Grant Details
Aquatic Invasives Control
Date
4/1/2008
Waters Involved
Echo Lake
Status
Complete
Echo Lake Assoc, Ltd: Aquatic Plant Management - Echo Lake, Barron County: Echo Lake Association is sponsoring a 4-yr. Eurasian watermilfoil (EWM) control project based on an Aquatic Plant Management Plan approved by the WI-DNR. The project includes AIS control for 2008 through 2011.
Activities include: Chemical treatment of EWM, physical removal of EWM by trained lake residents, aquatic plant surveys, monitoring for Eurasian watermilfoil weevil, walleye fingerling stocking in an attempt to manipulate the lake trophic cascade, a watercraft inspection program, in-lake monitoring for new aquatic invasive species, development of an AIS emergency response plan, water quality monitoring including dissolved oxygen profiles, protection of native aquatic plants, sediment testing to predict EWM growth, and AIS information & education outreach including boat landing signage, brochures, and resident training opportunities.
See project special conditions listed on page 3, Other Conditions.
Deliverables include a final report summarizing all activities completed under this grant, including copies of the raw data, all data and status reports, educational materials, aquatic plant survey results etc. The DNR shall receive a paper and electronic copy of the final report.
This scope summarizes the scope provided in the grant application and does not supersede grant application specifics. Data, records, and reports including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional Lake Coordinator. If a consultant is to provide a final report, it is recommended that the Grantee provide the DNR Lake Coordinator with a draft for commenting on report adequacy prior to making final payment to the consultant. Final reimbursement is dependent on DNR approval of the final report
Grant Details
Aquatic Invasives Control
Date
4/1/2011
Waters Involved
Horseshoe Lake
Status
In_Progress
Horseshoe Lake Improvement Association: Horseshoe Lake 2011-2013 Apm Plan Implementation Project: Horseshoe Lake Improvement Association is sponsoring a 3-year project to implement approved activities from its Aquatic Plant Management Plan. Activities include chemical treatment and manual removal of HWM; annual pre- and post-treatment aquatic plant surveys; EWM weevil and wild rice monitoring; watercraft inspection program; public meetings and outreach; and annual reporting. The project requires the following project updates annually: technical report with subsequent year\2019s treatment plan and communication (i.e. meeting or letter) with lake group.
Deliverables include aquatic plant survey results (spreadsheets and GIS maps); watercraft inspection data collection and SWIMS entry; I & E products; and Plan/strategy updates, as necessary. This information will be provided in an annual progress and final report with pre- and post-treatment monitoring results and treatment plan for the next year.
Special Conditions: All monitoring and management should follow approved recommendations within the Horseshoe Lake Aquatic Plant Management Plan, WDNR\2019s Aquatic Plant Management in Wisconsin guidance, and/or Citiizen Lake Monitoring Network protocols, as specified by the Department.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional Lake Coordinator.
Grant Details
Aquatic Invasives Control
Date
3/15/2023
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: 2023-24 Horseshoe Lake, Barron/Polk County Ais Management Project: Horseshoe Lake Public Inland Lake Protection and Rehabilitation District is sponsoring a project to control Hybrid and Eurasian Water Milfoil (HWM, EWM) in Horseshoe Lake. Project activities include: 1) In-lake water quality monitoring; 2) EWM Management; 3) Herbicide concentration testing; 4) Aquatic Invasive Species monitoring; 5) Lake user education; 6) Meeting Minutes
Project final deliverables include: All data collected, agendas and minutes for planning meetings, monitoring data and results, target species management plans and activities.
Specific project activities include: 1) HWM/EWM management (physical, DASH, and/or herbicide); 2) Management planning and implementation; 3) Lake user education; 4) AIS Monitoring; 5) Aquatic Plant Monitoring; 6) Water quality monitoring
Special Conditions:
1)CLMN efforts should not be duplicated, and the data shall be included in the trend analysis and final reporting.
2) All data shall be entered into the SWIMS database.
3) All monitoring completed with department approved protocols.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft or comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee\2019s final payment request.
Grant Details
Aquatic Invasives Early Detection and Response
Date
7/16/2007
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake Improvement Association: Horseshoe Lake Improvement Assoc., Rapid Response Program: Horseshoe Lake Improvement Association is sponsoring an Aquatic Invasive Species Rapid Response grant which will focus on physical removal of hybrid Eurasian Water Milfoil plants from Horseshoe Lake by scuba divers (professional and resident) and may include some small-scale chemical treatment (subject to DNR approval and permits) in fall 2007, 2008, and early season 2009. A full lake point-intercept plant survey will be completed in 2008.
Project activities include:
1) physical removal by scuba divers, 2007-2009
2) pre- and post- treatment surveying
3) small-scale chemical application (currently set at 3.5 acres or less in 2008, with the potential for a small-scale application in Fall of 2007)
4) full lake point-intercept aquatic plant survey
5) marker buoys and improved public access signage to education lake users about the hybrid EWM and to designate problem locations in the lake to minimize spread
Project deliverables include:
1) all current and future reports related to surveying completed, diving results, point-intercept plant survey, chemical application, and a final report describing overall findings, work completed, results, and guidance for continued control actions; all in digital format.
Special conditions for this project:
- all chemical application must be permitted and approved by DNR;
- final report needs department review and approval
Grant Details
Aquatic Invasives Early Detection and Response
Date
7/2/2009
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake Improvement Association: Horseshoe Lake Ais Early Detection And Responseproject, 2009-2011: The Horseshoe Lake Improvement Association is sponsoring a three-year project on Horseshoe Lake, Barron and Polk Counties, to do the following activities: hybrid Eurasian watermilfoil management and monitoring; public education, including AIS workshop(s) and web updates; watercraft inspection in partnership with the Turtle Lake School District; AIS monitoring; and development of an aquatic plant management plan including completing a sociological survey.
Deliverables associated with this project include: 1) A project report summarizing education and outreach and monitoring activities; 2) Clean Boats Clean Waters data collection summary. Data collected must include those data required as part of the CBCW program and must be entered in the statewide database to be eligible for grant reimbursement; 3) Aquatic Plant Management Plan.
Special Conditions: 1) WDNR\2019s Aquatic Plant Management in Wisconsin guidance should be followed for point-intercept survey monitoring, pre/post treatment monitoring, and aquatic plant management plan development; 2) Draft public surveys must be reviewed and approved by the Department before being initiated.
This scope is intended to summarize the detailed project scope provided in the application and does not supersede those application tasks/deliverables. Data, records, reports, and educational materials, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional lake coordinator.
Grant Details
Aquatic Invasives Education
Date
4/1/2013
Waters Involved
Echo Lake
Status
Complete
Echo Lake Assoc, Ltd: 2013-2015 Apm Plan Implementation Project: Echo Lake Association is sponsoring a 3-yr project to implement approved activities from the Echo Lake Aquatic Plant Management Plan.
Project deliverables include GIS data & maps of areas monitored, aquatic plant monitoring & bed mapping results, examples of AIS education & outreach, AIS monitoring & watercraft inspection data in SWIMS, water quality data in SWIMS, and report on shoreland restoration education.
Specific project activities include: 1) Pre-post treatment aquatic plant monitoring; 2) Fall bed mapping for Eurasian water milfoil; 3) Watercraft inspections, including Landing Blitz participation; 4) AIS education & monitoring; 5) Dissolved oxygen and temperature profile monitoring; 6) Shoreland restoration education.
Special Conditions: 1) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for aquatic plant monitoring; 2) Sponsor shall contact DNR immediately if a new AIS is found; 3) AIS monitoring and watercraft inspection personnel shall be trained and follow DNR approved protocols.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Aquatic Invasives Education
Date
2/15/2017
Waters Involved
Echo Lake
Status
Complete
Echo Lake Assoc, Ltd: Echo Lake 2-Yr Ais Management Planning And Education Project: The Echo Lake Association is sponsoring a two-year project to conduct AIS education and monitoring activities and update their APM plan.
Deliverables include AIS monitoring & watercraft inspection data in SWIMS, examples of AIS education & outreach, shoreline & woody habitat monitoring results & report, aquatic plant survey results, and an updated APM plan.
Specific project activities include: 1) Watercraft inspection; 2) EWM monitoring and treatment planning; 3) Volunteer AIS monitoring; 4) AIS outreach & education; 5) Shoreline and woody habitat surveys; 6) Spring and summer whole lake point intercept plant surveys.
Special Conditions: 1) Sponsor shall contact DNR immediately if a new AIS is found; 2) Watercraft inspection and AIS monitoring personnel shall be trained and follow DNR approved protocols; 3) Watercraft inspection and AIS monitoring data shall be entered in SWIMS; 4) Education materials shall be consistent with the Department\2019s statewide education strategy for preventing and controlling AIS; 5) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for point-intercept survey monitoring and aquatic plant management plan development. The NOR Native Plant Protection Strategy shall be integrated into the APM plan.
This scope is intended to summarize the detailed project scope provided in the application and does not supersede those application tasks/deliverables. Data, records, reports, and education materials, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional lake coordinator.
Grant Details
Aquatic Invasives Education
Date
2/15/2020
Waters Involved
Echo Lake
Status
Complete
Echo Lake Assoc, Ltd: 2020-21 Echo Lake Ais Education And Planning Project: Echo Lake Association is sponsoring a project to complete AIS education and planning including water quality sampling and various aquatic surveys.
Project deliverables include: all data collected, agendas and minutes for planning meetings.
Specific project activities include: 1) In-lake water quality monitoring; 2) Course woody debris survey; 3) Educate lake owners and residents on AIS identification; 4) Conduct signage assessment at landings and replace as needed; 5) Conduct AIS monitoring; 6) EWM bed-mapping survey; 7) Pre/Post-Treatment Plant monitoring for EWM.
Specific project conditions: 1) CLMN efforts should not be duplicated, and these data shall be included in the trends analysis and final reporting; 2) All data shall be entered into SWIMS database; 3) Shoreline assessments must be reviewed and approved by the Department before being initiated; 4) Conduct AIS monitoring with Department approved protocols. 5) Notify the local DNR AIS Coordinator of any new AIS populations identified.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
4/1/2006
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake Improvement Association: Ais Horseshoe Lake Improvement Assoc.: The Horseshoe Lake Improvement Association in partnership with Echo Lake Association and the Towns of Beaver and Almena is sponsoring a two-year project on Horseshoe and Echo Lakes, Barron and Polk Counties, to do the following activities: public education, in particular riparians; watercraft inspection (approximately 650 inspection hours in 2006); AIS monitoring; signage construction at boat landings.
Specifically the deliverables associated with this project include:
1. A project report summarizing education and outreach and monitoring activities.
2. Clean Boats Clean Waters data collection summary. Data collected must include those data required as part of the CBCW program and must be entered in the statewide database.
3. Digital images of boat landing signs.
4. An example mailing that is sent to riparians.
Special Conditions
1. Any new identification of an aquatic invasive species must be immediately reported to the Department.
2. Data, records, and reports, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional Lake Coordinator.
A draft report/deliverables should be submitted to the regional Lake Coordinator for review before finalization.
Grant Details
Aquatic Invasives Education
Date
2/15/2020
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Horseshoe Lake, Barron/Polk Pi And Update Of Apm Plan: Horseshoe Lk Public Inland Lk Protect. and Rehab. District is sponsoring a project to complete a full lake Point-Intercept survey and update the lake-wide Aquatic Plant Management Plan.
Project deliverables include: All data collected, and an updated lake management plan that included methodologies, results, and management alternatives discussion with an implementation plan.
Specific project activities include: 1) Full lake aquatic macrophyte PI-survey; 2) Water quality monitoring; 3) Lake level monitoring; 4) Course woody habitat surveys; 5) Aquatic invasive species education and monitoring of lake; 6) Aquatic invasive species signage monitoring; 7) Hybrid watermilfoil genetic testing; 8) Aquatic plant management plan update.
Specific project conditions: 1) CLMN efforts should not be duplicated, and this data shall be included in the trends analysis and final reporting; 2) All data shall be entered into SWIMS database; 3) Shoreline assessments must be reviewed and approved by the Department before being initiated; 4) All monitoring needs to be completed using Department approved protocols.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the region Lake Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
Clean Boats, Clean Waters
Date
2/15/2017
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Horseshoe Lake P & R District 2017 Cbcw: Horseshoe Lake P & R District is sponsoring a Clean Boats Clean Waters project in 2017 at 1 single public boat landings and 0 public boat landing pairs on HORSESHOE LAKE.
Grant Details
Clean Boats, Clean Waters
Date
2/15/2018
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Horseshoe Lake P & R District 2018 Cbcw: Horseshoe Lake P & R District is sponsoring a Clean Boats Clean Waters project in 2018 at 1 single public boat landings and 0 public boat landing pairs on HORSESHOE LAKE.
Grant Details
Clean Boats, Clean Waters
Date
2/15/2019
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Horseshoe Lake P&R District 2019 Cbcw: Horseshoe Lake P&R District is sponsoring a Clean Boats Clean Waters project in 2019 at 1 single public boat landings and 0 public boat landing pairs on HORSESHOE LAKE (ONLY ONE LANDING).
Grant Details
Clean Boats, Clean Waters
Date
2/15/2020
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Horseshoe Lake P&R District 2020 Cbcw: Horseshoe Lake P&R District is sponsoring a Clean Boats Clean Waters project in 2020 at 1 single public boat landings and 0 public boat landing pairs on HORSESHOE LAKE (HORSESHOE LAKE).
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Apple River
Status
Complete
Apple River P & R District: Hlk-Apple River Flowage Shoreline Native Plantings: Apple River P & R District will implement best practices described in Wisconsin\2019s 2014-2017 Healthy Lakes Implementation Plan. Practices include: 350 ft2 native plantings on 5 properties.
The best practices require a contract to remain in effect for 10 years and must include minimum operation and maintenance requirements and data collection as described in grant condition #17. If best practice(s) are implemented on land owned by the grant Sponsor, this Lake Protection Grant Agreement serves as the contract. If best practice(s) are implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner that abides by grant condition #17 is required.
The Department may require re-payment of project installation costs if the best practice is disturbed or removed. The Sponsor and/or the Department may perform site inspections and/or monitoring to ensure project success.
Deliverables: Best practice location and design information, if not included in the application; signed 10-year landowner contract; pre and post project installation photographs; summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: The state share of each best practice cannot exceed $1,000. The state share of grant administration and technical assistance costs may not exceed 10% of the grant award; technical assistance does not include implementation labor. Funding cannot be used for mitigation or regulatory compliance activities. Water regulation and/or county zoning permits must be issued before construction. The Healthy Lakes logo should be used for promotion and publicity, and DNR recognized as a funding source.
Grant Details
Lake Protection Grant
Date
4/15/2016
Waters Involved
Apple River
Status
Complete
Apple River P & R District: Hlk-319 Match -Apple River Flowage Healthy Lakes Native Plantings: Apple River P & R District will implement best practices described in Wisconsin\2019s 2014-2017 Healthy Lakes Implementation Plan. Best practices will be designed and installed according to the Healthy Lakes fact sheets and technical guidance. Practices include: 350 ft2 native plantings on 4 properties.
The best practices require a contract to remain in effect for 10 years and must include minimum operation and maintenance requirements and data collection as described in grant condition #16. If best practice(s) are implemented on land owned by the grant Sponsor, this Lake Protection Grant Agreement serves as the contract. If best practice(s) are implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner that abides by grant condition #16 is required.
The Department may require re-payment of project installation costs if the best practice is disturbed or removed. The Sponsor and/or the Department may perform site inspections and/or monitoring to ensure project success.
Deliverables: Best practice location and design information, if not included in the application; signed 10-year landowner contract; pre and post project installation photographs; summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: The state share of each best practice cannot exceed $1,000. The state share of grant administration and technical assistance costs may not exceed 10% of the grant award; technical assistance does not include implementation labor. Funding cannot be used for mitigation or regulatory compliance activities. Water regulation and/or county zoning permits must be issued before construction. The Healthy Lakes logo should be used for promotion and publicity, and DNR recognized as a funding source.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Apple River
Status
Complete
Apple River P & R District: Hlk-Apple River Flowage Healthy Lakes Native Plantings, Take 3: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Apple River Flowage
Status
Complete
Apple River P & R District: Hlk-Apple River Flowage Shoreline Native Plantings: Apple River P & R District will implement best practices described in Wisconsin\2019s 2014-2017 Healthy Lakes Implementation Plan. Practices include: 350 ft2 native plantings on 5 properties.
The best practices require a contract to remain in effect for 10 years and must include minimum operation and maintenance requirements and data collection as described in grant condition #17. If best practice(s) are implemented on land owned by the grant Sponsor, this Lake Protection Grant Agreement serves as the contract. If best practice(s) are implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner that abides by grant condition #17 is required.
The Department may require re-payment of project installation costs if the best practice is disturbed or removed. The Sponsor and/or the Department may perform site inspections and/or monitoring to ensure project success.
Deliverables: Best practice location and design information, if not included in the application; signed 10-year landowner contract; pre and post project installation photographs; summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: The state share of each best practice cannot exceed $1,000. The state share of grant administration and technical assistance costs may not exceed 10% of the grant award; technical assistance does not include implementation labor. Funding cannot be used for mitigation or regulatory compliance activities. Water regulation and/or county zoning permits must be issued before construction. The Healthy Lakes logo should be used for promotion and publicity, and DNR recognized as a funding source.
Grant Details
Lake Protection Grant
Date
4/15/2016
Waters Involved
Apple River Flowage
Status
Complete
Apple River P & R District: Hlk-319 Match -Apple River Flowage Healthy Lakes Native Plantings: Apple River P & R District will implement best practices described in Wisconsin\2019s 2014-2017 Healthy Lakes Implementation Plan. Best practices will be designed and installed according to the Healthy Lakes fact sheets and technical guidance. Practices include: 350 ft2 native plantings on 4 properties.
The best practices require a contract to remain in effect for 10 years and must include minimum operation and maintenance requirements and data collection as described in grant condition #16. If best practice(s) are implemented on land owned by the grant Sponsor, this Lake Protection Grant Agreement serves as the contract. If best practice(s) are implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner that abides by grant condition #16 is required.
The Department may require re-payment of project installation costs if the best practice is disturbed or removed. The Sponsor and/or the Department may perform site inspections and/or monitoring to ensure project success.
Deliverables: Best practice location and design information, if not included in the application; signed 10-year landowner contract; pre and post project installation photographs; summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: The state share of each best practice cannot exceed $1,000. The state share of grant administration and technical assistance costs may not exceed 10% of the grant award; technical assistance does not include implementation labor. Funding cannot be used for mitigation or regulatory compliance activities. Water regulation and/or county zoning permits must be issued before construction. The Healthy Lakes logo should be used for promotion and publicity, and DNR recognized as a funding source.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Apple River Flowage
Status
Complete
Apple River P & R District: Hlk-Apple River Flowage Healthy Lakes Native Plantings, Take 3: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Balsam Lake
Status
Complete
Balsam Lake P & R District: Acq-Bass Bay Property Acquisition: The Balsam Lake Protection & Rehabilitation District is proposing to purchase a vacant lot on Balsam Lake in Polk County. The lot is located adjacent to property owned by the lake district. The long term intent for use of this property is to maintain the property in its natural condition and preserve natural shoreland habitat.
The property will be managed in accordance with the management plan contained in the project application. A deed restriction including the following language must be inserted in the deed:
By acceptance of this deed, the sponsor, for itself and its successors and assigns, hereby covenants and agrees not to sell, lease, assign or mortgage the premises herein described without the prior written approval of the Secretary of the Department of Natural Resources, his designee, or any successor and the rights herein conveyed are subject to the interests of the State under the lake management grant program, s. 281.69 & 281.71, Statues., and NR 191 Wis. Admin. Code.
Property Legal Description:
Lot 77, Park Addition in the Village of Balsam Lake, Polk County, Wisconsin.
Grant Details
Lake Protection Grant
Date
9/1/2011
Waters Involved
Balsam Lake
Status
Complete
Balsam Lake P & R District: Acq-Stumps Bay Acquisition - Soltau Property: The Balsam Lake P&R District will purchase approximately 34 acres of property in the Stumps Bay area of Balsam Lake. The property is adjacent to property owned by the Lake District and will be maintained in a wild state and managed in accordance with the property management plan submitted with the lake protection grant application dated April 26, 2011.
The property will be managed in accordance with the management plan contained in the project application.
A deed restriction including the following language must be inserted in the deed:
By acceptance of this deed, the sponsor, for itself and its successors and assigns, hereby covenants and agrees not to sell, lease, assign or mortgage the premises herein described without the prior written approval of the Secretary of the Department of Natural Resources, his designee, or any successor and the rights herein conveyed are subject to the interests of the State under the lake management grant program, s. 281.69 & 281.71, Statues., and NR 191 Wis. Admin. Code.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Balsam Lake
Status
Complete
Balsam Lake P & R District: Hlk-Balsam Lake Native Plantings: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Beaver Dam Lake
Status
Complete
Beaver Dam Lake Management District: Hlk-Beaver Dam Lake Fish Stick Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Beaver Dam Lake
Status
Complete
Beaver Dam Lake Management District: Lmi-Library Lake Soutwest Stormwater Wetland: The Beaver Dam Lake Management District is sponsoring a project to construct a storm water wetland facility. The project will also divert storm water away from Library Lake and into the wetland facility to treat the storm water.
Special conditions: Litter shall be removed from the project property and the shoreline it borders. The wetland pond shall be operated and maintained for a minimum of 25 years in accordance with the operation and maintenance plan, which must be approved by the Department. A contract will specify these approved plans and be filed with the Register of Deeds.
The final deliverables include a summary report that includes final design updates; pre/post site photos; copies of signed operation and maintenance plans and contracts, and educational materials developed.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. The grant sponsor shall submit all data, records, and reports, including GIS-based maps and digital images, to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Big Blake Lake
Status
Complete
Blake Lake Protection & Rehabilitation Dist: Hlk-Healthy Lakes Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
7/1/2010
Waters Involved
Bone Lake
Status
Complete
Bone Lake Management District: Lmi-Bone Lake Comprehensive Plan Implementation: Bone Lake Management District will implement recommendations described in its comprehensive management plan including activities to reduce erosion; improve habitat and water quality; and expand lake protection/restoration marketing. Activities include: 1) design/build retention basins; 2) restore shorelines and integrate shoreline woody habitat; 3) implement residential diversion/infiltration best management practices (e.g. berms, rain gardens, rain barrels); 4) continue informational/educational outreach efforts, including implementing waterfront runoff marketing plan.
Shoreline restorations on properties using grant funds require a Department approved restrictive covenant permanently establishing the vegetative buffer on the parcel. Restorations will follow standards set forth in NR 191.24(3) unless mutually agreed to in writing with the regional lake coordinator before implementation occurs. Stormwater BMPs will have maintenance, operation, and protection plans specified in a ten-year contract for each site. The Department may perform site inspection and/or monitoring.
Project deliverables include: a report summarizing project activities describing accomplishments and challenges; final shoreline restoration plans/maps for grant funded implementation sites; pre/post photos of funded restorations; list of property owners and parcels committed to restrictive covenants or copies of signed covenants; educational materials developed.
Special conditions: project design plans and landowner contracts need approval before project begins; applicable water regulation permits must be issued before construction activities commence.
This scope summarizes the detail provided in the application and does not negate tasks/deliverables described therein. Data, records, reports, and education materials, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional lake coordinator.
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Bone Lake
Status
Complete
Bone Lake Management District: Lmi-Lake Management Plan Implementation: Bone Lake Management District is sponsoring a Lake Protection grant to implement activities from their approved lake management plan.
The specific project tasks include: 1) Design and install watershed BMPs; 2) Mini (10x35 foot) shoreline buffer restorations; 3) Design and install waterfront runoff projects; 4) ALUM dosage analysis; 5) Installation of woody habitat structures; 6) Establish Slow-No-Wake Ordinance; 7) Develop land protection strategy.
Maintenance, operation, and protection will be specified in a ten-year contract for each BMP site. The Department may perform site inspection and/or monitoring.
Project deliverables include: a report and map summarizing project activities including number of shoreline buffers and watershed BMPs installed, number of runoff reduction sites installed, pre/post photos of funded restorations and other BMPs, list of property owners and parcels committed to covenants and/or contracts, alum dosage report, and educational materials developed.
Special conditions: Applicable water regulation and/or county zoning permits must be issued before construction activities commence.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Church Pine Lake
Status
Complete
Church Pine Round & Big Lake P & R District: Hlk-Church Pine, Round & Big Healthy Lakes 2017: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Deer Creek
Status
Complete
Deer Lake Conservancy Inc: Lmi-Runoff Control From Direct Drainage: Deer Lake Conservancy, Inc. proposes to install storm water best management practices to control direct drainage runoff. Specifically, the Conservancy will: 1) implement individual waterfront lot infiltration practices (rain gutters with drain tiles, infiltration pits, or rain gardens) on approximately 20 riparian lots; 2) design/build restoration of approximately 4 eroded gullies; 3) provide technical and financial assistance for traditional shoreline buffer restoration; 4) establish demonstration sites with open houses/tours of restoration/infiltration sites; and 5) coordinate education outreach and sociological surveys (in the form of focus groups) to determine barriers to participation and share benefits of the projects.
Special conditions: 1) Gully project design plans need approval before project begins; 2) applicable water regulation permits must be issued before construction activities commence; and 3) focus group script must be reviewed by statewide sociologist well in advance of first session.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
9/1/1998
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Res-Deer Lake Blakeman/Hill Wetland Restoration, 1998-99: The Deer Lake Conservancy, Inc. proposes to restore a one half acre wetland on an intermittent stream in a small (211 acres) watershed that has been indentified by previous LMPG studies as contributing high phosphorus concentrations to Deer Lake. The wetland is located on the north side of Deer Lake. The wetland will be excavated to remove approximately five feet of accumulated sediments. The purpose of the project will be to restore open water habitat in this wetland, eliminate potential nutrient loading from the existing sediments, create habitat for ducks and other aquatic birds, and provide room for stormwater detention and settling of sediments and nutrients.
The Deer Lake Conservancy must comply with all regulations, restrictions, etc. that may be imposed on this project as a result of the water regulatory permit or authorization issued by the depoartment for this project. Water qualiy monitoring will be conducted on this waterway during and after the resoration project. The Deer Lake Conservancy, Inc. will provide the Department of Natural Resources with electronic and paper copies of the results of this monitoring and a final summary report on this project.
Grant Details
Lake Protection Grant
Date
9/1/2004
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Acq-Flagstad Farm Preserve Acquisition: The Deer Lake Conservancy, Inc. has purchased a 70 acre parcel known as the Flagstad Farm Preserve. This lake protection grant is to be applied to the property including Lot 22 of the Assessor's Plat of Government Lot Seven (7), section 25, Township 34 North, Range 18 West Polk County and the northern 50 acres of the acquired property. The property includes 150 feet of frontage on Deer Lake and several wetlands in addition to upland. The property will be managed in accordance with the Property Management Plan, Flagstad Farm Preserve as outlined in the project description as attached to the Project Application (Form 8700-240) for this Lake Protection Grant.
A deed restriction including the following language must be inserted in the deed:
By acceptance of this deed, the sponsor, for itself and its successors and assigns, hereby covenants and agrees not to sell, lease, assign or mortgage the premises herein described without the prior written approval of the Secretary of the Department of Natural Resources, his designee, or any successor and the rights herein conveyed are subject to the interests of the State under the lake management grant program, s. 281.69 & 281.71, Statues., and NR 191 Wis. Admin. Code.
Property Legal Description:
The Northwest Quarter of the Northeast Quarter (NW 1/4-NE 1/4) except the South 400 feet, and East 30 Acres of the Northeast Quarter of the Northwest Quarter (NE \00BC-NW \00BC) except the South 400 feet, Section 36, Township 34 North, Range 18 West, EXCEPT parcels described in Volume 234 of Records, Page 135, Document Number 300256 and in Volume 234 Records, Page 138, Document 300259. And also including Lot 22 of the Assessor's Plat of Government Lot Seven (7), Section 25, Township 34 North, Range 18 West, Polk County, Wisconsin.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Acq-Flagstad Farm Back 20: The Deer Lake Conservancy, Inc. has a land contract for 20 acres around Deer Lake. The property will be managed in accordance with the Property Management Plan, Flagstad Farm Preserve as outlined in the project description as attached to the Project Application (Form 8700-240) for this Lake Protection Grant.
A deed restriction including the following language must be inserted in the deed:
By acceptance of this deed, the sponsor, for itself and its successors and assigns, hereby covenants and agrees not to sell, lease, assign or mortgage the premises herein described without the prior written approval of the Secretary of the Department of Natural Resources, his designee, or any successor and the rights herein conveyed are subject to the interests of the State under the lake management grant program, s. 281.69 & 281.71, Statues., and NR 191 Wis. Admin. Code.
Legal Description:
The South 400 feet of the Northwest Quarter of the Northeast Quarter (NW \00BC NE \00BC), and the East 30 acres of the Northeast Quarter of the Northwest Quarter (NE \00BC NW \00BC), Section 36, Township 34 North, Range 18 West, Polk County, Wisconsin, Except parcels described in Volume 234 of Records, Page 135, Document Number 300256 and in Volume 234 Records, Page 138, Document 300259, containing approximately 20 acres.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Lmi-Runoff Control From Direct Drainage: Deer Lake Conservancy, Inc. proposes to install storm water best management practices to control direct drainage runoff. Specifically, the Conservancy will: 1) implement individual waterfront lot infiltration practices (rain gutters with drain tiles, infiltration pits, or rain gardens) on approximately 20 riparian lots; 2) design/build restoration of approximately 4 eroded gullies; 3) provide technical and financial assistance for traditional shoreline buffer restoration; 4) establish demonstration sites with open houses/tours of restoration/infiltration sites; and 5) coordinate education outreach and sociological surveys (in the form of focus groups) to determine barriers to participation and share benefits of the projects.
Special conditions: 1) Gully project design plans need approval before project begins; 2) applicable water regulation permits must be issued before construction activities commence; and 3) focus group script must be reviewed by statewide sociologist well in advance of first session.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
7/1/2011
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Lmi-Nearing The Goal: Deer Lake Watershed Phosphorus Reduction: Deer Lake Conservancy is sponsoring a project to design/build an iron/sand filter pond with pretreatment in a agriculture-dominated subwatershed (Watershed 1); continue the 2007 Direct Drainage best practices project to slow runoff and restore habitat; develop a land protection/conservation plan; promote community information and education. Watershed 1 pre-construction water quality data will be compared to post-construction data.
Special conditions: The iron/sand filter pond and pretreatment practices shall be operated and maintained for a minimum of 10 years in accordance with the operation and maintenance (O&M) plan, which must be approved by the Department. A contract will specify the approved plans and be filed with the Register of Deeds. All enrolled shoreline restoration parcels require a Department-approved restrictive covenant that permanently establishes the parcel vegetative buffer. Restorations will follow NR 191.24(3) standards unless mutually agreed to in writing with the regional lake coordinator before implementation. Runoff BMPs such as rain gardens and infiltration trenches will have maintenance, operation, and protection plans specified in a ten-year contract for each BMP site. The Department may perform site inspection and/or monitoring.
Project deliverables: pre/post site photos of implemented practices; pond engineering/design plans; copies of O&M plans and contracts; final shoreline restoration plans/maps and copies of deed restrictions if implementation is funded by the Department; land protection plan; educational materials developed; project summary report including water quality data comparison.
This scope summarizes the detailed scope in the project application and does not supersede those application tasks/deliverables. Data, records, reports, and education materials, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional lake coordinator.
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Acq-Johnson Preserve Acquisition: Deer Lake Conservancy is sponsoring a grant to help fund the fee title acquisition of the Johnson Preserve property which includes approximately 95 acres located in part of Section 25, in the Town of St. Croix Falls and part of Section 30 in the Town of Balsam Lake, Polk County.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Deer Lake
Status
Complete
Deer Lake Conservancy Inc: Lower Rock Creek Acquisition: The Deer Lake Conservancy has purchased 32.10 acres of undeveloped property on Deer Lake in Polk County. The parcel includes approximately 500 feet of shoreline, a riparian wetland and has Rock Creek flowing through the property. The property is adjacent to existing Conservancy owned property. Trails will be developed connecting with existing trails of the adjacent property.
Grant Details
Lake Protection Grant
Date
3/15/2022
Waters Involved
Echo Lake
Status
Complete
Echo Lake Assoc, Ltd: Hlr - Echo Lake Association - Healthy Lakes Projects: Partnering with property owners, Echo Lake Association is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts.
Special conditions:
Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
If rain garden practices located within the 35 foot buffer zone will need Barron County Zoning permits prior to begining work on practice. If location is not approved, the rain garden will need to be moved further from the lake.
Grant Details
Lake Protection Grant
Date
9/1/2010
Waters Involved
Half Moon Lake
Status
Complete
Half Moon Lake Conservancy, Inc.: Acq-Tamarack Bay Rostvolt Acquisition: The Half Moon Lake Conservancy is sponsoring a project involving the acquisition of two lake lots totaling 31.5 acres and a conservation easment on 8.14 acres on Tamarack Bay of Half Moon Lake and inlcuding portions of Tamarack Creek, a tributary to Tamarack Bayall in the town of Milltown in Polk County. The acquistition is being donated in fee and easement to Half Moon Lake Conservancy Inc. Project funding will assist with project expenses associated with the baseline study, appraisal costs, and misc. legal and closing costs.
Grant Details
Lake Protection Grant
Date
9/1/2010
Waters Involved
Harder Creek
Status
Complete
Half Moon Lake Conservancy, Inc.: Acq-Tamarack Bay Rostvolt Acquisition: The Half Moon Lake Conservancy is sponsoring a project involving the acquisition of two lake lots totaling 31.5 acres and a conservation easment on 8.14 acres on Tamarack Bay of Half Moon Lake and inlcuding portions of Tamarack Creek, a tributary to Tamarack Bayall in the town of Milltown in Polk County. The acquistition is being donated in fee and easement to Half Moon Lake Conservancy Inc. Project funding will assist with project expenses associated with the baseline study, appraisal costs, and misc. legal and closing costs.
Grant Details
Lake Protection Grant
Date
4/15/2019
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake P&R District: Hlk-2019-20 Horseshoe Lake Shoreland Habitat Improvement: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes Example Report is available to assist you.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables
Grant Details
Lake Protection Grant
Date
9/1/2010
Waters Involved
Library Lake
Status
Complete
City Of Cumberland: Acq-Library Lake - Neurer Acquisition: The City of Cumberland is sponsoring a land acquisition project to acquire a permanent limited easement on the Richard and Lorrain Neurer property.
This acquisition project is part of a mulit phase stormwater management project within the City. The Neurer easement is for the purpose of installing a stormwater best management practice on the eased property.
Special conditions for this project: the draft permanent limited easement must be reviewed by the Department prior to signing.
Grant Details
Lake Protection Grant
Date
7/1/2011
Waters Involved
Library Lake
Status
Complete
Beaver Dam Lake Management District: Lmi-Library Lake Ne Stormwater Wetland: Beaver Dam Lake Management District in partnership with the City of Cumberland propose to design/build a stormwater pretreatment and wetland pond and restore shoreline on City-owned property along the NE shore of Library Lake and to promote public information and education, including local school district participation.
Special conditions: Litter should be removed from the project property and the shoreline it borders. The wetland pond shall be operated and maintained for a minimum of 10 years in accordance with the operation and maintenance plan, which must be approved by the Department. A contract will specify these approved plans and be filed with the Register of Deeds.
Project deliverables include: final shoreline restoration plans/maps if implementation is funded by the Department; pre/post site photo; wetland pond engineering/design plans and copies of operation and maintenance plans and contracts; educational materials developed and project summary report.
This scope is intended to summarize the detailed project scope provided in the application and does not supersede those application tasks/deliverables. Data, records, reports, and education materials, including GIS-based maps and digital images, must be submitted to the Department in a format specified by the regional lake coordinator.
Grant Details
Lake Protection Grant
Date
7/1/2013
Waters Involved
Library Lake
Status
Complete
Beaver Dam Lake Management District: Acq-Southeast Library Lake Land Acquisition: The Beaver Dam Lake Management District is sponsoring a grant which will provide funding for a fee title land acquisition project iinvolving property on the southeast side of Library Lake. This acquisition is one of a number of acquisitions proposed to be used by the City of Cumberland for installation of a stormwater treatment facility. Ownership of the property will be transfered to the City of Cumberland.
Project activities include the acquisition of the property and associated closing activities; demonlition of the structure on the parcel to be acquired.
Grant Details
Lake Protection Grant
Date
2/15/2017
Waters Involved
Library Lake
Status
Complete
Beaver Dam Lake Management District: Acq-Desantis Property Acquisition: The Beaver Dam Lake Management District is purchasing approximately 0.6 acres of property on the southwest side of Library Lake. The property will be used to treat stormwater runoff through the use of a wetland complex. The project is being done in cooperation with the City of Cumberland. The lake district will own the property and the City will maintain the stormwater facilities.
A legal description of the property is as follows:
GL 9-13, being part of Government Lot 9 described as part of residential lot 1, TP Stone's Oak Park Addition, beginning at a point on the south line of Elm Street along US Highway 63, 1120 feet west of west line of 2nd Street; thence west along Elm & 63 152 feet; thence south parallel to 2nd Street 172 feet; thence east 152 feet; thence north 172 feet to point of beginning. Except that part in SE-NW, Section 7 T35N, R13W described as beginning on the south line of Elm Street 1120 feet west of west line of 2nd Avenue; thence south to point 30 feet south of center line of Highway 63; thence west 132.5 feet parallel to said center line; thence north to south line of Elm Street; thence east to point of beginning, in the unplatted City of Cumberland, Barron County, Wisconsin.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Little Blake Lake
Status
Complete
Blake Lake Protection & Rehabilitation Dist: Hlk-Healthy Lakes Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
10/1/2013
Waters Involved
Long Lake
Status
Complete
Long Lake Prot & Rehab Dist: Lmi-Waterfront Projects Design & Installation And Alum Dosage Study: Long Lake P&R District is sponsoring a Lake Protection grant to protect and improve Long Lake water quality by designing and implementing shoreline restoration and runoff reduction practices. The project also includes an Alum dosage study.
Specific project tasks include: 1) Shoreline design/restoration on approximately 10 shoreline sites; 2) Design/installation of rain gardens, rock gardens, rock pits, and swales; 3) Alum dosage study.
Shoreline restorations will follow standards set forth in NR 191.24(3) unless mutually agreed to in writing with the regional lake coordinator before implementation occurs. Shoreline restorations using grant funding for plants or labor require a Department approved restrictive covenant that permanently establishes the vegetative buffer on the parcel. This project includes BMPs such as rain gardens and shoreline stabilization. Maintenance, operation, and protection will be specified in a ten-year contract for each BMP site. The Department may perform site inspection and/or monitoring.
Project deliverables include: a report and map summarizing project activities, including documenting linear feet of shoreline stabilized, square feet of shoreline buffer restored, and number of runoff reduction sites installed; individual property shoreline restoration/stabilization plans/maps; pre/post photos of funded restorations; list of property owners and parcels committed to covenants and/or contracts; and Alum dosage report.
Special conditions: Applicable water regulation and/or county zoning permits must be issued before construction activities commence.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Coordinator.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Lost Creek
Status
Complete
Blake Lake Protection & Rehabilitation Dist: Hlk-Healthy Lakes Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Magnor Lake
Status
Complete
Lake Magnor Lake Association: Hlk-Healthy Lakes - Lake Magnor, Phase 1: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
3/15/2022
Waters Involved
Magnor Lake
Status
Complete
Polk County: Lmi - Magnor Lake Management Plan Implementation: Polk will partner with Magnor Lake District and agricultural landowners to install BMPs that will reduce phosphorus loading to Magnor Lake. Deliverables include: engineered design plans, maps of locations of installed BMPs, operation and maintenance (O&M) plans, costshare contracts, and a final report that describes the installed BMPs and estimates nutrient and sediment reductions. Activities include: design and install watershed conservation practices including grassed waterways, water and sediment control basins, contour buffer strips, shoreline restoration, and cover crops. Special Conditions: Restoration projects utilizing grant funds or used as match to this grant require pre-approval from the WDNR. All permits must be issued before construction, and all regulatory requirements apply. Designs shall follow NRCS standards and comply with county zoning standards for shoreline restoration. Polk County shall enter into landuse agreements for lands restored utilizing grant funding or used as match to the project to ensure land restored remains in conservation per s. NR 193. A 10-year O&M period is required for approved Healthy Lakes and Rivers projects. All other restoration projects require the land be maintained for conservation for a 20-year period through a land use agreement including a O&M plan recorded at the Registrar of Deeds Office. With each reimbursement request, grantee must provide: a list of practices to reduce nonpoint source pollution installed since during the period for which you are seeking reimbursement. For each practice, include date installed, cost and estimated load reductions for N, P, and Sediment lb/yr. WDNR staff may be contacted for technical assistance.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the WDNR in a format specified by the Biologist.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Nepadoggen Creek
Status
Complete
Lake Magnor Lake Association: Hlk-Healthy Lakes - Lake Magnor, Phase 1: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
3/15/2022
Waters Involved
Nepadoggen Creek
Status
Complete
Polk County: Lmi - Magnor Lake Management Plan Implementation: Polk will partner with Magnor Lake District and agricultural landowners to install BMPs that will reduce phosphorus loading to Magnor Lake. Deliverables include: engineered design plans, maps of locations of installed BMPs, operation and maintenance (O&M) plans, costshare contracts, and a final report that describes the installed BMPs and estimates nutrient and sediment reductions. Activities include: design and install watershed conservation practices including grassed waterways, water and sediment control basins, contour buffer strips, shoreline restoration, and cover crops. Special Conditions: Restoration projects utilizing grant funds or used as match to this grant require pre-approval from the WDNR. All permits must be issued before construction, and all regulatory requirements apply. Designs shall follow NRCS standards and comply with county zoning standards for shoreline restoration. Polk County shall enter into landuse agreements for lands restored utilizing grant funding or used as match to the project to ensure land restored remains in conservation per s. NR 193. A 10-year O&M period is required for approved Healthy Lakes and Rivers projects. All other restoration projects require the land be maintained for conservation for a 20-year period through a land use agreement including a O&M plan recorded at the Registrar of Deeds Office. With each reimbursement request, grantee must provide: a list of practices to reduce nonpoint source pollution installed since during the period for which you are seeking reimbursement. For each practice, include date installed, cost and estimated load reductions for N, P, and Sediment lb/yr. WDNR staff may be contacted for technical assistance.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the WDNR in a format specified by the Biologist.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
North Twin Lake
Status
Complete
City Of Amery: Lmi-Amery Lakes Management Plan Implementation: The City of Amery in partnership with the Amery Lakes District will develop a storm water management plan/ordinance and implement run-off control best management practices in priority (i.e. high nutrient load) sub-watersheds. Specifically, the City will: 1) update existing ordinances and develop a storm water management plan to reduce non-point source pollution; 2) design/build wetland basins and rain gardens at Soldier's Field; 3) design-build rain gardens at Flagpole Park; 4) select and install storm water control (e.g. rain gardens and barrels, shoreline buffers, porous pavement, and/or infiltration trenches) practices at demonstration sites within city limits; 5) develop example storm water education materials that will be applicable to other small cities; 6) inventory and measure in-lake habitat, including undeveloped shoreline and critical areas and develop plans for long-range protection and for measuring success of storm water control BMPs.
Special conditions:
* Project design plans need approval before project begins, and applicable water regulation permits must be issued before construction activities commence.
* Best management practices installed at Soldier's Field and Flagpole Park will be maintained for a minimum of 10 years.
* An operation and maintenance plan will be developed for care of the BMPs.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
3/2/1994
Waters Involved
Pike Lake
Status
Complete
City Of Amery: Acq-Pike Lake - York Acquisition: The City of Amery will acquire approximately 32.7 acres of land along the northwest side of Pike Lake. Project costs include the cost of the parcel ($160,500) and the appraisal cost ($950).
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Pike Lake
Status
Complete
City Of Amery: Lmi-Amery Lakes Management Plan Implementation: The City of Amery in partnership with the Amery Lakes District will develop a storm water management plan/ordinance and implement run-off control best management practices in priority (i.e. high nutrient load) sub-watersheds. Specifically, the City will: 1) update existing ordinances and develop a storm water management plan to reduce non-point source pollution; 2) design/build wetland basins and rain gardens at Soldier's Field; 3) design-build rain gardens at Flagpole Park; 4) select and install storm water control (e.g. rain gardens and barrels, shoreline buffers, porous pavement, and/or infiltration trenches) practices at demonstration sites within city limits; 5) develop example storm water education materials that will be applicable to other small cities; 6) inventory and measure in-lake habitat, including undeveloped shoreline and critical areas and develop plans for long-range protection and for measuring success of storm water control BMPs.
Special conditions:
* Project design plans need approval before project begins, and applicable water regulation permits must be issued before construction activities commence.
* Best management practices installed at Soldier's Field and Flagpole Park will be maintained for a minimum of 10 years.
* An operation and maintenance plan will be developed for care of the BMPs.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Rock Creek
Status
Complete
Deer Lake Conservancy Inc: Lmi-Runoff Control From Direct Drainage: Deer Lake Conservancy, Inc. proposes to install storm water best management practices to control direct drainage runoff. Specifically, the Conservancy will: 1) implement individual waterfront lot infiltration practices (rain gutters with drain tiles, infiltration pits, or rain gardens) on approximately 20 riparian lots; 2) design/build restoration of approximately 4 eroded gullies; 3) provide technical and financial assistance for traditional shoreline buffer restoration; 4) establish demonstration sites with open houses/tours of restoration/infiltration sites; and 5) coordinate education outreach and sociological surveys (in the form of focus groups) to determine barriers to participation and share benefits of the projects.
Special conditions: 1) Gully project design plans need approval before project begins; 2) applicable water regulation permits must be issued before construction activities commence; and 3) focus group script must be reviewed by statewide sociologist well in advance of first session.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Sand Creek
Status
Complete
Sand Lake Management District: Lmi-Sand Lake Wash Repair & Agricultural Bmp Project: Sand Lake Management District is sponsoring a Lake Protection grant to repair gulley erosion, provide agricultural BMP incentives, and monitor tributaries to document nutrient reductions.
The specific project tasks include: 1) NW Gulley Washout repair; 2) Agriculture BMP incentive payments; 3) Tributary and outlet water quality monitoring; 4) Field and lake BMP educational tours.
Maintenance, operation, and protection will be specified in a ten-year contract for each BMP site. The Department may perform site inspection and/or monitoring.
Project deliverables include: annual summary reports and maps summarizing project activities including NW Gulley repair, categories and acres of agriculture BMP\2019s installed, copies of agriculture BMP contracts, stakeholder meeting agendas and minutes, water quality sampling results, and educational materials developed.
Special conditions: Applicable water regulation and/or county zoning permits must be issued before construction activities commence.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
Grant Details
Lake Protection Grant
Date
4/15/2015
Waters Involved
Sand Lake
Status
Complete
Sand Lake Management District: Lmi-Sand Lake Wash Repair & Agricultural Bmp Project: Sand Lake Management District is sponsoring a Lake Protection grant to repair gulley erosion, provide agricultural BMP incentives, and monitor tributaries to document nutrient reductions.
The specific project tasks include: 1) NW Gulley Washout repair; 2) Agriculture BMP incentive payments; 3) Tributary and outlet water quality monitoring; 4) Field and lake BMP educational tours.
Maintenance, operation, and protection will be specified in a ten-year contract for each BMP site. The Department may perform site inspection and/or monitoring.
Project deliverables include: annual summary reports and maps summarizing project activities including NW Gulley repair, categories and acres of agriculture BMP\2019s installed, copies of agriculture BMP contracts, stakeholder meeting agendas and minutes, water quality sampling results, and educational materials developed.
Special conditions: Applicable water regulation and/or county zoning permits must be issued before construction activities commence.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
Grant Details
Lake Protection Grant
Date
9/1/2004
Waters Involved
Silver Lake
Status
Complete
Barron County: Lmi-Silver Lake Water Quality Diagnostic Feasibility Study: The Barron County Soil & Water Conservation Department, in cooperation with the US Geological Survey, Dept. of Nat. Res., and a private consultant, will conduct a comprehensive diagnostic/feasibility study of Silver Lake and it's watershed and develop a lake management plan.
The project includes the following objectives ( ) and activities [ ]; (1) Determination of the source(s) of pollutants that have caused recent reductions of water quality - [watershed assessment], [shoreline assessment], [complete water quality study], [develop hydrologic budget], [develop phosphorus budget], [develop groundwater model], [lake sediment core assessment], [shoreline septic systems assessment], [lake bacterial water quality assessment], and [an assessment of the feasibility of a water level control device], (2) Prediction of probable water quality responses to possible pollution reduction practices - [assessment of lake water quality responses utilizing acceptable computer "models"], (3) Protection of Silver Lake from invasive exotic aquatic species - [conduct aquatic plant survey to detect any exotic species], [recommend measures to prevent future exotic species infestations], (4) Evaluation of the fishery of Silver Lake - [Wis. DNR will conduct fishery survey and prepare report]
Project deliverables include a USGS water-resources investigations report, or equivalent document, a USGS fact sheet, or equivalent document, and a comprehensive lake management report for the Silver Lake system.
Conditions for this project include:
* The installation of stream and lake gauging stations must receive the approval and/or permit from the Department of Natural Resources water regulation section.
The Department of Natural Resources will be provided with electronic and paper copies of the annual and final reports of the results of this study and the lake management plan. Project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.
Grant Details
Lake Protection Grant
Date
9/1/2012
Waters Involved
Silver Lake
Status
Complete
Silver Lake Association: Lmi-Waterfront Lots Water Quality Improvements: Silver Lake Association is sponsoring a project to implement shoreline stabilization, restoration, runoff reduction, and wetland restoration practices.
Project tasks: 1) Design/stabilization on approximately 10 shoreline sites; 2) Shoreline restoration design technical assistance; 3) Design/installation on approximately 6 runoff reduction sites; 4) Install woody habitat improvement (Fish Sticks) on approximately 4 sites; 5) Design/implement wetland restoration; 6) Landscaper training/education.
Shoreline restorations using grant funding for plants or labor require a Department approved restrictive covenant to permanently establish the parcel vegetative buffer. Restorations will follow NR 191.24(3) standards unless mutually agreed to in writing with the DNR lake coordinator before implementation. BMPs such as rain gardens and shoreline stabilization must have maintenance, operation, and protection plans specified in a ten-year contract.
Project deliverables: report and map summarizing project activities, documenting linear feet of shoreline stabilized, square feet of shoreline buffer restored, number of Fish Stick sites with numbers of trees used, number of runoff reduction sites installed; individual property shoreline restoration/stabilization plans/maps; pre/post photos of funded restorations; list of property owners and parcels committed to covenants and/or contracts; and educational materials developed.
This scope summarizes details provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the DNR Lake Coordinator.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Straight River
Status
Complete
Blake Lake Protection & Rehabilitation Dist: Hlk-Healthy Lakes Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Unnamed
Status
Complete
Deer Lake Conservancy Inc: Lmi-Runoff Control From Direct Drainage: Deer Lake Conservancy, Inc. proposes to install storm water best management practices to control direct drainage runoff. Specifically, the Conservancy will: 1) implement individual waterfront lot infiltration practices (rain gutters with drain tiles, infiltration pits, or rain gardens) on approximately 20 riparian lots; 2) design/build restoration of approximately 4 eroded gullies; 3) provide technical and financial assistance for traditional shoreline buffer restoration; 4) establish demonstration sites with open houses/tours of restoration/infiltration sites; and 5) coordinate education outreach and sociological surveys (in the form of focus groups) to determine barriers to participation and share benefits of the projects.
Special conditions: 1) Gully project design plans need approval before project begins; 2) applicable water regulation permits must be issued before construction activities commence; and 3) focus group script must be reviewed by statewide sociologist well in advance of first session.
A final report in PDF format summarizing the results of the project as well as copies of databases, maps, GIS files, guidebooks, ordinances or any other products resulting from the project shall be provided to the Department for review prior to final payment.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Unnamed
Status
Complete
Beaver Dam Lake Management District: Hlk-Beaver Dam Lake Fish Stick Project: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Unnamed
Status
Complete
Beaver Dam Lake Management District: Lmi-Library Lake Soutwest Stormwater Wetland: The Beaver Dam Lake Management District is sponsoring a project to construct a storm water wetland facility. The project will also divert storm water away from Library Lake and into the wetland facility to treat the storm water.
Special conditions: Litter shall be removed from the project property and the shoreline it borders. The wetland pond shall be operated and maintained for a minimum of 25 years in accordance with the operation and maintenance plan, which must be approved by the Department. A contract will specify these approved plans and be filed with the Register of Deeds.
The final deliverables include a summary report that includes final design updates; pre/post site photos; copies of signed operation and maintenance plans and contracts, and educational materials developed.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. The grant sponsor shall submit all data, records, and reports, including GIS-based maps and digital images, to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Unnamed
Status
Complete
Lake Magnor Lake Association: Hlk-Healthy Lakes - Lake Magnor, Phase 1: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Lake Protection Grant
Date
4/15/2017
Waters Involved
Wind Lake
Status
Complete
Church Pine Round & Big Lake P & R District: Hlk-Church Pine, Round & Big Healthy Lakes 2017: Partnering with property owners, the applicant is sponsoring a grant to implement water quality and habitat best practices from Wisconsin\2019s Healthy Lakes Implementation Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to the Healthy Lakes fact sheets, technical guidance and grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in grant condition #16 at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a Conservation Contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required.
The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: Signed 10-year landowner Conservation Contract(s) with operation and maintenance requirements; data collected; pre and post project installation photographs; and summary of education activities and publicity/promotion of Healthy Lakes initiative, if applicable.
Special conditions: Project management and technical assistance costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction, and all regulatory requirements apply. The Healthy Lakes logo should be used for promotion and publicity and DNR recognized as a funding source.
This scope summarizes the scope in the grant application and attachments and does not supersede those application tasks/deliverables.
Grant Details
Large Scale Lake Planning
Date
2/15/2016
Waters Involved
Horseshoe Lake
Status
Complete
Horseshoe Lake Improvement Association: Horseshoe Lake Water Quality & Education Project: The Horseshoe Lake Improvement Association is sponsoring a water quality and education project for Horseshoe Lake.
Project deliverables include GIS data & maps of areas monitored, water quality and flow data, bed mapping data, shoreline and woody habitat data, sediment P release report, and a hybrid milfoil treatment report.
Specific project activities include: 1) Tributary and in-lake monitoring; 2) Precipitation monitoring; 3) Shoreline and woody habitat survey; 4) Lake sediment phosphorus release study; 5) AIS education; 6) Fall EWM bed mapping.
Special Conditions: 1) CLMN efforts should not be duplicated, and these data shall be included in the trends analysis and final reporting; 2) Sponsor shall contact DNR immediately if a new AIS is found; 3) All monitoring data shall be entered into SWIMS.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. The grant sponsor shall submit all data, records, and reports, including GIS-based maps and digital images, to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Large Scale Lake Planning
Date
4/1/2001
Waters Involved
Magnor Lake
Status
Complete
Polk County: Magnor Lake Planning - Phase I: The Polk County Land & Water Resources Department will conduct a comprehensive lake management planning project involving two phases of study and evaluation on Magnor Lake in Polk County. Phase 1 project activities include; delineating the watershed, compiling of historical data, conducting a comprehensive in-lake water quality survey, conducting a critical habitats survey, compiling a comprehensive land use and soils inventory with phosphorus loadings estimates, monitoring lake level and precipitation, conducting a lake bottom hydrographic survey update, conducting a shoreline video documentation survey, compiling fisheries census and management data, and conducting an on-going public participation, media involvement , and information and education program. The results of the Phase 1 and Phase 2 study projects will be combined to generate a comprehensive lake management plan for Lake Magnor and the watershed.
Specific deliverables for this grant project include:
? Complete records of all phase 1 project activities listed above and in the application project description.
Specific deliverables for this phased grant project (Phase 1 and Phase 2) include:
? A comprehensive lake management plan for Magnor Lake and the watershed.
The Department of Natural Resources will be provided with both a paper copy and an electronic copy of the final report. The project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.
Grant Details
Large Scale Lake Planning
Date
4/1/2001
Waters Involved
Magnor Lake
Status
Complete
Polk County: Magnor Lake Planning - Phase Ii: The Polk County Land & Water Resources Department will conduct a comprehensive lake management planning project involving two phases of study and evaluation on Magnor Lake in Polk County. Phase 2 project activities include; conducting a watershed biodiversity survey, conducting an exotic species inventory, conducting a sociological landowner survey, conducting a watershed inflow storm event sampling survey, developing hydrologic and nutrient budgets and a computer lake response model, conducting a lake sediment dredge sample and analysis survey, conducting an on-going public participation, media involvement, and information and education program, and completing a comprehensive lake management plan. The results of the Phase 1 study project will be combined with this Phase 2 study project to generate a comprehensive lake management plan for Lake Magnor and the watershed.
Specific deliverables for this grant project include:
? Complete records of all phase 2 project activities listed above and in the application project description.
? A comprehensive lake management plan for Magnor Lake and the watershed.
The Department of Natural Resources will be provided with both a paper copy and an electronic copy of the final report. The project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.
Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Magnor Lake
Status
Complete
Lake Magnor Lake Association: Lake/Watershed Management Master Plan & Sediment Core Project: The Lake Magnor Lake Association will conduct a Lake/Watershed Management Master Plan Development Project for Magnor Lake in Polk County. Previous grant projects have been and are being conducted on this lake to collect the water quality and other data necessary to proceed with the development of a comprehensive lake management plan. Activities involved in this current Management Plan project include; review of all existing lake data, conduct of public meetings to collect additional lake use data and user input, conduct a watershed survey, conduct a lake sediment core study, conduct watershed and water quality/quantity modeling and evaluate development scenarios, evaluate available information and develop a draft Phase 1 LWMMP report.
The specific deliverable for this project will consist of a final grant project report, including a listing of all grant activities and results, and a copy of the final "LWMMP" supplement.
The Department of Natural Resources will be provided with both a paper copy and an electronic copy of the final report. The project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.
Grant Details
Large Scale Lake Planning
Date
2/15/2018
Waters Involved
Magnor Lake
Status
Complete
Polk County: Magnor Lake Water Quality Assessment & Lmp Development: Polk County is sponsoring a water quality and Lake Management Plan project for Magnor Lake.
Project deliverables include GIS data & maps of areas monitored; water quality, flow, precipitation, and water level data, shoreline monitoring data and report, phytoplankton data & analysis, watershed modeling, aquatic plant data and reports, and a Comprehensive Lake Management Plan that meets the requirements of NR 191.45.
Specific project activities include: 1) In-lake chemistry monitoring; 2) Tributary chemistry and flow monitoring; 3) Lake water level monitoring; 4) Precipitation monitoring; 5) Shoreline monitoring; 6) Phytoplankton monitoring; 7) Spring and summer whole lake point intercept aquatic plant surveys; 8) Watershed modeling using LiDAR; 9) Sociological survey; 10) Comprehensive Lake Management Plan.
Special Conditions: 1) CLMN efforts should not be duplicated, and these data shall be included in the trends analysis and final reporting; 2) Sponsor shall contact DNR immediately if a new AIS is found; 3) All monitoring data shall be entered into SWIMS; 4) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for point-intercept survey monitoring and aquatic plant management plan development. The NOR Native Plant Protection Strategy shall be integrated into the plan; 5) Draft sociological surveys must be reviewed and approved by the Department before being initiated.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. The grant sponsor shall submit all data, records, and reports, including GIS-based maps and digital images, to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Nepadoggen Creek
Status
Complete
Lake Magnor Lake Association: Lake/Watershed Management Master Plan & Sediment Core Project: The Lake Magnor Lake Association will conduct a Lake/Watershed Management Master Plan Development Project for Magnor Lake in Polk County. Previous grant projects have been and are being conducted on this lake to collect the water quality and other data necessary to proceed with the development of a comprehensive lake management plan. Activities involved in this current Management Plan project include; review of all existing lake data, conduct of public meetings to collect additional lake use data and user input, conduct a watershed survey, conduct a lake sediment core study, conduct watershed and water quality/quantity modeling and evaluate development scenarios, evaluate available information and develop a draft Phase 1 LWMMP report.
The specific deliverable for this project will consist of a final grant project report, including a listing of all grant activities and results, and a copy of the final "LWMMP" supplement.
The Department of Natural Resources will be provided with both a paper copy and an electronic copy of the final report. The project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.
Grant Details
Large Scale Lake Planning
Date
2/15/2018
Waters Involved
Nepadoggen Creek
Status
Complete
Polk County: Magnor Lake Water Quality Assessment & Lmp Development: Polk County is sponsoring a water quality and Lake Management Plan project for Magnor Lake.
Project deliverables include GIS data & maps of areas monitored; water quality, flow, precipitation, and water level data, shoreline monitoring data and report, phytoplankton data & analysis, watershed modeling, aquatic plant data and reports, and a Comprehensive Lake Management Plan that meets the requirements of NR 191.45.
Specific project activities include: 1) In-lake chemistry monitoring; 2) Tributary chemistry and flow monitoring; 3) Lake water level monitoring; 4) Precipitation monitoring; 5) Shoreline monitoring; 6) Phytoplankton monitoring; 7) Spring and summer whole lake point intercept aquatic plant surveys; 8) Watershed modeling using LiDAR; 9) Sociological survey; 10) Comprehensive Lake Management Plan.
Special Conditions: 1) CLMN efforts should not be duplicated, and these data shall be included in the trends analysis and final reporting; 2) Sponsor shall contact DNR immediately if a new AIS is found; 3) All monitoring data shall be entered into SWIMS; 4) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for point-intercept survey monitoring and aquatic plant management plan development. The NOR Native Plant Protection Strategy shall be integrated into the plan; 5) Draft sociological surveys must be reviewed and approved by the Department before being initiated.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. The grant sponsor shall submit all data, records, and reports, including GIS-based maps and digital images, to the Department in a format specified by the regional Lakes Biologist.
Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Unnamed
Status
Complete
Lake Magnor Lake Association: Lake/Watershed Management Master Plan & Sediment Core Project: The Lake Magnor Lake Association will conduct a Lake/Watershed Management Master Plan Development Project for Magnor Lake in Polk County. Previous grant projects have been and are being conducted on this lake to collect the water quality and other data necessary to proceed with the development of a comprehensive lake management plan. Activities involved in this current Management Plan project include; review of all existing lake data, conduct of public meetings to collect additional lake use data and user input, conduct a watershed survey, conduct a lake sediment core study, conduct watershed and water quality/quantity modeling and evaluate development scenarios, evaluate available information and develop a draft Phase 1 LWMMP report.
The specific deliverable for this project will consist of a final grant project report, including a listing of all grant activities and results, and a copy of the final "LWMMP" supplement.
The Department of Natural Resources will be provided with both a paper copy and an electronic copy of the final report. The project results will be disseminated to the public by newsletter(s), public meeting(s), and local newspaper articles.