2024-01-03
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-02-16
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
SIWP APPROVAL
|
|
2023-01-23
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-12-20
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
REC'D CK #669418 $700, SIWP
|
|
2022-10-18
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
SUPPLEMENTAL SIR
|
|
2022-10-18
|
366
|
VAL and/or VRSL Exceeded at Off-Site Property or ROW
|
|
|
|
2022-07-12
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-04-05
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
SIWP NO FEE
|
|
2022-01-10
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2021-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-03-05
|
99
|
Miscellaneous
|
|
STATUS UPDATE
|
|
2021-03-03
|
99
|
Miscellaneous
|
|
STATUS INQUIRY
|
|
2021-01-20
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
PHASE II (REPORT DATED AUGUST 25, 2020)
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2019-12-05
|
99
|
Miscellaneous
|
|
EMAIL UPDATE FROM CONSULTANT, STATUS OF RECS AND PHASE II ANALYTICALS
|
|
2019-11-08
|
99
|
Miscellaneous
|
|
PHASE I ANALYTICALS
|
|
2019-09-23
|
99
|
Miscellaneous
|
|
CONSULTANT UPDATE: PHASE I AND II AT EPA FOR APPROVAL
|
|
2019-06-11
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
PHASE I
|
|
2017-01-31
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2016-10-04
|
200
|
Push Action Taken
|
|
EMAILED CONSULTANT FOR STATUS UPDATE
|
|
2016-08-03
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2016 - 6/30/2016
|
|
2016-02-17
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2015 - 12/31/2015
|
|
2015-02-05
|
99
|
Miscellaneous
|
|
MMP FROM DOT
|
|
2015-01-29
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2014 - 12/31/2014
|
|
2015-01-29
|
99
|
Miscellaneous
|
|
REC'D SOIL SAMPLE RESULTS FORM ADJACENT ROW
|
|
2014-12-17
|
43
|
Site Activity Status Update Received
|
|
UPDATE FROM CONSULTANT - SI TO HAPPEN 2015
|
|
2014-09-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2014 - 6/30/2014
|
|
2012-06-07
|
99
|
Miscellaneous
|
|
CONSULTANT SELECTED: AECOM
|
|
2012-06-06
|
99
|
Miscellaneous
|
|
ADDITIONAL SAMPLED SCHEDULED FOR FALL 2013
|
|
2012-06-01
|
99
|
Miscellaneous
|
|
PROPOSED SAMPLING BETWEEN WIDOT ^ CITY DURING WIS 83 PROJECT
|
|
2011-12-30
|
99
|
Miscellaneous
|
|
PM CHANGE LETTER SENT (CHRISTINE LILEK)
|
|
2011-12-16
|
99
|
Miscellaneous
|
|
PUSH RESPONSE FROM CITY
|
|
2011-12-07
|
200
|
Push Action Taken
|
|
|
|
2011-09-07
|
130
|
DNR Regulatory Reminder Sent
|
|
Vapor Intrusion (VI) Assessment Notification Ltr Sent
|
|
2002-11-25
|
200
|
Push Action Taken
|
|
|
|
1999-05-21
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
1998-11-03
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
1998-11-03
|
43
|
Site Activity Status Update Received
|
|
SIR FOR THE NOVA BUILDING
|