | 2 | Responsible Party (RP) letter sent |
![]() |
||
2017-05-16 | 1 | Notification of Hazardous Substance Discharge |
![]() |
Substance | Type | Amt Released | Units |
---|---|---|---|
Naphthalene | Naphthalene | ||
Per- and Polyfluoroalkyl Substances (PFAS ADDED FROM AC120) | Industrial Chem | ||
Polynuclear Aromatic Hydrocarbons | Petroleum |
(E) Future Redevelopment of Property – Vapor Control Technology Required for Construction: DNR requires notification prior to new building construction or building modifications. Potential for vapor intrusion exists due to residual contamination. Vapor control technologies are required to be installed or modified, and verified protective unless a vapor evaluation is accepted by DNR. |
CAROL INVESTMENT CORPORATION 1410 S CLINTON ST, CHICAGO, IL 60607 |
Southeast Region Contact: Jenny Meyer jennifer.meyer1@wisconsin.gov |