Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Arbter Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Big Marsh
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Bradley Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Butler Pond
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Clark Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Coffee Swamp
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Dunes Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Europe Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Forestville Flowage
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Kangaroo Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
3/15/2024
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Aquatic Plant Management Plan - North Basin Phase1: The Kangaroo Lake Association is sponsoring a project to update the aquatic plant portion of the Kangaroo Lake Comprehensive Lake Management Plan.
Activities: 1) Collect current aquatic plant data on Kangaroo Lake north basin which includes a whole-lake point-intercept survey, an aquatic plant community survey and a late-season EWM mapping survey; 2) Development of a report describing the current aquatic plant community in Kangaroo Lake and changes based on comparisons with historic data with specific attention to assessing the effectiveness of the on-going aquatic plant protection and restoration efforts in Kangaroo Lake.
Deliverables: 1) all data collected 2) agendas and minutes for planning meetings 3) a report that includes methodologies, results, and management alternatives discussions.
Conditions:
1) Aquatic plant monitoring shall follow DNR approved protocols.
2) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for aquatic plant monitoring and aquatic plant management plan development.
This scope summarizes details provided in the application and does not negate tasks and/or deliverables described therein. Data, reports, surveys, and supporting information, including photos, maps and GIS data, must be submitted to the DNR Biologist in electronic format and in any other format they specify.
If a consultant provides a final report, it is recommended that the Grantee provide the DNR Biologist with a draft for comment on report adequacy prior to making a final payment to the consultant. Include electronic copy of the final report along with or prior to submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
3/15/2024
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Aquatic Plant Management Plan - South Basin Phase2: The Kangaroo Lake Association is sponsoring a project to update the aquatic plant portion of the Kangaroo Lake Comprehensive Lake Management Plan.
Activities: 1) Collect current aquatic plant data on Kangaroo Lake south basin which includes a whole-lake point-intercept survey, an aquatic plant community survey, and a late-season EWM mapping survey; 2) Development of a report describing the current aquatic plant community in Kangaroo Lake and changes based on comparisons with historic data with specific attention to assessing the effectiveness of the on-going plant protection and restoration efforts in Kangaroo Lake.
Deliverables: 1) all data collected 2) agendas and meeting minutes for planning meetings 3) a report that includes methodologies, results, and management alternatives discussion.
Conditions:
1) Aquatic plant monitoring shall follow DNR approved protocols.
2) WDNR\2019s Aquatic Plant Management in Wisconsin guidance shall be followed for aquatic plant monitoring and aquatic plant management plan development.
This scope summarizes details provided in the application and does not negate tasks and/or deliverables described therein. Data, reports, surveys, and supporting information, including photos, maps and GIS data, must be submitted to the DNR Biologist in electronic format and in any other format they specify.
If a consultant provides a final report, it is recommended that the Grantee provide the DNR Biologist with a draft for comment on report adequacy prior to making a final payment to the consultant. Include electronic copy of the final report along with or prior to submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Lake Michigan
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Little Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Little Marsh
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Little Sturgeon Bay
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Lost Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Mackaysee Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Mink River Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Mud Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Pinney Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Pluff Pond
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Schwartz Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Sturgeon Bay
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Thorp Pond
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Unnamed
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Upper Lost Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Voecks Marsh
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Aquatic Invasives Education
Date
10/1/2005
Waters Involved
Zoo Lake
Status
Complete
Door County: Door County Ais Coordination Project: The Door County Land and Water Conservation Department proposes to conduct an aquatic invasive species (AIS) education, prevention, planning and control project in partnership with the Door County Invasive Species Team during the period of October 2005 - December 2007. The project elements and deliverables are specified in the Door County Soil and Water Conservation Department's Aquatic Invasive Species Control Grant application, dated July 29, 2005. The project includes hiring a coordinator; integrating and coordinating AIS control efforts with recruitment and training sessions for volunteers; identifying and recording locations of priority problem species; developing county-wide control plans for purple loosestrife, Phragmites, reed canary grass and other AIS; measuring the success of control measures; creating an AIS control equipment loan program; holding Demonstration Control Field Days to increase volunteer knowledge of monitoring and control techniques; coordinating the township volunteer invasive species monitors; conducting "Clean Boats, Clean Waters" and rusty crayfish workshops; managing an AIS database, website and advertising; designing and distributing AIS fact sheets; assisting partners in developing AIS control projects and obtaining funding for their implementation; and obtaining additional funding to implement county-wide control projects and maintain the coordinator position. A mid-term progress report and a final report summarizing the two-year project will be provided to DNR.
The grantee will provide the DNR Aquatic Invasive Species Coordinator with a draft of the final report for comment on report adequacy prior to requesting final reimbursement. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Nearshore Health and NPS
Date
10/1/2010
Waters Involved
Lake Michigan
Status
Proposed
Egg Harbor Beach And Boat Trailer Parking Lot Improvements: The Village is proposing to repave an 18’ wide strip of pavement (the drive aisle) with a pervious strip that will reduce the volume of runoff leaving the parking lot. The Village would also make improvements to divert a greater portion of the runoff from the parking lot to the existing biofilter.
Grant Details
Nearshore Health and NPS
Date
10/1/2010
Waters Involved
Lake Michigan
Status
Proposed
Establishment Of Regional Rapid Method Test Facilities In Wi: This project would expand existing (Racine and/or Milwaukee Counties) and establish new rapid test method labs in the Lake Superior region (serving Ashland, Bayfield, Douglas, and Iron Counties), Door County (Serving Brown, Door, and Kewaunee counties), and Manitowoc (serving Manitowoc and Sheboygan counties). This project would provide all infrastructure required including all equipment and training needed to start using the qPCR rapid test methods. By leveraging current testing facilities (Ashland, Sturgeon Bay, Manitowoc, Racine, and Milwaukee) and using this capital investment all of Wisconsin's coastal waters would be able to get beach testing results within 4 hours.
Grant Details
Nearshore Health and NPS
Date
10/1/2010
Waters Involved
Sturgeon Bay
Status
Proposed
Implementation Of Bmps At Beaches To Improve Water Quality: The project will focus on developing a cost share program for the construction of practices for reducing storm water contamination at seven beaches throughout the County. These seven beaches completed the preliminary and final design process for addressing storm water run off and discharge to their beaches and are therefore eligible to participate in the SWCD’s beach contamination reduction implementation project.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Arbter Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
2/19/1996
Waters Involved
Bass Lake
Status
Complete
Marinette County: Res - Bass Lake Restoration Alum Treatment: Marinette County proposes to treat Bass Lake with alum to reduce the effects of sediment phosophorus in the lake. Project activities include treating all waters of Bass Lake in excess of 3 feet deep and conducting pre and post treatment water quality monitoring.
AMENDMENT #1: Marinette County proposes a "5 fold" increase the Alum dose in Bass Lake to provide long term control of P release from enriched sediments.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Big Marsh
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Bradley Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Butler Pond
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Clark Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Coffee Swamp
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Dunes Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Europe Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Forestville Flowage
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
5/24/1996
Waters Involved
Kangaroo Lake
Status
Complete
The Nature Conservancy: Acq-Kangaroo Lake Land Acquisition - Michelsen Property: The Nature Conservany will acquire approximately 60 acres of land situated along the west side of the north end of Kangaroo Lake 1) to create a significant buffer for the large undisturbed wetland/shallow marl lake system, 2) to protect the north end of the lake from large scale development, and 3) to protect the property's dolomite planteau which is a probable recharge site of the shallow aquifer that feeds the lake through springs near share and in Peil Creek. Approximately 12 acres adjacent to County E (Maple Rd.) on the west edge of the property consists of an old field of predominately low herbaceous vegetation. The remainder of the property is forested. Shrubs grow on the lake edge of the shoreline ridge. The acquisition of this property is part of the sponsor's Kangaroo Lake/Piel Creek Complex plan. The primary goals of the property's management are contained in the Kangaroo Lake/Peil Creek Project Management Plan and include 1) to maintain or improve the water quality of Piel Creek and the integrity of the riparian corridor of the creek and the lake shoreline; to protect and restore as necessary, natural hydrologic systems, and 2) to preserve and enhance the site's native plant and animal communities, ensuring that the entire gradient of natural communities represented is protected; to protect the forest areas from further fragmentation or logging.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Kangaroo Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
9/1/2002
Waters Involved
Kangaroo Lake
Status
Complete
The Nature Conservancy: Acq-Kangaroo Lake Land Acquisition (Ritger): The Nature Conservancy proposes to purchase for conservancy purposes 83.2 acre parcel on Kangaroo Lake known as the Ritger parcel.
Grant Details
Lake Protection Grant
Date
9/1/2004
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Res-Kangaroo Lake Bulrush Restoration Project: The Kangaroo Lake Association proposes to conduct an experiment with the re-establishment of native bulrushes within the southern slow-no-wake area on Kangaroo Lake. Hard-stem bulrush (Schoenoplectus acutus) and soft-stem bulrush (Schoenoplectus tabernaemontani) would be planted in plots at different lengths from the shoreline and monitored to verify if they establish and expand. A report detailing the findings with recommendations will be supplied to the Kangaroo Lake Association and the Department of Natural Resources in hardcopy and PDF format.
Grant Details
Lake Protection Grant
Date
3/15/2022
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Hlr-Kangaroo Lake Fish Sticks 2022: Partnering with property owners, Kangaroo Lake Association\00A0is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions:\00A0 Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement.\00A0 The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Lake Michigan
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Little Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Little Marsh
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Little Sturgeon Bay
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Lost Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Mackaysee Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1996
Waters Involved
McCaslin Lake
Status
Complete
Mccaslin Lake District: Acq-Mccaslin Lake Land Acquisition-Hansen (Parcel A) Property: The Mc Caslin Lake Rehabilitation District will acquire 25.88 acres of lowland, including water frontage and wetlands, on Mc Caslin Lake for lake protection purposes. Long term management goals for this property include preserving it as a quiet natural conservancy area used for passive outdoor recreation and enjoyment. No major development plans are included.
Grant Details
Lake Protection Grant
Date
2/1/1998
Waters Involved
McCaslin Lake
Status
Complete
Mccaslin Lake District: Acq-Mccaslin Lake District Hansen Ii Acq.: The McCaslin Lake District will acquire an additional 38.50 acres of land near McCaslin Lake for conservancy purposes.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Mink River Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Mud Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Pinney Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Pluff Pond
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Schwartz Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Sturgeon Bay
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Thorp Pond
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Unnamed
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Upper Lost Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Voecks Marsh
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Lake Protection Grant
Date
4/1/1998
Waters Involved
Zoo Lake
Status
Complete
Door County: Lco-Door County Inventory Of Surface Water Resources: Door County Soil & Water Conservation Department proposes to conduct a phased approach to the development of protection strategies for its waters including lakes. This phase of the project will collect and analyze information regarding surface water resources in order to develop specific implementation recommendations for phase II indlucing upgrading regulatory programs. Project deliverables shall include a draft and final report containing: 1) an inventory and classification of county inland lakes; 2) appropriate supporting data and maps and; 3) recommendations specifying phase II implementation activities including proposed regulatory standards for shoreland and lake protection. Electronic copieis will be made available upon request of all final reports and maps.
Grant Details
Large Scale Lake Planning
Date
10/1/2007
Waters Involved
Bradley Lake
Status
Complete
City Of Sturgeon Bay: Little (Bradley) Lake Planning Grant Ph 2: the City of Sturgeon Bay proposes to conduct a lake planning project (Phase 2) which will develop a final report and actions including the following:
1. Recommendations
2. Design/construction plans
3. Public participation process and summary
Grant Details
Large Scale Lake Planning
Date
10/1/2007
Waters Involved
Bradley Lake
Status
Complete
City Of Sturgeon Bay: Little (Bradley) Lake Planning Grant Phase 1: The City of Sturgeon Bay proposes to conduct a lake planning project (Phase 1) that will develop an appraisal report and conceptual designs including the following:
1. Public participation integration
2. Watershed delineation w/ pollutant load estimate
3. Lake water quality appraisa
4. Aquatic Plant survey
5. Fish harvest appraisal
6. Conceptual rehabilitation plan
Grant Details
Large Scale Lake Planning
Date
2/15/2018
Waters Involved
Bradley Lake
Status
Complete
City Of Sturgeon Bay: Bradley Lake Coastal Resource Management Plan: The City of Sturgeon Bay is sponsoring a project to develop a long-term lake management plan that will address the designed habitat maintenance and water quality requirements for Bradley Lake.
Project final deliverables include: all data collected, agendas and minutes for planning meetings, presentations, water quality data reports, newsletters and educational materials provided to the public.
Specific project activities include: 1) Define the existing conditions of aquatic habitat types of the nearshore Sturgeon Bay area by conducting a bathymetric survey, topographic survey and aerial photography of the shoreline areas; 2) Involve the community with the lake management planning process and communication of project results through several public meetings and input opportunities; 3) Development of a final comprehensive lake management plan that addresses Bradley Lake\2019s water quality, fishery, and aquatic ecosystem habitat and recreational usage and management practices within Sunset Park.
Special Conditions: 1) Collection of water quality samples and laboratory analysis will not be funded by this grant.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Rivers Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Biotic Eval & Strategic Plan Study Phase 1: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted January 30, 2005. Phase 1 of the study will include lake and river water quality sampling, stream flow measurements, macroinvertebrate sampling, coordinator, and faculty associated with overall study, macroinvertebrate and fishery study components.
Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Biotic Eval & Strategic Study Phase 2: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted January 30, 2005. Phase 2 of the study will include the marl/turbidity study, the fishery habitat component, Hines Emerald dragonfly survey, septic system survey, graduate student salary for sampling, historic record review, and beginning the hydraulic modeling.
If consultant is to provide the final report, it is recommended the Grantee provide the DNR Aquatic Invasive Species Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Bioltic Evaluation & Strategic Plan Study Ph 4: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted August 1, 2005. Phase 4 of the study will include lake water quality sampling for marl/turbidity sampling and analysis in 2006 student assistance, UWSP coordinator, and faculty associated with overall study.
If consultant is to provide the final report, it is recommended the Grantee provide the DNR Lakes Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Biotic Evaluation & Strategic Plan Study Ph 3: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted August 1, 2005. Phase 3 of the study will include lake water quality sampling for winter 2006 and fall macroinvertebrate sampling, student assistance, UWSP coordinator, and faculty associated with overall study.
Grant Details
Large Scale Lake Planning
Date
4/1/2006
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Biotic Evaluation & Strategic Plan Study Ph 5: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted January 30, 2006. Phase 5 of the study will include lake and tributary water quality sampling and analysis, continuous flow monitoring, travel costs and student assistance associated with overall study.
Grant Details
Large Scale Lake Planning
Date
4/1/2006
Waters Involved
Clark Lake
Status
Complete
Ridges Sanctuary Inc: Clark Lake Water Quality, Biotic Evaluation & Strategic Plan Study Ph 6: The Ridges Sanctuary in cooperation with the Clark Lake Association proposes to conduct water quality and biotic evaluation and strategic planning in the Clark Lake watershed in Door County. The project elements and deliverables are specified in the grant application materials submitted January 30, 2006. Phase 6 of the study will include aquatic macrophyte survey, sensitive area survey and mapping, and faculty, staff, and student assistance associated with overall study.
If consultant is to provide the final report, it is recommended the Grantee provide the DNR Lakes Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to, submission of grantee's final payment request.
Grant Details
Large Scale Lake Planning
Date
10/1/2008
Waters Involved
Dunes Lake
Status
Complete
Door County: Dunes Lake Watershed Study Ph 2: Door County Soil & Water Conservation Department proposes to conduct monitoring on Dunes Lake and its watershed to better understand the watershed contributions to Dunes Lake. The monitoring results will used to educate and inform the public about the lake and effects of land use practices on water quality. Data collected from this effort will be used to develop a management plan and implementation strategy for the Dunes Lake watershed. The project elements and deliverables will be completed as described in the project proposal submitted to the Department and dated July 31, 2008.
Grant Details
Large Scale Lake Planning
Date
4/1/2009
Waters Involved
Dunes Lake
Status
Complete
Door County: Dunes Lake Watershed Study Ph 3: Door County Soil and Water Conservation Department proposes to continue to assess surface and groundwater impacts to Geisel Creek and Dunes Lakes in a multi-phased project. Phase 3 will focus on the role of groundwater in the water budget and nutrient loading in Geisel Creek and Dunes Lake through the delineation of the hydrologic connections between surface and groundwater in the watershed. Specifically, phase 3 will contract with UW-Madison graduate student to investigate the hydrology of the Dunes Lake watershed, determine a water budget for Dunes Lake, delineate the zone of groundwater contribution to at least three springs, evaluate the nutrients present in groundwater and surface water samples taken throughout the watershed, investigate the use of viral tracing from the treatment ponds, and develop a final report. The project elements and deliverables are specified in the grant application materials submitted to the Department dated February 1, 2009.
Grant Details
Large Scale Lake Planning
Date
10/1/2009
Waters Involved
Dunes Lake
Status
Complete
Door County: Door County Dunes Lake Watershed Study Ph 4: AMENDED SCOPE: Door County Soil and Water Conservation Department proposes to continue to assess the connectivity between surface and groundwater hydrology of the Dunes Lake watershed. This is a multi-phased project to help define pollutant sources to Dunes Lake. Specifically, phase 4 will collect water quality samples to investigate connectivity through chemical analysis. The results of this phase will be summarized in a final report. The project elements and deliverables are specified in the grant application materials submitted to the Department dated July 30, 2009.
Grant Details
Large Scale Lake Planning
Date
4/1/1997
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Milfoil Weevil Study: Kangaroo Lake Association proposes to document the distribution and evaluate the potential of the aquatic weevil, Euhrychiopis lecontei as a Eurasian Watermilfoil control agent on Kangaroo Lake. Project activies will result in a field evaluation of experimental weevil stocking, a status report and presentation to the lake group, and a final report including feasibility recommendations.
Grant Details
Large Scale Lake Planning
Date
10/1/2002
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Comp Lake Mgt Plan Dev. Ph 2: Kangaroo Lake Association proposes to conduct studies and develop a comprehensive lake management plan for Kangaroo Lake. The study will take place in two phases. This is phase 2 and will include an inventory of native and exotic aquatic plants, an assessment of the lake's shoreline condition concerning natural habitat and buffering areas, and data analysis and report development. The Department of Natural Resources will be provided with both a paper copy and electronic copy of the final lake management plan.
Grant Details
Large Scale Lake Planning
Date
10/1/2002
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Comp Lake Mgt Plan Dev. Phase 1: Kangaroo Lake Association proposes to conduct studies and develop a comprehensive lake management plan for Kangaroo Lake. The study will take place in two phases. This is phase 1 and will include public participation and education, plan development discussions with the project steering committee, preliminary assessments of the Kangaroo Lake watershed, lake water quality analysis and modeling, and data analysis and report development. The Department of Natural Resources will be provided with both a paper copy and electronic copy of the final lake management plan.
Grant Details
Large Scale Lake Planning
Date
2/15/2016
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Management Plan Update: The Kangaroo Lake Association is sponsoring a project to update their Comprehensive Lake Management Plan with special emphasis on the lake\2019s north lobe.
Project final deliverables include: all data collected, agendas and minutes for planning meetings, and a lake management plan that includes methodologies, results, and management alternatives discussion with an implementation plan.
Specific project activities include: 1) Water quality and watershed assessment and modeling; 2) Fisheries data compilation and integration within the management plan; 3) Shoreline and coarse woody habitat assessment; 4) Assessment of the current aquatic plant community; 5) Aquatic invasive plant surveys; 6) Completion of stakeholders survey; 7) Public participation in the planning process; 8) Volunteer AIS monitoring; 9) Creation of a comprehensive lake management plan that includes an implementation strategy.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request
Grant Details
Small Scale Lake Planning
Date
4/1/2014
Waters Involved
Dunes Lake
Status
Complete
Door County: Dunes Lake Prot & Feas. Study: Door County Soil and Water Conservation Department proposes to hire an Engineering/Consulting firm to complete a feasibility study. The developed concept plan will identify and evaluate passive treatment technologies that can be implemented to reduce nutrient loads from the wastewater treatment lagoons. The plan will include planning level cost estimates and a summary of the operation and maintenance of the passive polishing cell system. The project elements and deliverables are specified in the grant application materials submitted to the Department dated January 31, 2014.
Grant Details
Small Scale Lake Planning
Date
4/1/2014
Waters Involved
Dunes Lake
Status
Proposed
Door County: Dunes Lake Prot & Feas. Study: Door County Soil and Water Conservation Department proposes to hire an Engineering/Consulting firm to complete a feasibility study. The developed concept plan will identify and evaluate passive treatment technologies that can be implemented to reduce nutrient loads from the wastewater treatment lagoons. The plan will include planning level cost estimates and a summary of the operation and maintenance of the passive polishing cell system. The project elements and deliverables are specified in the grant application materials submitted to the Department dated January 31, 2014.
Grant Details
Small Scale Lake Planning
Date
4/1/2014
Waters Involved
Kangaroo Lake
Status
Complete
Kangaroo Lake Association, Inc.: Kangaroo Lake Shroreline Pres. & Rest. Plan: Kangaroo Lake Association proposes to undertake a shoreline preservation and restoration planning and implementation project. Kangaroo Lake Association will obtain and disseminate information, conduct educational opportunities, develop action plans and begin implementation of shoreline restoration activities by assisting lake land owners to place dropped trees in the water along their shoreline and assessing and planting bulrush along shoreline where they once thrived. The project elements and deliverables are specified in the grant application materials submitted to the Department dated January 22, 2014.
Grant Details
Small Scale Lake Planning
Date
4/1/2014
Waters Involved
Kangaroo Lake
Status
Proposed
Kangaroo Lake Association, Inc.: Kangaroo Lake Shroreline Pres. & Rest. Plan: Kangaroo Lake Association proposes to undertake a shoreline preservation and restoration planning and implementation project. Kangaroo Lake Association will obtain and disseminate information, conduct educational opportunities, develop action plans and begin implementation of shoreline restoration activities by assisting lake land owners to place dropped trees in the water along their shoreline and assessing and planting bulrush along shoreline where they once thrived. The project elements and deliverables are specified in the grant application materials submitted to the Department dated January 22, 2014.
Grant Details
Targeted Runoff - Rural Construction
Date
8/10/2005
Waters Involved
Shivering Sands Creek
Status
Complete
Door County: Shivering Sands/Haberli Project: To cost-share retrofit of manure storage and runoff practices to address violations of performance standards.
Grant Details
Targeted Runoff - Rural Construction
Date
8/10/2005
Waters Involved
Unnamed
Status
Complete
Door County: Logan Creek/Lautenbach Site: To cost-share installation of manure storage and barnyard runoff practices to address violations of performance standards on the Gerald Polster farm within the Hibbards Creek sub-watershed.
Grant Details
River Planning Grant
Date
2/15/2016
Waters Involved
Fish Creek
Status
Complete
Town Of Gibraltar: Fish Creek Improvement And Protection Plan: The Town of Gibraltar is sponsoring a project to develop a community based Improvement and Protection Plan for Fish Creek.
Project final deliverables include: all data collected, agendas and minutes for planning meetings, and a river management plan that includes methodologies, results, and management alternatives discussion with an implementation plan.
Specific project activities include: 1) Evaluate existing nutrient and flow data for Fish Creek; 2) Develop a model to estimate flow, sediment, and nutrients to Fish Creek; 3) Gather sociological information and solicit participation in the planning process; 4) Develop a 9-Key element watershed based plan and an improvement and protection plan that addresses groundwater infiltration and water flow in Fish Creek while reducing stormwater runoff. The plan will also identify strategies to address invasive species and restore and protect fishery and wildlife habitat.
Special Conditions: 1) Draft sociological/user surveys must be reviewed and approved by the Department before being initiated.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Rivers Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
River Protection Grant
Date
4/15/2018
Waters Involved
Fish Creek
Status
Complete
Town Of Gibraltar: Restoring Fish Passage To Fish Creek: The Town of Gibraltar is sponsoring a project to begin implementing their 2017 Fish Creek Watershed Plan which involves stream restoration and fish passage improvements in Fish Creek in Door County.
Project final deliverables include: all design plans and a final report summarizing the project.
Specific project activities include: 1) Developing a conceptual design plan and cost estimate for State Highway 42 culvert fish passage; 2) Developing a conceptual design plan and completion of meander restoration and stream channel enhancement of Fish Creek upstream of State Highway 42; 3) Developing a conceptual design plan and cost estimate for Redmann dam fish passage.
Special Conditions: 1) Prior to construction, the Town will obtain all requisite landowner access and permits as required from WDNR, the US Army Corps of Engineers (USACOE), Door County, and other regulatory agencies or municipalities.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Rivers Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
River Protection Grant
Date
4/15/2018
Waters Involved
Fish Creek
Status
In_Progress
Town Of Gibraltar: Restoring Fish Passage To Fish Creek: The Town of Gibraltar is sponsoring a project to begin implementing their 2017 Fish Creek Watershed Plan which involves stream restoration and fish passage improvements in Fish Creek in Door County.
Project final deliverables include: all design plans and a final report summarizing the project.
Specific project activities include: 1) Developing a conceptual design plan and cost estimate for State Highway 42 culvert fish passage; 2) Developing a conceptual design plan and completion of meander restoration and stream channel enhancement of Fish Creek upstream of State Highway 42; 3) Developing a conceptual design plan and cost estimate for Redmann dam fish passage.
Special Conditions: 1) Prior to construction, the Town will obtain all requisite landowner access and permits as required from WDNR, the US Army Corps of Engineers (USACOE), Door County, and other regulatory agencies or municipalities.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Rivers Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Grant Details
River Protection Grant
Date
4/15/2020
Waters Involved
Fish Creek
Status
Complete
Town Of Gibraltar: Restoring Fish Passage To Fish Creek At The Hwy 42 Culvert: The Town of Gibraltar is sponsoring a project to install fish passage improvements past the box culvert at State Highway 42 on Fish Creek in Door County.
Project final deliverables include: all design plans, an installed fish ladder and baffles and a final report summarizing the project.
Specific project activities include: 1) Installation of a fish ladder to the apron of the culvert at STH 42 on Fish Creek which will allow fish easier access to the culvert; 2) Installation of baffles inside the culvert which will help concentrate the water flow during times of low water and also provide a place for the fish to get out of the current and rest when needed; 2) Coordination with agencies such as WisDOT, WDNR, US Army Corps of Engineers (USACOA), and US Fish & Wildlife Service as identified in the selected design from Miller Engineers Scientists; 4) Hold at least one public meeting regarding this project; and 5) Summarize the project in a final report.
Special Conditions: 1) Prior to construction, the Town will obtain all requisite landowner access and permits as required from WDNR, the USACOE, Door County, and other regulatory agencies or municipalities.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Rivers Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.