CITY OF WHITEWATER: Bloomingfield Acres & E Clay St Detention Basins

Purpose

to cost-share construction of two new wet detention basins to reduce (TSS) loadings to Whitewater Creek: the Bloomingfield Acres basin at the intersection of Bloomingfield Drive and North Tratt Street (CTH N) and the East Clay Street basin at the intersection of East Clay Street and Dann Street, per the UNPS & SW Program Construction Grant Application titled Bloomingfield Acres and East Clay Street Detention Basins and submitted in 2013.

Related Reports

Run Project Summary Report
View Umbrella-Projects
View Related-Projects

NPS Grant
Urban Nonpoint - Stormwater Construction
LR14-64291-14
2014
Complete
 
Reports and Documents
Bloomingfield Acres & East Clay Street Detention Basins - Final Report
 
Activities & Recommendations
Grant Awarded
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin�s waters and was funded by the 319 grant. Specifically, the grantee will cost-share construction of two new wet detention basins to reduce (TSS) loadings to Whitewater Creek: the Bloomingfield Acres basin at the intersection of Bloomingfield Drive and North Tratt Street (CTH N) and the East Clay Street basin at the intersection of East Clay Street and Dann Street.
Runoff Grant - Urban Nonpoint Source & Stormwater Management - Construction
East Clay Street
Runoff Grant - Urban Nonpoint Source & Stormwater Management - Construction
Bloomingfield Acres
Best Management Practices, Implement
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the grantee will cost-share construction of two new wet detention basins to reduce (TSS) loadings to Whitewater Creek: the Bloomingfield Acres basin at the intersection of Bloomingfield Drive and North Tratt Street (CTH N) and the East Clay Street basin at the intersection of East Clay Street and Dann Street.
 
Watershed