Watershed - Roxbury Creek (LW18)
Roxbury Creek Watershed

Details

The Roxbury Creek Watershed lies mostly in northwest Dane County although a small portion of it extends into Columbia County. Land use in the watershed is predominantly agricultural, although a good percentage of the watershed is covered by broad-leaf deciduous forest. There are no incorporated municipalities in the watershed.

Date  2002

Population, Land Use

Overall population in the watershed in 2000 was estimated to be around 5,500 people. Residential development in the watershed is increasing as a result of the watershed's proximity to Madison.

Date  2002

Nonpoint and Point Sources

The major known water quality problems in the watershed are from nonpoint source pollution. The Roxbury Creek watershed is ranked as a high priority for nonpoint source pollution reduction. The Dunlap Creek sub-watershed was chosen as a small-scale nonpoint source pollution abatement project. Streams in the watershed are also impacted by stream channelization and portions of Dunlap Creek have been extensively channeled. Development pressure in the watershed could pose a threat to water quality in the watershed. In addition, a portion of the watershed is in an atrazine prohibition area. These areas indicate that elevated levels of atrazine, an herbicide used on corn, has been found in some tested private water wells. Soils are permeable which has allowed atrazine to reach groundwater in some locations. The Crystal Lake Campground discharges to groundwater in the watershed and the Roxbury Sewerage District discharges to Roxbury Creek.

Date  2002

Ecological Landscapes for Roxbury Creek Watershed

Ecological Landscapes

The western half of the Roxbury Watershed is located in the Western Coolee and Ridges Ecological Landscape and the eastern half is located within the Central Sand Hills Ecological Landscape. The Western Coulee and Ridges Ecological Landscape in southwestern and west central Wisconsin is characterized by its highly eroded, driftless topography and relatively extensive forested landscape. Soils are silt loams (loess) and sandy loams over sandstone residuum over dolomite. Several large rivers including the Wisconsin, Mississippi, Chippewa, Kickapoo and Black flow through or border the Ecological Landscape. Historical vegetation consisted of southern hardwood forests, oak savanna, scattered prairies, and floodplain forests and marshes along the major rivers. With Euro-American settlement, most of the land on ridgetops and valley bottoms was cleared of oak savanna, prairie, and level forest for agriculture. The steep slopes between valley bottom and ridgetop, unsuitable for raising crops, grew into oak-dominated forests after the ubiquitous presettlement wildfires were suppressed. Current vegetation is a mix of forest (40%), agriculture, and grassland with some wetlands in the river valleys. The primary forest cover is oak-hickory (51%) dominated by oak species and shagbark hickory. Maple-basswood forests (28%), dominated by sugar maple, basswood and red maple, are common in areas that were not subjected to repeated presettlement wildfires. Bottomland hardwoods (10%) are common in the valley bottoms of major rivers and are dominated by silver maple, ashes, elms, cottonwood, and red maple. Relict conifer forests including white pine, hemlock and yellow birch are a rarer natural community in the cooler, steep, north slope microclimates. The Central Sand Hills Ecological Landscape is located in central Wisconsin at the eastern edge of what was once Glacial Lake Wisconsin. The landforms in this Ecological Landscape are a series of glacial moraines that were later partially covered by glacial outwash. The area is characterized by a mixture of farmland, woodlots, wetlands, small kettle lakes, and cold water streams, all on sandy soils. The mosaic of glacial moraine and pitted outwash throughout this Ecological Landscape has given rise to extensive wetlands in the outwash areas, and the headwaters of coldwater streams that originate in glacial moraines. The growing season is long enough for agriculture but the sandy soils limit agricultural productivity somewhat. Historic upland vegetation consisted of oak-forest, oak savanna, and tallgrass prairie. Fens were common in this Ecological Landscape and occurred along with wet-mesic prairie, wet prairie, and rare coastal plain marshes. Current vegetation is composed of more than one-third agricultural crops, and almost 20% grasslands with smaller amounts of open wetland, open water, shrubs, barren, and urban areas. The major forested type is oak-hickory, with smaller amounts of white-red-jack pine, maple-basswood, lowland hardwoods, aspen-birch, and spruce-fir.

Date  2002

Recreational Opportunities

The Mazomanie and Black Hawk units of the Lower Wisconsin State Riverway lie in this watershed. The Mazomanie unit is 4,261 acres (only 3,518 are owned, the rest are leased). This unit has areas of marsh, potholes, forest, lake and stream and offers a variety of recreational opportunities from a dog training ground, Class I field trial grounds, fishing, canoeing, birdwatching, berry picking and hiking. The Black Hawk Unit is 800 acres of state owned land and has a historical site as well as opportunities to cross country ski, and birdwatch.

Date  2002

Wildlife and Habitat

The watershed is also home for a variety of rare plant and animal species including; 1 species of beetle, 3 species of birds, 3 species of butterflies, 3 species of dragonflies, 13 species of fish, 1 species of grasshopper, 3 species of moths, 8 species of mussels, 30 plant species, 3 species of snakes, 2 species of mammals and 1 species of lizard. These plants and animals are also listed on the state's Natural Heritage Inventory (NHI).

Date  2002

Watershed Documents
Watershed Grants
Grant Details
Aquatic Invasives Education
Date
10/1/2011
Waters Involved
Crystal Lake
Status
Complete

Dane County: Aquatic Mgmt Plan Amendment: Dane County Office of Lakes and Watersheds will update Aquatic Plant Management (APM) Plans on the following lakes: Crystal, Fish, Indian, Lower Mud, Upper Mud, and the Yahara River between Lakes Monona and Kegonsa. All these waters are sources of established populations of Eurasian watermilfoil, among other exotics, and are managed via county harvesting operations. In addition, the new Lake Belle View may require harvesting, so a new APM plan will be developed for that lake. Updated monitoring and amended plans are recommended by DNR for the other waters. A consultant will use established point intercept maps to survey current plant populations, and use those data to re-evaluate management plans, ensuring that the best management options are being implemented. Regular updates are presented in public meetings to Dane County staff and the Dane County Lakes and Watershed Commission. Updated plans are posted on the county website.


Grant Details
Aquatic Invasives Education
Date
10/1/2011
Waters Involved
Fish Lake
Status
Complete

Dane County: Aquatic Mgmt Plan Amendment: Dane County Office of Lakes and Watersheds will update Aquatic Plant Management (APM) Plans on the following lakes: Crystal, Fish, Indian, Lower Mud, Upper Mud, and the Yahara River between Lakes Monona and Kegonsa. All these waters are sources of established populations of Eurasian watermilfoil, among other exotics, and are managed via county harvesting operations. In addition, the new Lake Belle View may require harvesting, so a new APM plan will be developed for that lake. Updated monitoring and amended plans are recommended by DNR for the other waters. A consultant will use established point intercept maps to survey current plant populations, and use those data to re-evaluate management plans, ensuring that the best management options are being implemented. Regular updates are presented in public meetings to Dane County staff and the Dane County Lakes and Watershed Commission. Updated plans are posted on the county website.


Grant Details
Clean Boats, Clean Waters
Date
2/15/2019
Waters Involved
Lake Wisconsin
Status
Complete

Southwest Badger R C & D: Southwest Badger R C & D 2019 Cbcw: Southwest Badger R C & D is sponsoring a Clean Boats Clean Waters project in 2019 at 4 single public boat landings and 1 public boat landing pairs on LAKE WISCONSIN (MOON VALLEY), BECKMAN LAKE(CADIZ SPRINGS), YELLOWSTONE LAKE (MAIN LAUNCH), GOVERNOR DODGE (COX HOLLOW, TWIN VALLEY), BLACKHAWK LAKE (MAIN LAUNCH).


Grant Details
Clean Boats, Clean Waters
Date
2/15/2019
Waters Involved
Wisconsin River
Status
Complete

Southwest Badger R C & D: Southwest Badger R C & D 2019 Cbcw: Southwest Badger R C & D is sponsoring a Clean Boats Clean Waters project in 2019 at 4 single public boat landings and 1 public boat landing pairs on LAKE WISCONSIN (MOON VALLEY), BECKMAN LAKE(CADIZ SPRINGS), YELLOWSTONE LAKE (MAIN LAUNCH), GOVERNOR DODGE (COX HOLLOW, TWIN VALLEY), BLACKHAWK LAKE (MAIN LAUNCH).


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Barbian Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Bass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Brandenburg Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Acq-Cherokee Marsh Land Acquisition: Dane County proposes to acquire approximately 110 acres of land as an addition to Cherokee Marsh for low impact recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Cherokee Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Crystal Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Dell Creek
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Delton Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2001
Waters Involved
Devils Lake
Status
Complete

Friends Of Devil'S Lake State Park: Res-Of Devil'S Lake By Bottom Water Withdrawl: Friends of Devil's Lake State Park, Inc. will construct and begin operating a siphon pipe system for the purpose of withdrawing P-rich bottom water from Devil's Lake over approximately a 15-year period.

A full description of the project scope and project deliverables is available in the grant application, which is a part of this aggreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant appllication.


Grant Details
Lake Protection Grant
Date
9/1/2009
Waters Involved
Devils Lake
Status
Complete

Friends Of Devil'S Lake State Park: Lmi-Devil'S Lake Bottom Withdrawal Pipe Alterations: The Friends of Devil's Lake State Park propose this project to reconstruct the siphon pipe system at Devil's Lake State Park, Sauk County, by lowering the portion of the siphon that is above the ordinary high water mark (OHWM) lake level so that the pipe will flow as a gravity feed flow system whenever the lake level is above the OHWM. This entails digging up about 900' of the pipe, and lowering the highest point. An additional butterfly flow valve will be installed to provide control of the pipe for safety and operational purposes. Deliverables of this project will be a brief final report documenting that the project was completed, including photos of the project during construction.

Special condition: The Sponsor agrees to abide by the "Conditions of Approval" contained in the Chapter 30 Regulated Activities manual code approval issued by the Department of Natural Resources on 6/6/06.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Diedrich Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Dutch Hollow Creek
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Dutch Hollow Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
10/1/1999
Waters Involved
Fish Lake
Status
Complete

Natural Heritage Land Trust: Acq-Fish Lake Conservation Project: This grant will provide financial assistance for the acquisition of approximately 117 acres along Fish Lake, including approximately 1,600 feet of lakeshore frontage.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fish Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2006
Waters Involved
Fish Lake
Status
Complete

Dane County Parks: Acq-Fish And Mud Lakes-Marx Acquisition: The Marx property has already been purchased by Dane County. The property will protect the majority of the Mud Lake shoreline, which is connected to Fish Lake, a very important resource in NW Dane County. This land is adjacent to other property already purchased by the County. In five years, the property will be converted from row cropping to natural drainage patterns and natural vegetation to encourage wildlife and promote water quality benefits.


Grant Details
Lake Protection Grant
Date
4/15/2016
Waters Involved
Fish Lake
Status
Complete

Dane County: Acq-Porter Land Acq Dane Co T. Roxbury: Dane County will acquire approximately a 1/2 acre of land located on the west shore of Fish Lake in the Town of Roxbury, Dane County. The acquisition will permanently protect 73 feet of shoreline and fishery ecosystem for wildlife and scenic beauty, remove another residential property from an ongoing flooding threat at Fish Lake and integrate this parcel with other County-owned parcels. Eligible costs include acquisition of the parcels, appraisal fees and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Fishers Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Goose Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Graber Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Grass Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Hook Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/1997
Waters Involved
Indian Lake
Status
Complete

Dane County: Acq-Indian Lake - Matz Acquisition: Dane County Parks will acquire 40.23 acres located adjacent to Indian Lake. The acquisition will prevent land use development and maintain a buffer of upland and wetland to filter contaminants from entering Indian Lake. The property also contains wetlands and springs that feed Indian Lake.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Indian Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Island Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Kalscheur Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Barney
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Belle View
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Harriett
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2002
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Acq-Ladd Property Acquisition: Dane County will purchase 80 acres of wetlands (The Ladd Property) in the Town of Dunn along the Door Creek Wetlands in order to preserve wildlife habitat and water quality.

A full description of the project scope and project deliverables is available in the grant application, which is a part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant appllication.


Grant Details
Lake Protection Grant
Date
9/1/2002
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Acq-Wheeler Property Acquisition: Dane County will purchase 20 acres fee acquisition of wetlands (The Wheeler Property) in the Town of Dunn along the Door Creek Wetlands in order to preserve wildlife habitat and water quality.

A full description of the project scope and project deliverables is available in the grant application, which is a part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant appllication.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Acq-Door Crk Wetlands-Bruns/Amundson Acq: Dane County Parks Department is seeking funding for acquisition of the Bruns/Amundson Property in order to acquire 19 acres of land. Acquisition of this land will protect property immediately adjacent to other county and town owned lands. This is part of a parcel of land owned Richard Amundson and Ernie Brun.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Parks: Acq-Vogts Acquisition - Door Creek Wetlands: Acquisition of the Vogts property will meet objectives of the Door Creek Wetlands Resource Protection Plan. This acquisition and the planned restoration of the wetland are expected to improve spawning habitat for northern pike in Lake Kegonsa and better control stormwater and run-off pollution entering Lake Kegonsa from Door Creek.

A full description of deliverables is included in the grant application, which is a part of this agreement.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Kegonsa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Koshkonong
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/1997
Waters Involved
Lake Mendota
Status
Complete

City Of Middleton: Lmi-Pheasant Branch Watershed - In Lake Mendota Priority Watersh: The City of Middleton will contract with the U.S. Geological Survey to monitor and model the surface and groundwater flow within a portion of the Pheasant Branch watershed to locate effective combination of storm water treatment and control sites within the North Fork to mitigate the impacts of urbanization on the quality and quantity of water reaching Lake Mendota. Activities of the project include developing a surface and groundwater model based on existing data, collecting various field data for model inputs (including monitoring precipitation and flow discharge) refine the model and calibrate it to field measurements, calculate present and future pollution loads, and conduct analyses to accomplish the project objectives. Deliverables include: a report summarizing the project work, results and recommendations, maps showing recharge areas, hydrologfical sensitive sites, and the final calibrated computer model.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Mendota
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Monona
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Lake Redstone
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Waubesa
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wingra
Status
Complete

Dane County: Res-Lake Wingra Shoreline Habitat Restoration: The Dane County Land Conservation Department will implement a Lake Wingra Shoreline Habitat Restoration project in order to restore native species and natural habitats, to control exotic and invasive speies that threaten native species and habitats and to reduce the impacts of stormwater runoff on Lake Wingra's water quality. Project deliverables include: creation of a natural vegetation buffer along 500 feet of the lake's shoreline, installing a carp removal exclosure and purple loosestrife and buckthorn control.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Lake Wingra
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Lake Wisconsin
Status
Complete

Town Of Lodi: Acq-Lake Wisconsin Okee Community Park Land Acquisition: The Town of Lodi proposes to acquire 8.5 acres of land in the Okee Bay area of Lake Wisconsin for recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Lake Wisconsin
Status
Complete

Town Of Merrimac: Acq-Clingman Property Land Acquisition: The Town of Merrimac will purchase the Clingman Property on Lake Wisconsin in the County of Sauk (approx. 15.1 acres). The Town of Merrimac will comply with the approved Regional Management Plan.


Grant Details
Lake Protection Grant
Date
4/15/2020
Waters Involved
Lake Wisconsin
Status
Complete

Town Of Dekorra: Res-Tipperary Road Shoreline Protection: Project final deliverables include: a project summary with dates and photos of the site before and after the project. Report will include a copy of informational brochures, and copies of agendas of Town Board meetings that include updates on this project.

Specific project activities include: 1) Remove failing retaining wall, stairs, storm sewer outfall, and pier, 2) regrade the existing steeply sloped shoreline to a 30-40% slope, install erosion matting, 3) plant native shrubs and understory plants, and weed, water and do supplemental plantings in year 1 and 2, 4) install riprap on shoreline, and 5) provide project information to public via brochures and presentations at Town Board meetings.

Special Conditions: No permit is needed so the budget was reduced by $1000.00

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.

If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Lake Wisconsin
Status
Complete

Columbia County: Hlr - Okee Bay Native Plantings: Partnering with property owners,Columbia County LWC is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Lake Wisconsin
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maher Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Marshall Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Maunesha Flowage
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Meier Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Mirror Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Morse Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mortenson Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
10/8/1996
Waters Involved
Mud Lake
Status
Complete

Dane County: Acq-Dane County Lower Mud Lake Affholder Acquisition: Dane County shall participate in the Lake Protection Grant Program by purchasing 95 acres of land for public outdoor recreation.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Mud Lake
Status
Complete

Dane County: Acq-Marcus Marx Property Acquisition: Dane County Parks Department will acquire 58 acres of land adjacent to Mud Lake in the Town of Roxbury in order to restore native vegetation and provide a permanent buffer that will filter upstream runoff before it enters Mud Lake and Fish Lakes. The acquisition of this property will protect the land and the waters from further degradation.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2008
Waters Involved
Park Lake
Status
Complete

Columbia County: Lmi-Tmdl Development-Phase Ii-Park Lake: Columbia County Land and Water Conservation Department will conduct phase 2 of its TMDL development program for Park Lake. This phase will focus on continued monitoring along with the use of a graduate student to conduct water quality modeling to allow for final development of a TMDL for Park Lake, a 303(d) listed lake. The objectives of this study are to quantify P export from the watershed, and link water quality with nutrient loss from the land. Project deliverables include 1) monitoring of wetland effectiveness by measuring upstream and downstream flow and concentration; 2) Field-scale Snap-Plus and watershed-scale modeling; 3) simulating water quality changes caused by wetlands in this watershed using Army Corp PRE-WET model; 4) continuation of water quality monitoring/data collection along with targeting water sample collection adjacent to wetlands; 5) information/education efforts throughout project; and 6) compilation, documentation, and recommendations of findings. Education efforts include a news release, providing updates and final presentation through regular and annual meetings of the Lake District.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rice Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Rockdale Millpond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Seeley Creek
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Seeley Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Shannahan Valley Creek
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Springfield Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
1/24/1997
Waters Involved
Stewart Lake
Status
Complete

Dane County: Lmi-Stewart Lake Water And Sediment Control Basins: Dane County Proposes to construct 5 storm water detention basins to reduce the amount of sediment entering Stewart Lake.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stewart Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Strickers Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Tiedemans Pond
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Token Creek
Status
Complete

Dane County: Acq-Cherokee Marsh Land Acquisition: Dane County proposes to acquire approximately 110 acres of land as an addition to Cherokee Marsh for low impact recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
3/2/1994
Waters Involved
Unnamed
Status
Complete

Dane County: Acq-Pheasant Branch Marsh - Frederick Acquisition: Dane County will acquire approximately 161 acres of land within the Pheasant Branch Marsh for lake protection and public outdoor recreation purposes. Amendment 1: The scope is changed to reflect a change of acreage to 100.5 acres.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Unnamed
Status
Complete

Dane County: Acq-Cherokee Marsh Land Acquisition: Dane County proposes to acquire approximately 110 acres of land as an addition to Cherokee Marsh for low impact recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County Parks: Aulik Acquisition-Patrick Marsh: Dane County will acquire acreage within Patrick Marsh, a DNR and Dane County project area that is identified in both the Land Legacy Report and the Dane County Parks and Open Space Plan. The Aulik property is approximately 11.6 acres along the southern shore of Patrick Marsh. The acquisition of this property will protect and enhance this natural resource site.


Grant Details
Lake Protection Grant
Date
4/1/2015
Waters Involved
Unnamed
Status
Complete

Village Of Mazomanie: Lmi-Lake Marion Family Recreational Fishery: The Village of Mazomanie will complete a large, multi-faceted lake restoration project on Lake Marion by installing an access sign at the boat landing, installing an aeration system, stocking fish, placing habitat structures on the bed, and reconfiguring and restoring large lengths of shoreline consistent with department recommendations. The boat landing access sign will explicitly reflect the Village ordinance allowing non-motorized boat use of the lake. Current steep shorelines will be graded to provide a healthy diversity of habitat, dead trees will be introduced and anchored to shore, and trees, shrubs and understory natives will be planted. Water quality will be monitored to track lake improvements. Project updates will be shared via social media, press releases, public meetings, and community volunteer workdays and celebration. Final report and other deliverables are detailed in the grant application form.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Upper Mud Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Virgin Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Virginia Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
White Mound Lake
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
9/1/2003
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane Cnty Lk & Stream Classification: Dane County Department of Planning and Development will hire a project staff in order to develop a Lake Classification project, which is seen as the first step toward developing a consistent set of county-wide standards and procedures to protect Dane County Waters. Project deliverables include:a written report describing the Dane County Water Body Classification System, a bibliography of research sources, a list of navigable water bodies in Dane County sorted according to classification, and a map and GIS layer showing classified water bodies.

A full description of the project scope and project deliverables is in the grant application, which is a part of this agreement. The DNR will be provided with a final report on the results of this project. Information will be disseminated to the public as described in the grant application.


Grant Details
Lake Protection Grant
Date
9/1/2005
Waters Involved
Windsor Lake
Status
Complete

Dane County Dept. Of Planning & Dev: Lco-Dane County Lake Classification - Phase 2: Dane County Lake Classification-Phase 2: The Phase 1 classification grant classified all county lakes and streams. This grant will take the next step by developing a management program based on the classification.

Detailed goals, methods and deliverables are outlined in the application.


Grant Details
Lake Protection Grant
Date
4/15/2020
Waters Involved
Wisconsin River
Status
Complete

Town Of Dekorra: Res-Tipperary Road Shoreline Protection: Project final deliverables include: a project summary with dates and photos of the site before and after the project. Report will include a copy of informational brochures, and copies of agendas of Town Board meetings that include updates on this project.

Specific project activities include: 1) Remove failing retaining wall, stairs, storm sewer outfall, and pier, 2) regrade the existing steeply sloped shoreline to a 30-40% slope, install erosion matting, 3) plant native shrubs and understory plants, and weed, water and do supplemental plantings in year 1 and 2, 4) install riprap on shoreline, and 5) provide project information to public via brochures and presentations at Town Board meetings.

Special Conditions: No permit is needed so the budget was reduced by $1000.00

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.

If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Wisconsin River
Status
Complete

Columbia County: Hlr - Okee Bay Native Plantings: Partnering with property owners,Columbia County LWC is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
3/15/2024
Waters Involved
Wisconsin River
Status
Complete

Sauk County: Hlr - Sauk County Healthy Lakes & Rivers 2024: Partnering with property owners, Sauk County is sponsoring a grant to implement best practices from Wisconsin\2019s 2019 Healthy Lakes & Rivers Action Plan. Best practices, including fish sticks, 350 sq. ft. native plantings, diversions, rock infiltration, and/or rain gardens, will be designed and installed according to program fact sheets, technical guidance and the grant application.
All funded best practices require contracts that must remain in place for 10 years and include the minimum operation and maintenance requirements described in the special conditions at the end of this agreement. If the landowner is the grant sponsor this Lake Protection Grant Agreement serves as the contract. If the best practice(s) will be implemented on land other than the sponsor\2019s, a contract between the sponsor and landowner describing the 10-year contract period, minimum operation and maintenance details, and data to be collected is required. The Department may perform site inspections and/or monitoring to ensure project success.
Deliverables include: a project summary including data requirements, pre/post photographs, and confirmation of completed design work and landowner contracts. A Healthy Lakes & Rivers Example Report is available to assist you.
Special conditions: Project management and technical assistance cash costs cannot exceed 10% of the state share of the grant award; this does not include implementation labor. Water regulation and/or county zoning permits must be issued before construction. Projects required for regulatory compliance purposes, including shoreland mitigation projects, are not eligible for reimbursement. The Healthy Lakes & Rivers logo should be used for promotion and publicity and DNR recognized as a funding source.
The grantee may request a one-time cost amendment and a one-time time extension. The grantee must notify the department if they wish to add or subtract practices to the scope of this grant agreement.


Grant Details
Lake Protection Grant
Date
5/25/1995
Waters Involved
Yahara River
Status
Complete

Dane County: Acq-Cherokee Marsh Land Acquisition: Dane County proposes to acquire approximately 110 acres of land as an addition to Cherokee Marsh for low impact recreational opportunities and lake protection. Eligible costs include acquisition of the parcel, appraisal fee and preparation of an environmental assessment.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Castle Rock Ditch
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Cruson Slough
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Crystal Lake
Status
Complete

Dane County: Crystal Lake Hydrologic Study: The objectives of this project are to: 1) Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Crystal, Fish, and Mud Lakes by simulating measured lake stage, groundwater elevation, and local stream flow. 2) Predict the possible effect of pumping water from Fish Lake on Crystal Lake stage.

A full description of project scope and product deliverables is available in the grant application, which is part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Crystal Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Crystal Lake
Status
Complete

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
12/20/1990
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Hydrology And Phosphorus Loading Evaluation: 1) Evaluate Fish Lake's hydrology and phophorus loading by lake stage and precipitation monitoring, estimation of surface runoff and lake evaporation, determination of groundwater flow, analysis of storm run-off, surface run-off, gorundwate, andprecipitation for total phosphorus; estimation of septic system outputs.


Grant Details
Large Scale Lake Planning
Date
10/11/1991
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Usgs Hydrology And Phosphorus Loading Assessment: Data analysis and preparation of hydrologic and nutrient budget needed for diagnostic and feasibility study as described in the project proposal.Make management recommendations to improve lake water quality.Publish all data in USGS's annual data report 'Water Resources Data for Wisconsin'.Information will be disseminated to the public by newsletter, fact sheet, public meetings, summary report, and local newspaper articles.The final report will be reposited in Dane County libraries, the City-County Building, and the Roxbury Town Hall.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Hydrologic Study: The objectives of this project are to: 1) Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Fish, Crystal, and Mud Lakes by simulating measured lake stage, groundwater elevation, and local stream flow.

A full description of project scope and product deliverables is available in the grant application, which is part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Fish Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Fish Lake
Status
Proposed

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Lake Du Bay
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Lake Wisconsin Harmony Grove Sediment Study: This project will investigate sediment in the Harmony Grove lagoons. The quantity of sediment will be determined through field measurements in the lagoons. Sediment samples will be collected and analyzed. Options for removal and disposal of the sediment will identified along with the costs associated with these options. Sediment inputs to the lagoons will also be evaluated and recommendations made to minimize future sedimentation. The information gathered in this study will be used to determine the need for future study or actions to support a lake management plan to protect the long term viability of the lagoons as a natural resource for fisheries and public recreation.

A full description of project scope and project deliverables is available in the grant application, which is a part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
10/1/1999
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Lake Wisconsin Harmony Grove Water Quality: Harmony Grove Lake Protection and Rehabilitation District will investigate water quality of the Harmony Grove lagoons. It will collect water quality data from the lagoons and Lake Wisconsin over a one year period. The impact of ground water flow to the lagoons will be determined. Pollution sources to the lagoons from the watershed will be identified and quantified. Recommendations will then be made to minimize the pollutant sources to the lagoons.

A full description of project scope and project deliverables is available in the grant application, which is part of this agreement.

The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Lake Wisconsin
Status
Complete

Harmony Grove Lake Prot. And Rehab. District: Apm & Sediment Management Plan For Harmony Grove Lake: The Harmony Grove Lake Protection and Rehabilitation District will monitor plants and sediments, summarize feasibility of all management options, and make recommendations for improving water quality.

A full description of project scope and deliverables is available in the grant application, which is part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be disseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2005
Waters Involved
Lake Wisconsin
Status
Complete

Town Of West Point: Lake Wisconsin Organization Development And Town Of West Point Land Use Study: The West Point Township will explore land use planning options to preserve sensitive habitat and rural character of township, build partnerships, and begin collecting baseline data of local subwatershed, water quality and critical habitat.

A full description of project scope and deliverables is available in the grant application, which is part of this agreement. The DNR will be provided with both a paper copy and an electronic copy of the final report. Information will be desseminated to the public as described in the grant application.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Little Pine Creek
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2001
Waters Involved
Mud Lake
Status
Complete

Dane County: Groundwater Lake Interactions - Crystal, Fish, Mud Lakes: This project will complete the work begun in projects LPL-666 and LPL-652 to: Demonstrate an understanding of the hydrology of lake/groundwater system in the vicinity of Crystal, Fish, and Mud lakes by simulating measured lake stage, groundwater elevation, and local stream flow; and predict the possible effect of pumping water from Fish Lake on Crystal Lake stage.

A full description of the project scope and deliverables is available in the grant application, which is part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Mud Lake
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Mud Lake
Status
Proposed

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2005
Waters Involved
Unnamed
Status
Complete

Dane County: Preparation Of Apm Plans--Lower Mud, Fish, Crystal, Wingra & Indian Lakes: Aquatic plant and substrate surveys will be conducted, followed by evaluation of changes over time to develop or modify APM plans for these waters.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Unnamed
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Large Scale Lake Planning
Date
4/1/2013
Waters Involved
Unnamed
Status
Complete

Dane County: Assessment Of Wq & Nearshore Fish Populations In Fish, Crystal And Mud Lakes: Dane County intends to sample water quality, algae, and near-shore fish populations, Fish, Mud and Crystal Lakes in northern Dane County. Baseline data are needed to help develop recreational use plans for a new county park in the area, and to document changes that have occurred since the lakes have been flooded since 2006 due to rising groundwater. The sampling frequency and protocol will also allow DNR partners to assess the lakes for possible 303d listing. Mud Lake will also be sampled for aquatic plants as a baseline inventory, as well as carp. The County will evaluate the possibility of doing carp control to help restore aquatic plants and cleaner water for the fishery. A final report including methods, findings and recommendations will be created and will be shared with District partners, the media and the DNR.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
10/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Comprehensive Rainfall Runoff Model For The Yahara River System: The Comprehensive Rainfall Runoff Model for the Yahara River System project will result in a comprehensive rainfall runoff model for the Yahara River System that will enable improved system management and enhance lake biota and recreation values. The model will be used to better manage lake levels, provide flood protection benefits, and enhance aquatic resources in the Yahara River and associated lakes and wetlands.

A full description of this project and its deliverables is available in the grant application, which is a part of this agreement.


Grant Details
Large Scale Lake Planning
Date
4/1/2010
Waters Involved
Wisconsin River
Status
Complete

Lake Alice Association, Inc: Lake Alice Stewardship Program Phase Ii - Understanding The Biota Of Lake Alice: Lake Alice Association is sponsoring phased large scale lake planning grants to study Lake Alice, in Lincoln County. The project will focus on developing and updating an Adaptive Lake Management Plan (LMP) for Lake Alice. Phase 2 was funded in this grant cycle and Phases 3-5 will be submitted for funding starting in 2011.

Project activities for Phase 2 include: 1) Educational program, meetings and educational events with lake association and Tomahawk High School students, written educational materials, news releases, and website updates; 2) Point-intercept (PI) aquatic plant survey; 3) Aquatic plant community and substrate mapping; 4) Water quality assessment; 5) Volunteer amphibian monitoring and angler survey; 6) Update LMP.

Project deliverables include: 1) Educational materials and news releases; 2) Aquatic plant community and substrate maps; 3) PI, water quality, amphibian, and angler data; 4) LMP.

Specific conditions for this project: LMP needs Dept review and approval

WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) and hard copy of LMP, news releases, any other educational materials/products, all data, all maps from project, and all GIS data.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Barbian Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Bass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Brandenburg Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Carl Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Cherokee Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Crystal Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
2/15/2015
Waters Involved
Crystal Lake
Status
Complete

Dane County: Crystal Lake Water Level Monitoring Station: Dane County is sponsoring a project to install a water level monitoring station on Crystal Lake, Dane County. This will provide useful data for lake water budgets to assist with management of the pump located on this lake.

Project final deliverables include: The station will be installed, and graphs of real-time data will be available for viewing by the public online. In addition, a report and website link for the data will be provided to DNR as a deliverable.

Specific project activities include: Installing a water level monitoring station at the lake, setting up the computer programming, and a resulting website display.

Special Conditions: Not applicable.

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.

If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Diedrich Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fish Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
2/15/2016
Waters Involved
Fish Lake
Status
Complete

Dane County: Fish Lake Water Level Monitoring Station: Dane County is sponsoring a project to install a water level monitoring station on Fish Lake, Dane County. This will provide useful data for lake water budgets to assist with management of the pump located on nearby Crystal Lake, which is hydrologically connected via groundwater.

Project final deliverables include: The station will be installed, and graphs of real-time data will be available for viewing by the public online. In addition, a report and website link for the data will be provided to DNR as a deliverable.

Specific project activities include: Installing a water level monitoring station at the lake, setting up the computer programming, and a resulting website display.

Special Conditions: Not applicable.

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.

If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.



Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Fishers Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Goose Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Graber Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Grass Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Hook Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Indian Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Island Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Kalscheur Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Barney
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Belle View
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Harriett
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Kegonsa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Koshkonong
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Mendota
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Monona
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Waubesa
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Lake Wingra
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2013
Waters Involved
Lake Wisconsin
Status
Complete

Columbia County: Lake Wisconsin Access Inventory: Lake Wisconsin Access Inventory \2013 Columbia County LWCD will conduct a public access survey on the Columbia County side of Lake Wisconsin to help the public better use these areas and to help identify infrastructure needs, in addition to preparing for an eventual lake management plan that would include aquatic invasive species prevention component. After collecting property deed information, each public access site would be photographed, and a variety of parameters documented, including things like fire number, driving directions to the site, parking surface and number of spaces, signs posted, survey markers present, topography, etc. The data will be entered into a GEO database, and a final report will be presented to stakeholders.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Louis Buechner Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maher Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Marshall Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Maunesha Flowage
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Meier Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Morse Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mortenson Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rice Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Rockdale Millpond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Salmo Pond (Raemisch Pond)
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Springfield Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stebbinsville Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stewart Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Stoughton Millpond 429
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Strickers Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tenney Park Lagoon
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Tiedemans Pond
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Unnamed
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
2/15/2015
Waters Involved
Unnamed
Status
Complete

Dane County: Crystal Lake Water Level Monitoring Station: Dane County is sponsoring a project to install a water level monitoring station on Crystal Lake, Dane County. This will provide useful data for lake water budgets to assist with management of the pump located on this lake.

Project final deliverables include: The station will be installed, and graphs of real-time data will be available for viewing by the public online. In addition, a report and website link for the data will be provided to DNR as a deliverable.

Specific project activities include: Installing a water level monitoring station at the lake, setting up the computer programming, and a resulting website display.

Special Conditions: Not applicable.

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.

If consultant is to provide final report, it is recommended that Grantee provide DNR Lake Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Upper Mud Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Verona Gravel Pit
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Virgin Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: Dane County Workshop For Local Resource Groups: Dane County will use this grant to provide a local workshop for networking between local resource protection groups. This networking would allow sharing of information and strategies for resource protection, strengthen relationships and create new ones, and continue to collaborate on county-wide lake and watershed protection and improvement issues. This project will also involve printing an in-depth "State of Dane County Waters" document.

The deliverable will be evidence that the workshop was planned, evidence that groups participated in the event, and 2500 copies of the in-depth "State of Dane County Waters" document.


Grant Details
Small Scale Lake Planning
Date
4/1/2004
Waters Involved
Windsor Lake
Status
Complete

Dane County: State Of The Waters' Publication: Dane County will use this grant to complete and publish a popularized"State of Dane County Waters" brochure. Draft documents will be reviewed by DNR staff and others.

The deliverable will be the comprehensive documents.


Grant Details
Small Scale Lake Planning
Date
4/1/2013
Waters Involved
Wisconsin River
Status
Complete

Columbia County: Lake Wisconsin Access Inventory: Lake Wisconsin Access Inventory \2013 Columbia County LWCD will conduct a public access survey on the Columbia County side of Lake Wisconsin to help the public better use these areas and to help identify infrastructure needs, in addition to preparing for an eventual lake management plan that would include aquatic invasive species prevention component. After collecting property deed information, each public access site would be photographed, and a variety of parameters documented, including things like fire number, driving directions to the site, parking surface and number of spaces, signs posted, survey markers present, topography, etc. The data will be entered into a GEO database, and a final report will be presented to stakeholders.


Grant Details
Targeted Runoff - Rural Construction
Date
4/1/2006
Waters Involved
German Valley Br
Status
Complete

Dane County Land Conservation Dept: German Valley Creek Middle: To cost-share installation of streambank restoration and protection practices designed to prevent unlimited livestock access to waters of the state.


Grant Details
Targeted Runoff - Rural Construction
Date
4/1/2006
Waters Involved
German Valley Br
Status
Complete

Dane County: German Valley North: Installation of streambank restoration/protection practices, to include: Riprap, rock weirs, shaping & seeding, critical area stabilization, and lunkers along approximately 14,000 feet of German Valley Creek north of grantee's 2004 project.


Grant Details
Targeted Runoff - Rural Construction
Date
4/1/2006
Waters Involved
German Valley Br
Status
Complete

Dane County: German Valley South: to costshare at 70% streambank rehabilitation within the southern segment of German Valley Creek


Grant Details
Total Maximum Daily Load
Date
4/1/2006
Waters Involved
German Valley Br
Status
Complete

Dane County Land Conservation Dept: German Valley Creek Middle: To cost-share installation of streambank restoration and protection practices designed to prevent unlimited livestock access to waters of the state.


Grant Details
Urban Nonpoint - Stormwater Construction
Date
1/1/2015
Waters Involved
Lake Monona
Status
Complete

City Of Monona: Storm Water Treatment Devices: This grant provides funding and authorizes cost-share reimbursement by the department for the above-named project as described in the grant application submitted for calendar year 2015 for the eligible storm water construction activities listed in the application to address nonpoint sources of pollution. The cost-share reimbursement rate will be up to 18% of the actual eligible project costs, to the maximum amount contained in Part 2.


Grant Details
River Planning Grant
Date
2/15/2015
Waters Involved
Lake Wisconsin
Status
Complete

Lake Wisconsin Alliance: Education And Awareness: Lake Wisconsin Alliance will undertake a River Planning Grant project that will expand outreach and education of Lake Wisconsin natural and recreational resources, and lake water quality issues. The goal is to increase membership, provide identity to the LWA, and inform citizens living within the Lake Wisconsin watershed.
Deliverables: 1. The Lake Wisconsin Alliance technical advisory team will provide action items to LWA members to help attain goals and objectives to protect and enhance L. Wisconsin. 2. Communicate the LWA mission and organizational roles through brochures and website development. 3. Develop a logo to give the alliance identity. 4. Website membership development to assist in expansion of membership, and develop a calendar of activites hosted by the alliance. 5. Host workshops and seminars to educate the public on lake water quality and strategies that help protect/enhance lake water quality.


Grant Details
River Planning Grant
Date
2/15/2019
Waters Involved
Lake Wisconsin
Status
Complete

Lake Wisconsin Alliance: Lake Wisconsin Property Owners Survey: Scope of Work:

The Lake Wisconsin Alliance (LWA) will:

1) With the assistance of the Survey Research Center at the University of Wisconsin-River Falls, develop a survey specific to include resident\2019s perceptions of the lake; involvement in the LWA; services LWA could provide; and resident\2019s lake management practices.

2) Mail the survey to the 1500+ residents of Lake Wisconsin and promote response to the survey through a variety of mailings, meetings, and contacts.

3) Analyze and report on the results of the survey by December 31, 2019.


Grant Details
River Planning Grant
Date
3/15/2023
Waters Involved
Unnamed
Status
Complete

Friends Of The Lower Wi Riverway (Flow): Swe - Lower Wisconsin River Basin Symposium: Friends of the Lower Wisconsin Riverway (FLOW) is sponsoring a project to hold a Lower Wisconsin River Basin Symposium in 2023.

Project final deliverables include:

Press releases and articles about the event will be copied for inclusion in the final report. The meeting agenda and program will be included, along with a list of land/watershed conservation organizations. A final symposium report will include information on symposium attendance, attendee survey rating responses and comments on the success or limitations of the symposium. The report will also include a compilation of presentations summaries/abstracts. Photographs of the event will be delivered with the final report and include file names and attribution information.

Specific project activities include:

FLOW will plan a one day educational symposium in fall of 2023, to include technical - scientific presentations and citizen - organization watershed restoration and aquatic monitoring presentations. To give greater understanding of the connection between land and water quality, land/waterway restoration strategies for wetland and water quality improvement, and inform people about the unique biological, physical and cultural features of the LWR Basin. A web page will promote the event and invitations will be sent to NGO's, NRCS and LWCD in the basin.

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Stream Biologist.


Grant Details
River Planning Grant
Date
7/1/2004
Waters Involved
Wisconsin River
Status
Complete

Sauk Prairie River Projects Assoc. Ltd: Wisconsin River Restoration: Sauk Prairie River Projects Association LTD will organize existing groups, clubs, and organizations and will work with local and state agencies in order to develop a plan for the project area. That plan will involve local groups in understanding and protecting: river natural resources and features, the positive impact of these resources on the local economy, and the importance of river access and recreational opportunities. A full description of the project goals, objectives, methods, activities, products and deliverables is included in the grant application, which is a part of this grant contract.


Grant Details
River Planning Grant
Date
2/15/2015
Waters Involved
Wisconsin River
Status
Complete

Lake Wisconsin Alliance: Education And Awareness: Lake Wisconsin Alliance will undertake a River Planning Grant project that will expand outreach and education of Lake Wisconsin natural and recreational resources, and lake water quality issues. The goal is to increase membership, provide identity to the LWA, and inform citizens living within the Lake Wisconsin watershed.
Deliverables: 1. The Lake Wisconsin Alliance technical advisory team will provide action items to LWA members to help attain goals and objectives to protect and enhance L. Wisconsin. 2. Communicate the LWA mission and organizational roles through brochures and website development. 3. Develop a logo to give the alliance identity. 4. Website membership development to assist in expansion of membership, and develop a calendar of activites hosted by the alliance. 5. Host workshops and seminars to educate the public on lake water quality and strategies that help protect/enhance lake water quality.


Grant Details
River Planning Grant
Date
2/15/2019
Waters Involved
Wisconsin River
Status
Complete

Lake Wisconsin Alliance: Lake Wisconsin Property Owners Survey: Scope of Work:

The Lake Wisconsin Alliance (LWA) will:

1) With the assistance of the Survey Research Center at the University of Wisconsin-River Falls, develop a survey specific to include resident\2019s perceptions of the lake; involvement in the LWA; services LWA could provide; and resident\2019s lake management practices.

2) Mail the survey to the 1500+ residents of Lake Wisconsin and promote response to the survey through a variety of mailings, meetings, and contacts.

3) Analyze and report on the results of the survey by December 31, 2019.


Grant Details
River Planning Grant
Date
3/15/2023
Waters Involved
Wisconsin River
Status
Complete

Friends Of The Lower Wi Riverway (Flow): Swe - Lower Wisconsin River Basin Symposium: Friends of the Lower Wisconsin Riverway (FLOW) is sponsoring a project to hold a Lower Wisconsin River Basin Symposium in 2023.

Project final deliverables include:

Press releases and articles about the event will be copied for inclusion in the final report. The meeting agenda and program will be included, along with a list of land/watershed conservation organizations. A final symposium report will include information on symposium attendance, attendee survey rating responses and comments on the success or limitations of the symposium. The report will also include a compilation of presentations summaries/abstracts. Photographs of the event will be delivered with the final report and include file names and attribution information.

Specific project activities include:

FLOW will plan a one day educational symposium in fall of 2023, to include technical - scientific presentations and citizen - organization watershed restoration and aquatic monitoring presentations. To give greater understanding of the connection between land and water quality, land/waterway restoration strategies for wetland and water quality improvement, and inform people about the unique biological, physical and cultural features of the LWR Basin. A web page will promote the event and invitations will be sent to NGO's, NRCS and LWCD in the basin.

This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Stream Biologist.


Monitoring & Projects

Projects including grants, restoration work and studies shown below have occurred in this watershed. Click the links below to read through the text. While these are not an exhaustive list of activities, they provide insight into the management activities happening in this watershed.

Grants and Management Projects
Roxbury Creek Watershed
Watershed Recommendations
Adaptive Management WQ Trading
Deerfield WWTF Adaptive Management Plan
Date
Status
AMP to achieve compliance with phosphorus water quality standards in accordance with s. NR 217.19, Wis. Adm. Code.
2/1/2019
In Progress
Projects
 
Best Management Practices, Implement
Columbia County TRM 2017
Date
Status
This project is a landowner installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the grantee will implement: a manure storage system, a barnyard runoff control system, critical area stabilization, roof runoff systems, a waste transfer system, wastewater treatment strips to remedy discharges of manure, sediment and phosphorus in runoff entering waters of the state and address the following NR 151 Agricultural Performance Standards and Prohibitions: sheet, rill, and wind erosion; manure storage facilities-new/significant alterations; process wastewater handling; clean water diversions; nutrient management; prevention of overflow from manure storage facilities; prevention of direct runoff from a feedlot or stored manure
1/1/2017
In Progress
Projects
 
Best Management Practices, Implement
Columbia County TRM 2017
Date
Status
This project is a landowner installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the grantee will implement: a manure storage system, a manure storage system closure, a barnyard runoff control system, critical area stabilization, diversions, heavy use area protection, roofing, roof runoff systems, a waste transfer system, wastewater treatment strips, relocation/abandonment of animal feeding operation, a milking center waste control system, and a feed storage runoff control system to remedy discharges of manure, sediment and phosphorus in runoff entering waters of the state and address the following NR 151 Agricultural Performance Standards and Prohibitions: sheet, rill, and wind erosion; process wastewater handling; clean water diversions; nutrient management; prevention of overflow from manure storage facilities; and prevention of direct runoff from a feedlot or stored manure.
1/1/2017
In Progress
Projects
 
Best Management Practices, Implement
Byrne Pond Retrofit
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the municipality will construct/install a bioretention for infiltration basin to remedy discharges of total suspended solids in urban runoff.
1/1/2017
In Progress
Projects
 
Best Management Practices, Implement
Deforest Storm Water Master Plan
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Storm water planning activities will be undertaken by the municipality and will result in the following products: updated construction erosion control ordinance, updated storm water ordinance for new development and re-development, updated low impact development/conservation subdivision ordinance, updated ordinances that affect runoff from the developed urban area, updated storm water financing mechanism, updated storm water management plan for the developed urban area, and updated storm water management plan for new development.
1/1/2016
In Progress
Projects
Documents
 
Best Management Practices, Implement
Middleton Storm Water Master Plan Update
Date
Status
This project promotes nonpoint source best management practices to contribute to the restoration of Wisconsin's waters and was funded by the 319 grant. Storm water planning activities will be undertaken by the municipality and will result in the following products: updated construction erosion control ordinance, updated storm water ordinance for new development and re-development, new ordinances that affect runoff from the developed urban area, updated ordinances that affect runoff from the developed urban area, new feasibility analysis of alternative funding mechanisms, updated storm water management plan for the developed urban area, and updated storm water management plan for new development.
1/1/2016
In Progress
Projects
Documents
 
Best Management Practices, Implement
Middleton Beach Road - Green Street Design
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin's waters and was funded by the 319 grant. Specifically, the grantee will implement: green street design.
1/1/2015
In Progress
Projects
 
Hire County Aquatic Invasives Coordinator
 
Date
Status
Hire Aquatic Invasives (AIS) County Coordinator - Columbia
1/1/2011
In Progress
Projects
 
Monitor Aquatic Biology
Marsh Creek (wbic: 1252900)
Date
Status
This water (1252900, Marsh Creek, AU: 13346) was assessed for the 2016 integrated reporting process and found to have clearly meeting total phosphorus but poor biology (either fish or macroinvertebrates) (see parameter assessment results). Follow up monitoring should be conducted to clarify the status of biology in the water.
7/30/2015
Proposed
Projects
 
Restore Riparian Habitat
2015 Pheasant Branch Streambank Rest. & Habitat Enhancement
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the grantee will implement: restoration and habitat enhancement.
1/1/2015
In Progress
Projects
Documents
 
Stormwater Planning, Implementation
Stormwater Pretreatment and Diversion to Manitou Pond
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin's waters and was funded by the 319 grant. The municipality will construct/install a proprietary storm water sedimentation device to remedy discharges of total suspended solids in urban runoff.
1/1/2017
In Progress
Projects
 
Stormwater Planning, Implementation
Stoughton - TMDL Storm Water Plan
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin's waters and was funded by the 319 grant. Storm water planning activities will be undertaken by the municipality and will result in the following products: updated construction erosion control ordinance, updated storm water ordinance for new development and re-development, updated ordinances that affect runoff from the developed urban area, updated storm water financing mechanism, updated storm water management plan for the developed urban area, and updated storm water management plan for new development.
1/1/2016
In Progress
Projects
Documents
 
Stormwater Planning, Implementation
Cross Plains - Storm Water Quality Management Plan
Date
Status
This project is an installation of nonpoint source best management practices to contribute to the restoration of Wisconsin?s waters and was funded by the 319 grant. Specifically, the grantee will implement: storm water quality management plan.
1/1/2015
In Progress
Projects
 
TMDL Implementation
Otter Creek (1237100) TMDL
Date
Status
Otter Creek is impaired due to degraded habitat because of excessive sediment loading from surrounding agricultural lands to the Creek. Otter Creek is currently not meeting the applicable narrative water quality standard (WQS) that prohibits objectionable deposits on the shore or in the bed of a water in amounts that interfere with public rights in the water. To address the degraded habitat impairments, Wisconsin Department of Natural Resources (WDNR) determined that sediment, specifically TSS, is the pollutant that must be addressed to attain designated uses and meet WQS.
9/22/2012
In Progress
Projects
Documents
 
TMDL Monitoring
Token Creek TMDL
Date
Status
Token Creek was approved and implemented in 1999. The Dam was removed and the stream restored.
7/1/2009
In Progress
Projects
Documents
 
Water Quality Planning
ARRA 18 CARPC Supplemental WQM Plan Funding
Date
Status
Supplemental funds for water quality planning in designated management areas; multi-agency watershed initiative to restore, protect, and maintain Yahara Watershed; contract with Capital Area Regional Planning Commission.
1/31/2010
In Progress
Projects
Documents
 
Watershed Mapping or Assessment
ARRA 18 CARPC Supplemental WQM Plan Funding
Date
Status
Supplemental funds for water quality planning in designated management areas; multi-agency watershed initiative to restore, protect, and maintain Yahara Watershed; contract with Capital Area Regional Planning Commission.
1/31/2010
In Progress
Projects
Documents
 
Roxbury Creek WatershedWatershed History Note

The Town of Roxbury is located in the Roxbury Creek Watershed. The town's growth was connected to the arrival of Agoston Haraszthy, a colorful nobleman and political refugee from Hungary. By 1841, he had purchased a large parcel of land where Sauk City now stands. He also built a hunting lodge, opposite his home, on a bluff in Roxbury overlooking the river. For the next several years, Haraszthy was active as a trader, hunter, steamboat operator, and viticulturist, and his business activities attracted attention to the area. He established a ferry that crossed the river, connecting Roxbury with Sauk City (then named "Haraszthy"). In 1841, Robert Richards and Jacob Fraelich, the ferry operators, became the first settlers in Roxbury after Haraszthy. Haraszthy's vineyards were located on a scenic hillside overlooking the Wisconsin River. Following several years of disappointment with winter damage on his vines and unfortunate politics, Haraszthy followed the gold rush west in 1849 and eventually became known as the founder of the California wine industry. Back in Roxbury, Peter Kehl took over the vineyards and planted conventional grape varieties, which he buried every year to protect them from Wisconsin's winters. The winery stayed in the family until 1899 when the farm was then converted to farm more conventional crops. But in 1972, the nearly abandoned property was purchased by the Wollersheim family who replanted the vines and brought the vineyards and wine business to a new level of success and national recognition.

Date  2011