02-05-586429
GP BROADWAY MILL EXPANSION - PFAS
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
GEORGIA-PACIFIC BROADWAY LLC | BROWN | NORTHEAST |
Address | Municipality |
---|---|
1919 S BROADWAY | GREEN BAY |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
SE 1/4 of the SE 1/4 of Sec 02, T23N, R20E | 44.4903718 | -88.0320692 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
Electronic Only - No Hard File | UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
405032870 | 2020-08-13 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2024-07-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-01-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-11-17 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER SAMPLING RESULTS | |
2023-09-22 | 43 | Site Activity Status Update Received |
![]() |
PFAS GROUNDWATER SAMPLING RESULTS | |
2023-07-26 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-06-05 | 43 | Site Activity Status Update Received |
![]() |
RP RESPONSE TO DNR QUESTIONS RELATED TO VI AND CONTAMINANT DELINEATION CONCERNS | |
2023-03-28 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER EVALUATION SUMMARY REPORT FOR VOCS, PAHS, METALS AND PCBS | |
2023-01-30 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2023-01-23 | 43 | Site Activity Status Update Received |
![]() |
RP RESPONSES TO DNR COMMENTS SENT VIA EMAIL ON 11/22/2022 | |
2022-11-30 | 43 | Site Activity Status Update Received |
![]() |
WASTE PROGRAM APPROVAL TO DISPOSE OF 1,600 CY OF SOIL GENERATED DURING CONSTRUCTION OF WW BUILDING | |
2022-11-29 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO ASPHALT DISPOSAL REQUEST | |
2022-11-11 | 43 | Site Activity Status Update Received |
![]() |
SUMMARY REPORT; AUGUST 2022 PFAS GROUNDWATER SAMPLING & MAY-JUNE 2022 SOIL SAMPLING FOR EXCAVATIONS | |
2022-11-10 | 43 | Site Activity Status Update Received |
![]() |
WASTE PROGRAM APPROVAL TO DISPOSE OF 950 CY OF SOIL GENERATED DURING CRANE PAD CONSTRUCTION | |
2022-09-22 | 43 | Site Activity Status Update Received |
![]() |
PFAS GROUNDWATER SAMPLING RESULTS | |
2022-08-29 | 43 | Site Activity Status Update Received |
![]() |
SITE INVESTIGATION SUMMARY SUMMARY REPORT; PFAS SOIL AND GROUNDWATER SAMPLING RESULTS | |
2022-07-28 | 43 | Site Activity Status Update Received |
![]() |
WASTE PROGRAM APPROVAL TO DISPOSE OF 60,000 CY OF SOIL GENERATED DURING INSTALLATION OF UTILITIES | |
2022-07-27 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-07-15 | 43 | Site Activity Status Update Received |
![]() |
PFAS SOIL AND GROUNDWATER SAMPLING RESULTS | |
2022-02-25 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
||
2022-01-26 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) | ADDITIONAL SOIL & GROUNDWATER INVESTIGATION | ||
2022-01-19 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2021-11-18 | 99 | Miscellaneous |
![]() |
DNR APPROVAL FOR ABANDONMENT OF MONITORING WELL MW-20-01 | |
2021-11-10 | 43 | Site Activity Status Update Received | PFAS GROUNDWATER SAMPLING RESULTS | ||
2021-08-19 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO PFAS EXPANDED SITE INVESTIGATION SUMMARY REPORT | |
2021-07-20 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-07-02 | 43 | Site Activity Status Update Received | PFAS EXPANDED SITE INVESTIGATION SUMMARY REPORT | ||
2021-06-10 | 43 | Site Activity Status Update Received |
![]() |
PFAS SOIL & GROUNDWATER SAMPLING RESULTS | |
2021-05-24 | 43 | Site Activity Status Update Received |
![]() |
PFAS GROUNDWATER SAMPLING RESULTS | |
2021-01-26 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
||
2021-01-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2020-12-18 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
||
2020-12-18 | 7 | Environmental Consultant Hired | TETRA TECH INC | ||
2020-10-19 | 2 | Responsible Party (RP) letter sent |
![]() |
||
2020-08-13 | 1 | Notification of Hazardous Substance Discharge |
![]() |
PFAS GROUNDWATER SAMPLING RESULTS (ELECTRONIC COPY); PREVIOUSLY COVERED UNDER BRRTS #02-05-583452 | |
2020-08-13 | 120 | PFAS Sampling Completed - Actionable Levels Detected | SEE AC1 OF SAME DATE FOR PFAS GROUNDWATER SAMPLING RESULTS | ||
2019-11-01 | 116 | PFAS Sampling Required |
![]() |
SAMPLING REQUESTED UNDER BRRTS #02-05-583452 | |
2019-06-28 | 114 | PFAS Scoping Statement Received |
![]() |
SUBMITTED FOR BRRTS #02-05-583452 |
Type | Related Activity |
---|---|
Property Affected -> | 13-68-585387 13425 WATERTOWN PLANK RD |
Property Affected -> | 13-68-585388 890 ELM GROVE RD |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Tetrachloroethene (Perchloroethylene) | VOC | ||
Trichloroethylene | Industrial Chem |
(A) Exceedence of Vapor Risk Levels - Vapor Mitigation Required: Vapor mitigation is required due to sub-slab or nearby soil vapor concentrations exceeding vapor risk screening levels. |
(B) Compounds of Concern in Use – Commercial/Industrial Restriction: Property use restricted to commercial or industrial. Notification of DNR required for change in property use to residential use. Vapor evaluation is required. Further cleanup may be required. |
(E) Future Redevelopment of Property – Vapor Control Technology Required for Construction: DNR requires notification prior to new building construction or building modifications. Potential for vapor intrusion exists due to residual contamination. Vapor control technologies are required to be installed or modified, and verified protective unless a vapor evaluation is accepted by DNR. |
Category | Fiscal Year | Amount |
---|---|---|
DERF Reimbursements:Grant | 2004 | $26,300 |
DERF Reimbursements:Grant | 2006 | $175,838 |
DERF Reimbursements:Grant | 2008 | $36,858 |
910 ELM GROVE ROAD LLC 910 ELM GROVE RD, ELM GROVE, WI 53122 |