02-67-220908
JERRYS DRY CLEANING FMR
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
JERRYS DRY CLEANING (FMR) | WASHINGTON | SOUTHEAST |
Address | Municipality |
---|---|
28 S MAIN ST | HARTFORD |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the SW 1/4 of Sec 21, T10N, R18E | 43.3171728 | -88.3785333 |
![]() |
![]() |
Additional Location Description |
---|
24 S MAIN ST |
Additional Activity Details | Acres |
---|---|
UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
267170750 | 1998-11-03 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-01-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-07-05 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-02-16 | 36 | Site Investigation Workplan (SIWP) Approved |
![]() |
SIWP APPROVAL | |
2023-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2022-12-20 | 135 | Site Investigation Workplan (SIWP) Received (fee) |
![]() |
REC'D CK #669418 $700, SIWP | |
2022-10-18 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
SUPPLEMENTAL SIR | |
2022-10-18 | 366 | VAL and/or VRSL Exceeded at Off-Site Property or ROW | |||
2022-07-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-04-05 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
SIWP NO FEE | |
2022-01-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2021-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-03-05 | 99 | Miscellaneous |
![]() |
STATUS UPDATE | |
2021-03-03 | 99 | Miscellaneous |
![]() |
STATUS INQUIRY | |
2021-01-20 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received |
![]() |
PHASE II (REPORT DATED AUGUST 25, 2020) | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2019-12-05 | 99 | Miscellaneous | EMAIL UPDATE FROM CONSULTANT, STATUS OF RECS AND PHASE II ANALYTICALS | ||
2019-11-08 | 99 | Miscellaneous |
![]() |
PHASE I ANALYTICALS | |
2019-09-23 | 99 | Miscellaneous | CONSULTANT UPDATE: PHASE I AND II AT EPA FOR APPROVAL | ||
2019-06-11 | 28 | Phase I Environmental Site Assessment (ESA) Rpt Received |
![]() |
PHASE I | |
2017-01-31 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2016 - 12/31/2016 | |
2016-10-04 | 200 | Push Action Taken | EMAILED CONSULTANT FOR STATUS UPDATE | ||
2016-08-03 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2016 - 6/30/2016 | |
2016-02-17 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2015 - 12/31/2015 | |
2015-02-05 | 99 | Miscellaneous |
![]() |
MMP FROM DOT | |
2015-01-29 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2015-01-29 | 99 | Miscellaneous | REC'D SOIL SAMPLE RESULTS FORM ADJACENT ROW | ||
2014-12-17 | 43 | Site Activity Status Update Received | UPDATE FROM CONSULTANT - SI TO HAPPEN 2015 | ||
2014-09-25 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2012-06-07 | 99 | Miscellaneous | CONSULTANT SELECTED: AECOM | ||
2012-06-06 | 99 | Miscellaneous | ADDITIONAL SAMPLED SCHEDULED FOR FALL 2013 | ||
2012-06-01 | 99 | Miscellaneous | PROPOSED SAMPLING BETWEEN WIDOT ^ CITY DURING WIS 83 PROJECT | ||
2011-12-30 | 99 | Miscellaneous | PM CHANGE LETTER SENT (CHRISTINE LILEK) | ||
2011-12-16 | 99 | Miscellaneous |
![]() |
PUSH RESPONSE FROM CITY | |
2011-12-07 | 200 | Push Action Taken |
![]() |
||
2011-09-07 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2002-11-25 | 200 | Push Action Taken |
![]() |
||
1999-05-21 | 2 | Responsible Party (RP) letter sent |
![]() |
||
1998-11-03 | 1 | Notification of Hazardous Substance Discharge |
![]() |
||
1998-11-03 | 43 | Site Activity Status Update Received |
![]() |
SIR FOR THE NOVA BUILDING |
Substance | Type | Amt Released | Units |
---|---|---|---|
Gasoline - Unleaded and Leaded | Petroleum | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
CITY OF HARTFORD 109 N MAIN ST, HARTFORD, WI 53027 |
JOHN FEENEY johnm.feeney@wisconsin.gov |