CITY OF GLENDALE: Bayshore Mall Redevelopment

Purpose

water quality-related components of the construction/installation of runoff treatment devices for the Bayshore Mall Redevelopment project. Eligibility of specific components will be more thoroughly specified after completion of the project design.

Objective

To install end-of-pipe water quality treatment devices that would achieve a minimum of 40% total suspended solids (TSS) removal from the stormwater discharging from the site.

Outcome

Three Stormcepter(brnd name) devices were installed.

Related Reports

Run Project Summary Report
View Umbrella-Projects
View Related-Projects

NPS Grant
Urban Nonpoint - Stormwater Construction
MI02-40231-05
2005
Complete
 
Reports and Documents
 
Activities & Recommendations
Grant Awarded
Runoff Grant - Urban Nonpoint Source & Stormwater Management - Construction
 
Watershed